Re:Why are nuclear power construction costs so high? Part II... by Spivak on Friday September 30, 2022 @04:44PM (#33040551)
So why don’t we have the US fricking navy actually run and manage the reactors? It’s not as if they only exist at sea. And if the reactors are actually wholly military operated we might get the added benefit of being able to use the Navy’s 20ish year lead on civilian nuclear. Amazing what you can learn when you have a navy nuclear engineer a few beers in and trying to impress you.
Re:Why are nuclear power construction costs so high? Part II... by dickholesalad on Friday September 30, 2022 @05:10PM (#33040858)
I’m an ex navy nuke (I did the whole thing, school through startups, sea trials, refuel, operations, maintenance, was nuke mechanic). I think some of the main impediments to adoption of navy-style training, operations, and maintenance in the civilian world are that the work is challenging and high stress. The school is very mentally and spiritually challenging to most people. When you get to the fleet the work is very challenging both mentally and physically. You are taking weekly technical short answer tests, operating the thing in 100F degrees doing legit physical work, responding to emergency stuff at 2 am before a 6 am shift. It’s nuts. The navy selects smart people through asvab test requirements. Most students are still challenged by the coursework. When you stay in by reenlisting it gets a little easier because you have less physical work to do but you still have to maintain excellence and train the junior people to the required competency level. Combine this with the fact that the pay is shitty compared to other jobs in industry available and the incentives just aren’t there. Where do we find these highly motivated, fit, young, intelligent people to work like dogs? They don’t exist in sufficient quantity to do this. The navy doesn’t have superior technology; most of the ships are old and maintained. The secret sauce is the personnel and their desperation. You aren’t going to contract people in the civillian world to do this stuff. I really don’t think it’s feasible.
Re:Why are nuclear power construction costs so high? Part II... by dqpb on Friday September 30, 2022 @05:30PM (#33041055)
> Combine this with the fact that the pay is shitty compared to other jobs in industry available and the incentives just aren’t there.

> Where do we find these highly motivated, fit, young, intelligent people to work like dogs?

We increase the pay. It's that simple.

Re:Why are nuclear power construction costs so high? Part II... by nradov on Friday September 30, 2022 @05:43PM (#33041184)
Thus killing the economics of nuclear power relative to competing sources. The Navy uses nuclear power on a few dozen carriers and submarines because that's the only practical way to accomplish the mission. But after building a handful of nuclear powered surface combatants they abandoned that approach, and returned to conventional engines largely for cost reasons. Civilian power plants have to find a way to operate at a profit.
Re:Why are nuclear power construction costs so high? Part II... by landemva on Friday September 30, 2022 @06:02PM (#33041378)
Personnel are a key ingredient for success. In civilian world for construction the regulatory environment is wildly different. Calls for Navy to run civilian nukes would likely not work with the civilian regulator.
Re:Why are nuclear power construction costs so high? Part II... by lifeisstillgood on Saturday October 01, 2022 @09:53AM (#33046593)
I get the "nuclear maintenance school is mentally challenging" ... but I am fascinated by spirtually challenging - could you elaborate?
Re:Why are nuclear power construction costs so high? Part II... by dickholesalad on Saturday October 01, 2022 @02:42PM (#33048895)
I can only speak for myself, although I would say I was pretty average as far as people who finished the school. My class had a fifty percent drop rate. Two people killed themselves that year. My good friend was the “petty officer of the watch” and found one of the people that jumped off of their second story common area balcony head first. The housing areas were named after ships so we made gallows humor jokes about them being in the xx diving squad. The school had zero cheating, a very fast pace, and very specific grading requirements. This led to a grade meritocracy that seemed gaussian in nature, distributed around a very specific skill set centered around quickly testing. Some people easily skated by. Others struggled. Some from both groups failed out. I think that seeing people be put into a meat grinder like that was more than I was prepared for. I believed in some kind of justice in the world, or at least in the man-made systems we created but didn’t encounter that. There is also the chance that everyone goes through experiences that change their outlook on life, but that was my lived experience. If you are interested there is a book that was passed around that tells it better: https://www.swm1.com/life%20in%20the%20nuclear%20navy.pdf I didn’t write it but it was pretty accurate and really funny IIRC.
Re:Why are nuclear power construction costs so high? Part II... by ok_dad on Friday September 30, 2022 @04:52PM (#33040626)
That only solves part of the problem, the civilian reactors are still too expensive to build. Nuclear is great, I went through the Naval Nuclear Power Program several decades ago myself, but it's not financially viable.

Let me say that again to those engineers who weren't listening:

Nuclear (fission) power is not, and will never be, financially viable for civilian powerplants.

I'll eat a roll of toilet paper covered in hot sauce if someday nuclear fission is financially viable enough to produce power for civilians at a decent scale.

Re:Why are nuclear power construction costs so high? Part II... by kinghajj on Friday September 30, 2022 @04:55PM (#33040655)
Even assuming that's the case, isn't the counterargument "Fine, then governments need to subsidize investment into nuclear power plants, just as we do with other green technologies."
Re:Why are nuclear power construction costs so high? Part II... by epistasis on Friday September 30, 2022 @05:44PM (#33041196)
The amount of subsidy required for nuclear is at least an order of magnitude larger than renewables.

Switching to renewable energy with massive amounts of storage is a world of cheaper energy than today. There has been zero learning curve for oil, and coal, and nuclear. If anything nuclear gets more expensive rather than less.

In contrast, renewables and storage are technologies that behave like semiconductors, or hard disks. There's a fairly predictable improvement in costs over time, resulting in massive changes in capabilities over the course of decades.

So not only is switching to renewables and storage cheaper than our current every sources, the faster we perform the change, the more money we save, the more of our resources we can devote to improving the quality of human lives, instead of devoting all that effort to make-work of welding pipes and pouring concrete.

Re:Why are nuclear power construction costs so high? Part II... by orangecat on Friday September 30, 2022 @04:58PM (#33040709)
Right. It's fascinating how this is the one area where so-called environmentalists suddenly become very concerned about fiscal responsibility.
Re:Why are nuclear power construction costs so high? Part II... by epistasis on Friday September 30, 2022 @05:29PM (#33041049)
Environmentalists have pretty much zero impact on the ability of nuclear plants to be started and demonstrate feasibility.

In the US, Georgia and South Carolina started building with nary a peep. France started building again without any environmental objections.

Yet these builds are all catastrophic failures, to the point that any other financial backer is scared away from even touching nuclear. The decision makers are those with the dollars to invest, not the environmentalists.

Re:Why are nuclear power construction costs so high? Part II... by andbberger on Friday September 30, 2022 @05:40PM (#33041153)
"environmentalists" in california have succesfully prevented at least 6GW from coming online, and were directly responsible for plans that shutter california's last operating reactor. They lobbied PG&E with a study they paid for that, under the insane assumption that california's energy use would _decrease_ in the future, concluded renewables would be cheaper. Meanwhile CAISO issued increasingly urgent press releases warning of the catastrophic consequences to grid stability were diablo canyon to close. A disaster which was narrowly avoided a few weeks ago by newsom.

don't underestimate the negative influence of "environmentalists"

Re:Why are nuclear power construction costs so high? Part II... by epistasis on Friday September 30, 2022 @05:49PM (#33041253)
> They lobbied PG&E with a study they paid for that, under the insane assumption that california's energy use would _decrease_ in the future, concluded renewables would be cheaper

Usage in California has gone down, and renewables are cheaper, just look at the blog series in the original article. Calling these well-known and irrefutable facts "insane" does not bode well for the plethora of other questionable assertions in your comment. For the usage:

https://www.energy.ca.gov/data-reports/energy-almanac/califo...

Re:Why are nuclear power construction costs so high? Part II... by andbberger on Friday September 30, 2022 @05:53PM (#33041288)
energy austerity is incompatible with climate change mitigations. eg thermal industrial processes currently powered by fossil fuels need to be moved to grid power.

their proposal was to spend $2B to lose 2GW of carbon free baseline power

everything in my statement is true and based on documents in the public record

Re:Why are nuclear power construction costs so high? Part II... by epistasis on Friday September 30, 2022 @05:59PM (#33041357)
I have followed the documents carefully, doing a deep dive on Diablo Canyon around 2020, but I do not recognize your framing of the situation as anywhere close to accurate. I'm also not sure what you mean when you are referring to energy austerity in your comment, of what $2B you are talking about.
Re:Why are nuclear power construction costs so high? Part II... by andbberger on Friday September 30, 2022 @06:11PM (#33041458)
$2B is the cost to decommission diablo canyon. energy austerity is planning to use less energy when we know for a fact we're going to need more.
Re:Why are nuclear power construction costs so high? Part II... by IncRnd on Friday September 30, 2022 @05:57PM (#33041333)
Environmentalists have not been, are not now, and will likely never be the decision makers for building nuclear power plants.
Re:Why are nuclear power construction costs so high? Part II... by manuel_w on Friday September 30, 2022 @05:48PM (#33041245)
Aren't governments subsidizing nuclear power plants a whole lot more than anything else?

I heard without government subsidies, nuclear power plants would simply not be buildable. No insurance company would insure them. The cost in case of a nuclear fallout is just too high.

Re:Why are nuclear power construction costs so high? Part II... by ncmncm on Friday September 30, 2022 @10:51PM (#33043365)
Strictly speaking, oil still gets almost all the subsidies. The rest are chicken scratch.

But yes, nukes all rely heavily on subsidies, always have.

Re:Why are nuclear power construction costs so high? Part II... by dale_glass on Friday September 30, 2022 @05:21PM (#33040961)
I think not really. It depends on why you think subsidizing is a good thing.

My personal take is that we should subsidize tech to take it from an early stage to a production stage as soon as possible. We need better power sources yesterday, not next century. So we can't sit around waiting for some sort of Elon Musk to get really passionate and dump heaps of cash into it.

But the assumption there is that once the tech is developed and mature, it'll be good enough to stand on its own. Because if it'll never not be expensive, we're just artifically choosing a power source that's permanently more expensive than the alternatives, and that's an unstable situation. Eventually people will get tired of dumping money into it, or there will be some other urgent matter to throw money at, and then we have a bunch of expensive tech that's falling out of use, and underdeveloped alternatives.

Subsidizing nuclear forever also doesn't make any sense economically. Money is fungible. There's no real difference between say, paying $200/month to your power company, or paying $100/month to your power company, and $100 in taxes that ends up going to the power company. The amount you have to spend at the end of the month is the same either way. Now paying $200/month for 5 years so that then your power bill drops to $50/month afterwards, that's a different proposition.

So, I support subsidizing solar, wind and storage because I believe that in their perfected, mass produced versions they're cheap and competitive. They just need a push now. I don't support subsidizing nuclear because I believe it'll always be expensive because it's a fundamentally complex technology that's not amenable to mass production and will always lose to brute force mass applications of simpler technologies.

Re:Why are nuclear power construction costs so high? Part II... by stormbrew on Friday September 30, 2022 @05:30PM (#33041056)
The US government makes a steady stream of trillions of dollars appear in order to, among other things, build single use missiles for millions of dollars each and jets that have never seen real combat for billions each. The idea that any durable public work is somehow "too expensive" in the face of that is comically absurd.
Re:Why are nuclear power construction costs so high? Part II... by epistasis on Friday September 30, 2022 @05:56PM (#33041321)
Putting aside the wisdom of such massive defense spending, the question is what is the alternate good that could perform the job?

If we spend $12B on a 1GW reactor, we have far far better alternatives. A 1GW nuclear reactor has a 90% capacity factor of undispatchable, hard to throttle electricity. At today's prices, thay $12B could instead buy 6GW of solar at 20% capacity factor, and 24GWh of batteries. This combined solar plus storage is more flexible, more responsive, and delivers 30% more overall energy. And this is with a stupid design of splitting the cash to half storage half solar. A smarter design more tailored to the actual demand curve would remove some flexibility but become far cheaper.

There's zero reason to build nuclear unless you want to line Bechtel's pockets.

Re:Why are nuclear power construction costs so high? Part II... by towaway15463 on Friday September 30, 2022 @06:27PM (#33041573)
Some questions jump out there:

What does that amount of solar and storage look like in terms of material used for its construction as well as area occupied once it’s deployed?

What current examples do we have of projects at this scale?

What is the lifespan of the solar arrays and batteries?

What are the operating costs? How many personnel are required for maintenance and day to day operation?

What other infrastructure is necessary to support such a deployment? Transmission lines, buildings, monitoring facilities, security, roads, office space, etc.

What is the construction timeline for such a project?

Re:Why are nuclear power construction costs so high? Part II... by epistasis on Friday September 30, 2022 @06:39PM (#33041666)
I don't have exact numbers for any of these questions. However, we know that regardless of the inputs in materials or land, the ultimate dollar cost, all in, is cheaper than nuclear. Take the levelized cost of solar for the MWh coinciding with daylight hours, and the levelized cost of storage during the other hours, and nuclear is blown out of the water:

https://www.lazard.com/perspective/levelized-cost-of-energy-...

Also, the scale doesn't matter, we have built far more than 6GW of solar, deployed more than 24GWh of storage, but it doesn't have to be at one location for these resources. Solar and batteries scale far better than nuclear, because they can be deployed on smaller installations without nearly as much hassle as nuclear. Or they can be sited at one location.

Re:Why are nuclear power construction costs so high? Part II... by ok_dad on Friday September 30, 2022 @07:43PM (#33042166)
Additionally, part of the bonus of solar+storage vs. large nuclear is that when you spread out your generation into smaller grid sections, then you can reduce the need for large transmission infrastructure that requires maintenance[1].

Distributed software is good, so why not distributed energy generation? Answer: distributed energy generation is great!

[1]: https://www.cnbc.com/2022/01/05/california-finds-pge-equipme...

Re:Why are nuclear power construction costs so high? Part II... by towaway15463 on Friday September 30, 2022 @07:54PM (#33042230)
Even so, when people say that we’ll just spread out this energy generation infrastructure everywhere I still want to know the actual numbers. Are there enough rooftops and vacant lots in LA to provide all the necessary power? What about lower density areas? What about northern climates with lots of snow and rain? There is still maintenance involved, installation costs are likely increased by doing this piecemeal rather than at a single site. Are we assuming all of this will be undertaken by individual homeowners or is it a commercial operation? Leaving it up to individuals seems like it would drastically slow roll out due to a lot of people not being able to afford it or simply being unwilling to have panels. If commercial then the available locations become very limited. These things can’t just be hand waved away.
Re:Why are nuclear power construction costs so high? Part II... by ncmncm on Friday September 30, 2022 @10:54PM (#33043375)
There is absolutely no need to use any land exclusively for solar or wind.

Both coexist synergetically with reservoirs, canal, pasture, even crop land. So, zero acres of land needed.

Re:Why are nuclear power construction costs so high? Part II... by labcomputer on Friday September 30, 2022 @08:43PM (#33042592)
So, like, why don't you try to calculate this for yourself? As a pedagogical exercise, I think you'll get much more out of it if you compute the numbers for yourself and play through a bunch of "what if" scenarios.

Just to get you started with some ballpark numbers: The solar irradiance at ground level on a sunny day is greater than 1kW/m^2 for about 6 hours per day (google for "AM1.5"). Typical commercial panels have a conversion efficiency of 21-22%.

You seem very confident that solar is impossible, so why don't you make some reasonable assumptions and prove it to all of us?

Re:Why are nuclear power construction costs so high? Part II... by towaway15463 on Saturday October 01, 2022 @09:50AM (#33046568)
I didn’t say that I think it’s impossible. I’m asking for the reasoning behind the belief that it would be the optimal solution. In this context a lot of details are being talked about to argue for or against the viability of nuclear but I don’t see the same critical process being applied to the assertions that we can run everything on solar and batteries. I’ve put forward many of the same questions that have been answered for nuclear, it is up to the solar proponents to answer them.
Re:Why are nuclear power construction costs so high? Part II... by epistasis on Saturday October 01, 2022 @07:49PM (#33051261)
It's safe to assume that most nuclear propositions are based upon unrealistic best case scenarios that won't stand up to the scrutiny of reality, and that all solar propositions have been treated incredibly harshly and conservatively and the solar solution will be completely underestimated.

There is a massive bias in the field in favor of nuclear and against solar, and this shows in every single prediction made over the past 15-20 years. The EIA would uncritically put out numbers for "advanced nuclear" that were unbeliever rosy for a tech that had never been built. And at the same time, use out of date costs for solar, and the assumption that solar would stay at the old prices and never improve in price.

Or you will see peer reviewed papers in nuclear that assume ridiculous rosy solutions, that make it all the way through to publication without those rosy assumptions being challenged. For example, using nuclear in remote areas, but it using the actual capacity factor of that sort of system, 40-50%, and instead assuming that the price is coming from using every last bit of electricity at all time. In contrast all the modeling around solar always picks the most conservative estimates, because of the unrealistic hyper criticism of solar, which leads to even the most rosy of solar predictions being underestimated of solar.

Similarly, "concerns" about land or energy density are not realistic concerns, but mere political talk used to delay delay delay as long as possible the obvious solution that solar will be a cornerstone of our energy future, from 40%-70% of most countries' energy.

But if you actually are interested in the land usage, it's a question that has been studied to death. NREL is usually a good source, but one caution is to look at the date of any publication, and realize that if it's more than a year old, a lot of the data will be out of date. Here's a 2013 report on land use:

https://www.nrel.gov/docs/fy13osti/56290.pdf

Re:Why are nuclear power construction costs so high? Part II... by towaway15463 on Friday September 30, 2022 @07:57PM (#33042250)
If small commercial solar operations are in fact cheap and have a high return then why am I not seeing startup solar power generation companies everywhere? Surely it would be a hot industry to get into if you can put it anywhere and make a profit?
Re:Why are nuclear power construction costs so high? Part II... by epistasis on Friday September 30, 2022 @08:36PM (#33042548)
I would suggest that those companies exist everywhere, you just don't see them. There's something like 1 TW of renewable projects that are being considered in US interconnection queues right now. Total US power draw is only 0.5TW. At and average of ~30% capacity factor, that's 60% of total US electricity demand replacement, with today's projects.

Now, only a fraction of these will get connected, because only the marginal best investment dollar gets the invested, but the scale is there.

Really the limit it current solar and wind production capacity, which is ever increasing at absolutely terrific speeds.

This is one of many reasons that I think a focus on nuclear is the wrong place. It's not going to be able to scale to catch up to these other technologies, even if after 60 years of development, nuclear finds a learning curve for the first time ever.

Re:Why are nuclear power construction costs so high? Part II... by towaway15463 on Saturday October 01, 2022 @10:07AM (#33046667)
I’m aware of several heavily subsidized renewable projects in my local area alone that have failed to deliver usable power to a grid that sorely needs it. I’m aware of 0 independently funded ventures even though my area has some of the highest electricity prices in the country.

My question is given this market where you have high prices and high demand, why do I not see any entrepreneurs building small solar installations and cutting deals with municipalities to provide some of their grid power?

That tells me that the technology, cost, and/or regulation isn’t viable yet. Promises of future developments do nothing to address current needs. I have a feeling that 100% renewable generation is fast becoming a “20 years away” problem since I’ve been hearing the same promises for at least 20 years now and those older than me likely remember even older promises.

Re:Why are nuclear power construction costs so high? Part II... by epistasis on Saturday October 01, 2022 @11:43AM (#33047420)
> That tells me that the technology, cost, and/or regulation isn’t viable yet.

I don't know where you live, but generalizing from one small locality with an out of wack market is leading you to the wrong conclusions.

In places where there's a free market for new generation, like Texas, there's more GW of storage being added than GW of natural gas. There's an order of magnitude of new wind and solar generation being added than natural gas, and this is the place with some of the cheapest natural gas in the entire world. Having trouble finding ERCOT, but for the entire US, 1.3TW of the 1.4TW on newly proposed projects are renewable or storage:

https://www.publicpower.org/periodical/article/renewables-do...

So your local utility, which is charging you high prices, probably has a process that disincentivizes renewables to a large degree. And if there are zero independent funded ventures, then your utility must be actively stopping renewables, and those investors are working in the far more fertile rest of the US.

In particular, small projects can be the hardest to get through. There's zero reason for a utility to cut a deal, they are a monopoly, they are raking in far checks by doing nothing. Utility executives are some of the people least likely to adopt any sort of new technology.

The biggest impediment to renewables sweeping through the grid and giving us cheaper electricity is politics, conservatives, and rentierism. In areas where there's a market set up to allow lower costs to win, fossil fuels are toast. But in most places, electricity is not a market.

Re:Why are nuclear power construction costs so high? Part II... by pfdietz on Saturday October 01, 2022 @07:43AM (#33045851)
Replacing existing operating power plants is tougher than outcompeting other options for new power plants. Demand for grid energy in the US has been flat for more than a decade.
Re:Why are nuclear power construction costs so high? Part II... by stormbrew on Saturday October 01, 2022 @12:18AM (#33043823)
I don't think this black and white thinking is really useful. There are inhabited places in the world where solar and wind face real challenges to practicality as the sole source of energy. I would be shocked if we're capable of building an amount of storage that will get the city I live in through the winter, for example. Certainly not for cheaper than a natural gas plant, which is the real competition.

Frankly, whenever this comes up the handwaving about storage just seems hopelessly optimistic even for places where it is practical, let alone places where you're lucky to get 4 hours of sunlight a day for a bunch of the year.

Nothing is ever that simple. If carbon zero is an imperative, then there will sometimes be need for something other than solar and wind, and it will inevitably be "impractically expensive" compared to the carbon emitting sources we're moving away from.

It's certainly important to improve the economies of scale of renewables, but doing so is not the goal. Saving money is not the goal. The survival of the human species is the goal, and we aren't going to get there by nickel and diming our way to it.

Re:Why are nuclear power construction costs so high? Part II... by pfdietz on Saturday October 01, 2022 @07:46AM (#33045868)
Does your city burn natural gas in the winter? That natural gas is not coming directly from wells, typically; it is stored in underground caverns and pipelines. Hydrogen can be stored just the same way. Power-to-X (where X can be hydrogen or other e-fuels) allows renewables to scale to 100% of the energy needed by society at affordable costs.

https://ieeexplore.ieee.org/document/9837910

Re:Why are nuclear power construction costs so high? Part II... by stormbrew on Saturday October 01, 2022 @04:57PM (#33050039)
I mean, nuclear might be expensive, time consuming to build, and difficult but at least we've been doing it for 70 years. It's not clear that projections of long term costs on things we haven't even done at scale are going to be realistic when we try them in the real world.

Even if it takes 20 years to build a nuke, that might still be sooner than "power to x" becomes a viable, affordable option for most of the world.

This is the weird thing about this argument: it so often rests simultaneously on an argument for practicality and/or cost effectiveness, but literally any criticism is met with a gish gallop of unproven technology. You can't have this both ways.

In the end, my central thesis here is just that if you think the be all and end all of this issue is cost effectiveness you are optimizing for the wrong goals and it leaves open a giant window for carbon emitting sources to justify their use when renewables don't work for various local reasons.

The thing to be black and white about is carbon emissions. "What energy mix works for place X right now if we try to eliminate carbon emissions asap" is not a decision that's gonna be made on an internet forum.

Re:Why are nuclear power construction costs so high? Part II... by pfdietz on Saturday October 01, 2022 @05:22PM (#33050233)
You're aware that current commercial nuclear power plants cannot power the world, right? They are thermal burner reactors. Supplying the entire world's current primary energy demand would require about 6000 1 GW(e) (which is 3 GW(th)) reactors. These would use up current uranium resource (not reserve) in about five years.

A nuke powered world will either require radically new sources of uranium (like sea water uranium extraction) or breeder reactors. Neither is available now, unlike cheap electrolyzers for making hydrogen (< $300/W in China).

Re:Why are nuclear power construction costs so high? Part II... by stormbrew on Saturday October 01, 2022 @05:33PM (#33050347)
Please point to me saying anything about "powering the world" with nukes. What a ridiculous strawman. This isn't Mortal Kombat: Energy Edition.
Re:Why are nuclear power construction costs so high? Part II... by pfdietz on Saturday October 01, 2022 @06:57PM (#33050962)
This is all about moving off fossil fuels because of induced climate change. That requires changing what powers the world. If nuclear is not going to power the world, then it's basically irrelevant, and the issues raised against renewables will not block their widespread adoption.
Re:Why are nuclear power construction costs so high? Part II... by stormbrew on Saturday October 01, 2022 @07:06PM (#33051010)
No one thing is going to power the whole world. Even "renewables" isn't one thing, and it can't and won't be deployed the same way in every climate or environment. It, as a blanket set of things, should be deployed everywhere however it can be. But there is no reason to exclude nuclear a priori as a blanket thing. And especially not in favor of waiting for promised improvements in storage or synthetic fuels that have not yet been proven.

Again, this is not a duel to the death. The only thing that should be dismissed out of hand is carbon emitting fuels.

Re:Why are nuclear power construction costs so high? Part II... by epistasis on Saturday October 01, 2022 @11:57AM (#33047532)
If you live in a place that only gets four hours of sun a day, sure, look more into nuclear.

But instead of being so "black and white" and insisting it must be nuclear that powers things, also evaluate options like thermal storage to gather summertime heat in reservoirs for use throughout the winter. It's super cheap, and makes a ton of sense in most areas, yet it's so low tech that it gets ignored.

I will be black and white that fission is not a feasible solution for the vast majority of the human population for at least the next 20 years, and probably forever. Despite more than half a century of experience, it has not improved as a technology. There would have to be some sort of drastic breakthrough for nuclear to be a realistic power source for most of the earth's surface.

Re:Why are nuclear power construction costs so high? Part II... by stormbrew on Saturday October 01, 2022 @04:52PM (#33050005)
> But instead of being so "black and white" and insisting it must be nuclear that powers things

It sure is a good thing I didn't say anything of the sort or wow I'd be a hypocrite.

I am definitely not the person trying to shoehorn the entire earth into one energy mix box in this conversation. I think the answer to this is likely to vary a lot all over the world.

Also a lot of the world's population is far enough north that winters produce relatively little solar or wind energy. And those places also tend to be massive energy consumers because it's also very cold.

Right now that doesn't show up in electricity stats because of how common in-home gas heating is. In order to decarbonize the northern parts of the world we will need to dramatically increase both electric energy consumption and production, during winter, because heat pumps will almost certainly be replacing gas furnaces.

Re:Why are nuclear power construction costs so high? Part II... by coryrc on Friday September 30, 2022 @09:48PM (#33042990)
> At today's prices, thay $12B could instead buy 6GW of solar at 20% capacity factor, and 24GWh of batteries.

I don't think that can actually be done. The world's largest battery installation is less than 1 GWh AFAICT. OTOH we're not doing great at nuclear either.

Re:Why are nuclear power construction costs so high? Part II... by pfdietz on Friday September 30, 2022 @10:31PM (#33043229)
It doesn't have to all be one giant stack of batteries. Your argument is like saying that we can't add more than (say) 2 GW of nuclear, because that's the size of the largest nuclear power plant.
Re:Why are nuclear power construction costs so high? Part II... by epistasis on Saturday October 01, 2022 @08:53AM (#33046231)
What do you mean by "can't be done"? If we can build a 500MWh battery we can build a 1GWh battery by doing the 500MWh battery two times.

Similarly if we can build a 1GWh battery we can build also a 24 GWh battery.

Re:Why are nuclear power construction costs so high? Part II... by coryrc on Saturday October 01, 2022 @10:33PM (#33052272)
That's the same argument for building nuclear -- we've done projects before, just do it more/bigger.

Yet we can't and aren't.

Re:Why are nuclear power construction costs so high? Part II... by psd1 on Saturday October 01, 2022 @04:42AM (#33045055)
I agree with your reasoning, but on this tiny rock we call Albion I'm not convinced that renewables will ever be viable for base load.

I'm concerned about the tonnage requirement of strategic minerals for battery storage. Supplies for EV batteries are currently choked; we need to scale far beyond that for grid storage.

Pumped hydro at the required scale will be a feat of engineering comparable to nuclear engineering. Millions of tonnes of Portland cement will be an input.

And renewables are land-extensive; that's an impedance mismatch for us.

Re:Why are nuclear power construction costs so high? Part II... by pfdietz on Saturday October 01, 2022 @07:53AM (#33045909)
There are many different battery technologies being pursued. Some use uncommon materials, but others are just using elements available in essentially unlimited amounts. There are also means of storing energy in other forms. For example, storage of electrical energy as heat energy in sand could have a round trip efficiency of 54% at a quite reasonable cost.

https://arpa-e.energy.gov/sites/default/files/2021-03/07%20D... (now being commercialized by Babcock & Wilcox.)

The big question of storage is not if it's possible, but which of the many options will come out on top.

Re:Why are nuclear power construction costs so high? Part II... by jacobsenscott on Friday September 30, 2022 @06:46PM (#33041712)
It is more viable than any other form of energy. You need to count the externalized costs of fossil fuel power plants. The cost of climate change has already exceeded the cost of building many nuclear plants, and that cost will continue to compound at an accelerating rate. One nuc plant costs less than twitter, and twitter is useless. So as a society we have more than enough resources, just not the will. Let it burn.
Re:Why are nuclear power construction costs so high? Part II... by pfdietz on Saturday October 01, 2022 @07:54AM (#33045915)
This is old thinking that considers nuclear as the only option to replacing fossil fuels. But this is now a broken world view, and you need to stop making this bad argument.
Re:Why are nuclear power construction costs so high? Part II... by remarkEon on Friday September 30, 2022 @05:02PM (#33040761)
Can we better define what “financially viable” means?

I don’t know that I need a nuclear power plant to “turn a profit”. That would be great, I suppose, but my view on electricity is a little more nuanced than a dogmatic adherence to market forces.

Re:Why are nuclear power construction costs so high? Part II... by orangecat on Friday September 30, 2022 @04:56PM (#33040684)
Ok, but France exists.
Re:Why are nuclear power construction costs so high? Part II... by fweimer on Friday September 30, 2022 @05:13PM (#33040883)
EDF has recently been re-nationalized, and has always been under strong government influence. It's not a good example of a civilian/free market nuclear power plant operator.
Re:Why are nuclear power construction costs so high? Part II... by franckl on Friday September 30, 2022 @05:52PM (#33041283)
Careful, the renationalization is due to a lot of factors, the main one is that the EU forced EDF to sell its nuclear eneegy at a loss to private energy providerd in order to "free the market". Look for ARENH if you would like to learn more (quick Google https://www.nusconsulting.com/energy-blog/arenh-reform-could...)
Re:Why are nuclear power construction costs so high? Part II... by fweimer on Saturday October 01, 2022 @08:17AM (#33046049)
I didn't mean to imply that nationalization happened because nuclear power isn't commercially viable. The French situation was special even before full nationalization.

I really doubt ARENH is the problem because as far as I understand it, it only applies to EDF's existing nuclear power plants. At 42 EUR/MWh wholesale, those plants should still make a tidy profit. Apparently, too few of them were actually running last year, and the French government imposed further price restrictions that also affected resale of energy that EDF purchased elsewhere at market prices (not coming from EDF's own nuclear fleet or its other power plants).

Re:Why are nuclear power construction costs so high? Part II... by dboreham on Friday September 30, 2022 @05:21PM (#33040963)
Electricity generation in the US isn't "under strong government influence"?
Re:Why are nuclear power construction costs so high? Part II... by fweimer on Friday September 30, 2022 @05:32PM (#33041076)
I wasn't talking about regulation. EDF's relationship with the French government goes well beyond that.
Re:Why are nuclear power construction costs so high? Part II... by megaman821 on Friday September 30, 2022 @04:58PM (#33040710)
I doubt Americans would be happy paying what France pays for electricity (both directly and government aid).
Re:Why are nuclear power construction costs so high? Part II... by psd1 on Saturday October 01, 2022 @04:27AM (#33044999)
Right, but non-monetary negative outcomes are swept under the rug.

It costs nothing for fossil plant operators to pump carbon and sulphur into the atmosphere; that's why it takes regulation to make them install scrubbers. Scrubbers help, but don't prevent the outcome.

The outcome can be measured in human deaths and loss of arable land. That cost is hidden.

The "free market" is a grim joke while these costs can be ignored.

Re:Why are nuclear power construction costs so high? Part II... by oceanplexian on Friday September 30, 2022 @06:26PM (#33041568)
I mean, if the choice is expensive electricity and rolling blackouts because the entire country relied on unreliable sources of energy, I'd take the former. The best energy source is one that's robust and dependable, not one that's theoretically cheaper in some ideal circumstances.
Re:Why are nuclear power construction costs so high? Part II... by layer8 on Friday September 30, 2022 @06:48PM (#33041729)
An important motivation for France to invest in nuclear technology is that they want to remain a nuclear weapons state.
Re:Why are nuclear power construction costs so high? Part II... by jjoonathan on Friday September 30, 2022 @05:00PM (#33040730)
Also 20% of the US's electric grid for the last 30 years.
Re:Why are nuclear power construction costs so high? Part II... by insane_dreamer on Friday September 30, 2022 @05:20PM (#33040942)
Counterpoint: France gets over 70% of its total energy from nuclear power (and exports some to other EU countries).
Re:Why are nuclear power construction costs so high? Part II... by Retric on Friday September 30, 2022 @05:28PM (#33041038)
False, with heavy subsides ~70% of Frances electricity production for the power grid was nuclear but they exported a great deal of that nuclear power in non peak times such as nights and weekends to maintain even a 68% capacity factor. Further they imported a great deal of non nuclear power to cover their own peak demand. By comparison US reactors generally have over a 90% capacity factor which means generating ~30% more electricity from the same investment or in Frances case posting a ~30% premium on nuclear power.

It’s hard to work out exact figures but around 60% of the grid’s electricity used in France came from nuclear reactors. To illiterate the difficulty, recently most of France’s nuclear power plant where undergoing maintenance however due to low seasonal demand other power plants where able to make up the difference.

PS: To be really pedantic, total electricity production would include car alternators, home PV panels, diesel electric locomotive etc, but that’s yet another calculation.

Re:Why are nuclear power construction costs so high? Part II... by epistasis on Friday September 30, 2022 @05:24PM (#33040997)
That doesn't counter the point above. France's fleet was built in the 70s, at difference costs. And what were those costs? Were they viable at the time, or was it a government program that would spend at any cost? Are today's costs viable now?

Have you bothered to look at Flamanville or Olkiluoto? What happened when in the past when France built subsequent copies of a reactor design, and won't we expect similar costs rises with these already unviable reactors?

Re:Why are nuclear power construction costs so high? Part II... by andbberger on Friday September 30, 2022 @05:42PM (#33041177)
there's a reference I can't find discussing the financials of hinkley point C, a wildly expensive reactor and concluding that even with the extreme cost overruns, the levelized cost would still be superior to renewables if not for aggressive interest rates by financiers.
Re:Why are nuclear power construction costs so high? Part II... by ryan93 on Friday September 30, 2022 @08:43PM (#33042595)
Expensive compared to the increase in national debt over last ten years?
Re:Why are nuclear power construction costs so high? Part II... by aaaaaaaaaaab on Friday September 30, 2022 @05:01PM (#33040736)
>I'll eat a roll of toilet paper covered in hot sauce if someday nuclear fission is financially viable enough to produce power for civilians at a decent scale.

So all the world’s nuclear power plants operate at a loss? That’s a pretty strong proposition…

Re:Why are nuclear power construction costs so high? Part II... by ok_dad on Friday September 30, 2022 @07:37PM (#33042122)
> at a decent scale

More than a few old reactors here and there that are about to be decommissioned would be my idea of "at decent scale" here, so let's say that 10% of the new build power was nuclear (which would be equal to how much old, rotten nuclear fission infrastructure we have today, in the world).

I would almost bet less than 2% of the current planned and contracted energy capacity was in nuclear and that probably a good part of that will never materialize.

Re:Why are nuclear power construction costs so high? Part II... by NovemberWhiskey on Friday September 30, 2022 @05:09PM (#33040848)
The problem is that people want to talk about fully-loaded life-cycle costs; and depending on who is doing the talking you get wildly different numbers.
Re:Why are nuclear power construction costs so high? Part II... by dboreham on Friday September 30, 2022 @05:22PM (#33040977)
The life cycle cost associated with boiling the planet is also quite high.
Re:Why are nuclear power construction costs so high? Part II... by pfdietz on Friday September 30, 2022 @10:34PM (#33043249)
There's never been a single merchant nuclear plant built to sell into a competitive market, anywhere in the world. So, all the nuclear plants around were built with a captive audience of customers who were to be forced to pay for them. In the US, the remainder of nuclear interest was down in the southeast where this sort of thing still exists.
Re:Why are nuclear power construction costs so high? Part II... by epistasis on Friday September 30, 2022 @04:49PM (#33040602)
Is our ultimate goal to get nuclear at any cost? Then sure.

But nuclear at any cost is not a reasonable goal. The only reason we want nuclear is for its carbon-free energy. At which point it must be evaluated on its merits, not as an end goal of its own

Re:Why are nuclear power construction costs so high? Part II... by donmaq on Friday September 30, 2022 @07:49PM (#33042200)
And how can we just ignore the waste problem? [1] In many cases, containment pools are full to the brim with spent rods [2], which is both environmentally hazardous, & a target for terrorists (dirty bombs)

1: https://www.ucsusa.org/resources/nuclear-waste

2: https://ips-dc.org/spent_nuclear_fuel_pools_in_the_us_reduci...

Re:Why are nuclear power construction costs so high? Part II... by pfdietz on Friday September 30, 2022 @10:35PM (#33043256)
We can ignore the waste problem because nuclear fails even if we do so.
Re:Why are nuclear power construction costs so high? Part II... by Schroedingersat on Friday September 30, 2022 @11:29PM (#33043585)
The waste problem is real, and if the nuclear shills can demonstrate that there can exist a nuclear reactor that can compete with solar+storage in winter at 45 degrees north economically then we can bother talking about it.

Until then we dismiss them along with every other technology that does not meaningfully exist.