News for hackers. Stuff that matters.
Re:Spanish rail's costly blunder: New trains too large for t... by Drunk_Engineer on Saturday February 11, 2023 @02:22PM (#34755392)
Clickbait headline -- the error was caught during the design phase. At worst, this will cause a 2-3 year delay in building the trains.

The more interesting thing about the story is how several top government officials were fired as a result. That would never happen in the US, where decade-long delays are commonplace for train procurement.

Re:Spanish rail's costly blunder: New trains too large for t... by Tao3300 on Saturday February 11, 2023 @02:39PM (#34755552)
And that's why I always travel with uBlock.
Re:Spanish rail's costly blunder: New trains too large for t... by remote_phone on Saturday February 11, 2023 @02:45PM (#34755618)
Only 2-3 years? That’s a disaster what do you mean! People need to be kept on the payroll, etc and the entire schedule will have more consequences. That is a huge expense for something that is literally a few clicks on a keyboard. It’s something that should never have happened.
Re:Spanish rail's costly blunder: New trains too large for t... by BigRedDog1669 on Saturday February 11, 2023 @03:44PM (#34756159)
I think they mean that it is bad, but minor compared to what would have happened in the US or some other countries, where train projects are delayed 10 years without design problems.
Re:Spanish rail's costly blunder: New trains too large for t... by fsckboy on Saturday February 11, 2023 @06:07PM (#34757370)
without even commenting on the idea that govt bureaucracy is somehow worse in the US than in the romance countries, a 2-3 year delay would still be added on, and is very significant. it's not like a 10 year delay is great because it gives time to make everything else come out right.
Re:Spanish rail's costly blunder: New trains too large for t... by simplotek on Sunday February 12, 2023 @07:47AM (#34762426)
> (...) but minor compared to what would have happened in the US or some other countries (...)

That's just speculation to try to mitigate a colossal screwup.

This is not the first time when Spanish railway companies are caught trying to cover up the consequences of massive incompetence. For instance, the infamous Santiago de Compostela train disaster[1] was attributed to a careless train conductor going over the speed limit to impress a girl, which was a very convenient scapegoat to both ADIF and Renfe, but in truth the root cause as that both companies failed to deploy a mandatory speed monitoring and control system, which has been standard for decades.

[1] https://en.wikipedia.org/wiki/Santiago_de_Compostela_derailm...

Re:Spanish rail's costly blunder: New trains too large for t... by BoorishBears on Saturday February 11, 2023 @03:00PM (#34755748)
Dishonest comment.

> While the manufacturer came to the realization relatively early during the design stage, the delivery will still be delayed by two to three years and the project, initially estimated at €258 million, will suffer a massive yet-to-be-determined cost blowout.

> "I hope that heads will roll!" said the president of the Cantabria regional government, Miguel Angel Revilla, on Thursday, February 2, without hiding his anger against what he called "monumental pig work."

Headline is exactly right... and strange that you went out of your way to invent the "at worst qualifier" to sure up your claim.

This is the definition of a blunder: having a firm work for nearly 3 years on bad measurements, then having to push back the project by 2-3 years? That's implying almost all of the work from when the designs were given to them in 2020 will have to be revised.

Re:Spanish rail's costly blunder: New trains too large for t... by handsclean on Saturday February 11, 2023 @03:42PM (#34756135)
In correcting a triviality, you’ve been more dishonest than GP and even the headline. GP inflated the confidence of the three year limit. You said that the headline is “exactly right”, while in fact it’s objectively false, the “new trains” it refers to do not exist. You’ve also fabricated 2-3 years of repeated work, which is not backed by this source, would be pretty bizarre if truly nothing could be salvaged, and in fact is apparently contradicted by other sources, which state that the firm worked with bad measurements for only about a year.
Re:Spanish rail's costly blunder: New trains too large for t... by BoorishBears on Saturday February 11, 2023 @04:29PM (#34756562)
You're clearly struggling with comprehension but I'm always happy to teach.

> You said that the headline is “exactly right”, while in fact it’s objectively false, the “new trains” it refers to do not exist

If I give you designs to build me a new house, and it doesn't fit on the lot, that means my new house is too big for the lot.

And in fact, I don't even have to give you designs. The moment I communicate intention for the new house, the phrase "new house" refers to... the new house, regardless of its state. We can chat about "the new house" without even having picked which continent it will exist on. "Where will the new house be built?"

Similarly if I ask an artist for a painting, and the artists finds the painting I asked for won't fit on the canvas before making a single brush stroke, the wording is "your new painting won't fit on this canvas".

-

Honestly not the most complicated turn of phrase, so if you couldn't grasp that, it's not hard to see where you're coming up with stuff like...

> You’ve also fabricated 2-3 years of repeated work

No, I didn't. Critical thinking may come across like a fabrication if you refuse to indulge yourself in it, but happy to share my work: If I'm on a project for 2-3 years, then I find because of a mistake I need to push things back 2-3 years, that means that heavily implies that... the work of those 2-3 years were wasted?

Now let's remember what I said...

> That's implying almost all of the work from when the designs were given to them in 2020 will have to be revised.

Marvelous.

-

> in fact is apparently contradicted by other sources, which state that the firm worked with bad measurements for only about a year.

That "apparently" is a funny way of saying "I didn't verify the sibling comment, which I already admitted was willing to inflate the sources I do have". If only the comprehension could catch up to the brevity.

-

By the way, what do you think it means when the government official says

"without hiding his anger against what he called "monumental pig work."

Obviously there was something lost in translation there, but let's apply that critical thinking and guess, if just maybe, it means there was a ton of wasted work...

Re:Spanish rail's costly blunder: New trains too large for t... by dang on Tuesday February 14, 2023 @03:44AM (#34786973)
You broke the site guidelines egregiously here. Please don't do that again.

https://news.ycombinator.com/newsguidelines.html

Re:Spanish rail's costly blunder: New trains too large for t... by handsclean on Tuesday February 14, 2023 @08:20PM (#34798793)
On re-reading my previous comment, it was pretty insulting, which I think provoked you to retaliate. I apologize for my tone.

Modifying your example’s verb, if you said “Where is the new house?”, then I’d say you’re implying the new house presently exists - unless we’re currently poring over housing development plans, in which case I’d say you’re clearly referring only to plans. Maybe the reason we’re reading the headline differently is context. This is the first I’ve heard of new Spanish trains, so I took the words out of context (until after clicking and reading), but if you were already aware of this planning-stage project then I can see how the headline would conjure train plans, not presently existing trains, for you.

Re 2-3 years, the alternative is that the delay includes some repeated work, some time where work is done inefficiently or even on hold due to confused requirements, some things with lead time that got reset, and the overhead of correcting the mistake. Still a costly screwup, of course.

Re:Spanish rail's costly blunder: New trains too large for t... by dang on Tuesday February 14, 2023 @03:45AM (#34786983)
Please make your substantive points without swipes or personal attacks.

https://news.ycombinator.com/newsguidelines.html

Re:Spanish rail's costly blunder: New trains too large for t... by handsclean on Tuesday February 14, 2023 @08:25PM (#34798838)
Ok. Sorry.
Re:Spanish rail's costly blunder: New trains too large for t... by Drunk_Engineer on Saturday February 11, 2023 @03:19PM (#34755931)
Reading Spanish language sources, I find no reporting that says the firm did any actual work on the project. The delay was due entirely to communication back and forth between Renfe, Adif, and the contractor about what size train to build. The firm notified their customer way back in 2021 about the size discrepancy, and it has taken much time to resolve.
Re:Spanish rail's costly blunder: New trains too large for t... by petre on Saturday February 11, 2023 @03:36PM (#34756091)
> it has taken much time to resolve

This is quite typical of state owned companies in Europe.

Re:Spanish rail's costly blunder: New trains too large for t... by BoorishBears on Saturday February 11, 2023 @03:30PM (#34756045)
Clearly they have been doing work if they notified the customer 2 years ago and are still going back and forth... the way this type of procurement works means that there's massive cost involved in this mistake even if not a single train has been built.

If anything you're actually proving the headline even more accurate, since you're making it clear Spain (as in the government) is the one really owning the majority of the incompetence here: when normally it's more of a mix between the firm and the customer

Re:Spanish rail's costly blunder: New trains too large for t... by favaq on Saturday February 11, 2023 @03:18PM (#34755923)
>The more interesting thing about the story is how several top government officials were fired as a result

This is false, government propaganda. https://www.antena3.com/noticias/sociedad/despedido-renfe-po...

Re:Spanish rail's costly blunder: New trains too large for t... by madaxe_again on Saturday February 11, 2023 @03:26PM (#34756009)
Yeah, I’m scratching my head at the British press laughing at them over this, but seemingly not giving two tiny damns that HS2 is now between £4,000,000,000 and £66,000,000,000 over budget depending on whose figures you trust, and counting.
Re:Spanish rail's costly blunder: New trains too large for t... by panick21_ on Saturday February 11, 2023 @04:24PM (#34756511)
British Press has been on HS2 quite a bit. Specially when you compare it to the endless highway expansion, those don't get criticized.
Re:Spanish rail's costly blunder: New trains too large for t... by madaxe_again on Saturday February 11, 2023 @04:42PM (#34756681)
True - RIS2 is also running £3,000,000,000 over the £25,000,000,000 budget — while also somehow saying that they can’t spend all of the budget on time.

It’s a nonsensical state of affairs.

https://committees.parliament.uk/committee/153/transport-com...

https://www.newcivilengineer.com/latest/transport-bosses-adm...

Re:Spanish rail's costly blunder: New trains too large for t... by panick21_ on Saturday February 11, 2023 @09:16PM (#34758891)
Reduce the high way budget by 90% and invest add the Leeds part of HS2 back.

HS2 is 100+ year infrastructure that massively improves the complete rail network of all of England and will allow England to go from backwards in terms of trains to having a fantastic overall network.

England is perfect for High Speed Rail, and rail in general. What they are missing is a few more Crossrail style projects (or S-Bahn style as we call it) in cities other then London, and more Crossrail in London.

I am advocating the same in Switzerland. We already have a great rail network, but one High Speed Line right across the major population part can improve overall rail infrastructure by a huge amount.

Switzerland has rail modal share of ~20% and with a new high speed line and a host of other things, that could be raised to 30-40%.

The capacity you gain on all the old lines for regional and cargo travel is huge.

Re:Spanish rail's costly blunder: New trains too large for t... by madaxe_again on Sunday February 12, 2023 @03:35AM (#34761087)
I support HS2 in principle, but the practical outcome is dire - they are having trouble securing rolling stock, and it looks like due to noise concerns they’re only going to run something like four (diesel) trains a day on it, at 60kph - and then they’ll declare it unprofitable and beeching it, most likely.

This is just how public infrastructure projects in the U.K. work, I’m afraid.

Re:Spanish rail's costly blunder: New trains too large for t... by panick21_ on Sunday February 12, 2023 @11:34AM (#34764150)
I don't believe that. If the lines that get built they will 100% not run diesel trains on it and it will run as often as planned. At least after a few years. And if a project is done for the next 100+ years, then a few years lower utilization isn't a big deal.

Seems to me all the claims made about how it will fall short and be barley better then a old Victorian line is scare mongering to devalue the project and discredit the benefits it gives.

What is really sad is that the Greens are against it, what utter idiots. Hopefully you can elect some government that actually gets behind the project fully again.

> and then they’ll declare it unprofitable and beeching it, most likely

I don't believe that. NetworkRail was unprofitable, made public still exists. Franchise, unprofitable, made public again still exist. So the idea of these lines simply going away isn't really credible.

Re:Spanish rail's costly blunder: New trains too large for t... by simplotek on Sunday February 12, 2023 @07:15AM (#34762269)
> Clickbait headline -- the error was caught during the design phase.

I don't agree. This is a colossal blunder. Train clearance is a very basic trait of each railway line, along with track gauge. Ordering trains that you cannot even operate in your railway lines is perhaps the biggest screwup any railway operator can possibly make.

I'm not sure you fully understand the magnitude of this sort of screwup. Catching the problem in the design stage actually means it took the manufacturer to double-check the contract to realize his client did a gross unrecoverable mistake that resulted in their orders being fundamentally incompatible with their intended use.

The only clickbaity aspect of this article was tacking another notorious episode of Spanish mishaps which was their submarine design being fundamentally broken. It reads more like a cheap jab at Spain than anything else.