Re:2025 Iberia Blackout Report by AnotherGoodName on Monday June 23, 2025 @05:07PM (#44360099)
Reads very similar to some blackouts we had in Australia. Weakly connected grids with vast geographical distances leading to oscillations that took down the grid.

https://en.wikipedia.org/wiki/2016_South_Australian_blackout

Completely solved with lithium based grid storage at key locations btw. This grid storage has also been massively profitable for it's owners https://en.wikipedia.org/wiki/Hornsdale_Power_Reserve#Revenu...

Australia currently has 4 of the 5 largest battery storage systems under construction as a result of this profit opportunity; https://en.wikipedia.org/wiki/Battery_energy_storage_system#...

You can also read numerous stories of how Australia's lithium ion grid storage systems have prevented blackouts in many cases. https://www.teslarati.com/tesla-big-battery-south-australia-... The fact is that the batteries responsiveness is the fastest of any system at correcting gaps like this. 50/60hz is nothing for a lithium ion battery nor are brief periods of multi-gigawatt draw/dumping as needed.

There's even articles that if Europe investing in battery storage systems like Australia they'd have avoided this. https://reneweconomy.com.au/no-batteries-no-flexibility-spai...

Re:2025 Iberia Blackout Report by londons_explore on Monday June 23, 2025 @05:14PM (#44360187)
> nor are brief periods of multi-gigawatt draw/dumping as needed.

Actually this is typically an issue for grid batteries.

Spinning generators can easily briefly go to 10x the rated current for a second or so to smooth out big anomalies.

Stationary batteries inverters can't do 10x current spikes ever - the max they can get to is more like 1.2x for a few seconds.

That means you end up needing a lot of batteries to provide the same spinning reserve as one regular power station.

Re:2025 Iberia Blackout Report by z_rex on Monday June 23, 2025 @07:35PM (#44361327)
A spinning generator is not outputting 10x it's rated current over any significant amount of time. You can only add so much steam or fuel to a turbine, and the rotor has a lot of inertia, but not enough to account for 10X its rated capacity for a second. The electrical switchyards would trip nearly instantaneously if it's connected plant output 10X its rated input.
Re:2025 Iberia Blackout Report by egberts1 on Monday June 23, 2025 @07:45PM (#44361386)
You can if the load was 10x under max. before getting tripped.

Misaligned oscillation can occurs under ANY load.

Re:2025 Iberia Blackout Report by javawizard on Monday June 23, 2025 @07:53PM (#44361436)
Batteries would also be able to 10x if their load was 10x under max, so I'm not sure how this is relevant to GP's point.
Re:2025 Iberia Blackout Report by lobochrome on Monday June 23, 2025 @08:11PM (#44361538)
The inverter would melt presumably.
Re:2025 Iberia Blackout Report by Geezus_42 on Monday June 23, 2025 @08:22PM (#44361603)
Just looking for an excuse. Lol
Re:2025 Iberia Blackout Report by zekrioca on Monday June 23, 2025 @08:27PM (#44361632)
Let alone the transmission lines totally catching fire after a 10X output increase.
Re:2025 Iberia Blackout Report by Gud on Tuesday June 24, 2025 @03:23AM (#44363664)
Where are you getting this information from?

Although I’m hardly an expert on power lines(my factory produces HV switchgear), a 1s short circuit current rating of 10x(actually more) is normal, standard to IEC norms.

Re:2025 Iberia Blackout Report by zekrioca on Tuesday June 24, 2025 @07:42PM (#44372249)
Arcing.
Re:2025 Iberia Blackout Report by scotty79 on Wednesday June 25, 2025 @04:00AM (#44374736)
I think they meant 10x current not 10x voltage, so no arcing.
Re:2025 Iberia Blackout Report by cyberax on Tuesday June 24, 2025 @02:23AM (#44363342)
A properly running grid with spinning generators never needs the 10x rated current. More importantly, oscillations are dampened by the rotating masses.
Re:2025 Iberia Blackout Report by AnotherGoodName on Monday June 23, 2025 @05:22PM (#44360272)
Collectively Australia's battery storage systems will be able to beat any single power plant for peak output in Australia once fully built out based on pure numbers. But for these sorts of grid oscillations the more important thing is the localization of generation. Which obviously favours the batteries over large centralized power stations in any case.
Re:2025 Iberia Blackout Report by adev_ on Tuesday June 24, 2025 @03:15AM (#44363611)
Being enthusiastic about battery technologies is one thing, spreading misinformation to support someone convictions is an other.

What causes the Iberian blackout is excessive reactive power and a lack of compensation at a given time (due to multiple factors).

Compensation of reactive power has strictly nothing to do with localization of generation. It barely even can be assimilated to oscillations

That's complete garbage and it shows mainly you do not seem to know much about Electricity power in general.

Re:2025 Iberia Blackout Report by ajross on Monday June 23, 2025 @06:40PM (#44360936)
That... doesn't sound correct. Inverters are the cheap part, you can literally wire as many as you want in parallel. Batteries have immense power availability, with most chemistries you can trivially deliver the entire capacity in half an hour or so (more like 5 minutes with lithium cells).

Basically I'm dubious. I'm sure there are grids somewhere that have misprovisioned their inverter capacity, but I don't buy that battery facilities are inherently unable to buffer spikes. Is there a cite I can read?

Re:2025 Iberia Blackout Report by AnotherGoodName on Monday June 23, 2025 @06:51PM (#44361006)
Agreed. The relatively small battery substation linked above can output 2GW of equivalent inertia generation (a measure to align batteries to inertial power systems) when needed. That's an entire power station they can match for short periods of time. Link: https://www.energymagazine.com.au/sa-approves-world-first-ba...

Australia's largest power plant has 2.9GW of inertial generation assuming all generators are running at 100%. As in the small battery substation alone comes close to the countries largest power station. I'm not sure where the idea that lithium ion can't dump power quickly comes from. They are absolutely phenomenal at it. Australia's building dozens of these substations too since they are so cheap and reduce overall power costs. It's a win from all points of view.

Re:2025 Iberia Blackout Report by tacticus on Monday June 23, 2025 @11:34PM (#44362652)
> assuming all generators are running at 100%.

which they won't ever be given the habits of coal plants to suffer outages whenever it's convenient to pump the price up.

Re:2025 Iberia Blackout Report by bob1029 on Tuesday June 24, 2025 @03:30AM (#44363704)
The article does not describe an inertia constant. Without the time component, any comparison to traditional systems is meaningless. Inertia is a measure of energy, not power.

Large spinning masses can provide several seconds of inertia. For 2GW of traditional turbine, you would have between 10-20 gigawatt-seconds of energy that is instantly available at any moment to resist RoCoF.

Re:2025 Iberia Blackout Report by ajross on Tuesday June 24, 2025 @08:11AM (#44365282)
The switching rate of a good power MOSFET has a bandwidth in megahertz. It's... all solid state electronics. Again, this is just wrong, absent someone showing a cite. It's very weird seeing this kind of seeming ignorance of basic electrical engineering on a hacker site of all places.
Re:2025 Iberia Blackout Report by probablypower on Monday June 23, 2025 @06:52PM (#44361016)
You can google "system inertia" as a starting point.
Re:2025 Iberia Blackout Report by rcxdude on Monday June 23, 2025 @07:10PM (#44361151)
This is what batteries can provide very well.
Re:2025 Iberia Blackout Report by ajross on Monday June 23, 2025 @08:22PM (#44361598)
I understand the concept. I was asking for a cite about the seemingly-incorrect point about batteries. FWIW, that very search term doesn't produce the string "battery" anywhere on the first page.
Re:2025 Iberia Blackout Report by epistasis on Monday June 23, 2025 @08:30PM (#44361656)
When it comes to the grid, there's a lot of outdated information left over from the 20th century, so any web search for "system interia" needs to also include some searches on "grid forming inverter"' to make sure that the info is complete.

(And "reactive power" could be good too but not absolutely necessary to understand at first...

Re:2025 Iberia Blackout Report by eldaisfish on Monday June 23, 2025 @07:13PM (#44361174)
it is technically correct, but so are you.

More inverters in parallel will achieve the same end goal - fast frequency response.

Re:2025 Iberia Blackout Report by ajross on Monday June 23, 2025 @08:23PM (#44361607)
Are you actually certain there are insufficient inverters though? Again, that doesn't pass the smell test and I'd want to see a cite for "batteries don't work for high frequency spike buffering because of inverter shortfalls" or something.
Re:2025 Iberia Blackout Report by eldaisfish on Monday June 23, 2025 @09:29PM (#44362009)
i'm certain there are more than enough inverters.

what's correct is that each individual inverter can only increase its power output momentarily to 20% or so above its maximum. Add more inverters and that problem is solved.

Re:2025 Iberia Blackout Report by bob1029 on Tuesday June 24, 2025 @01:46AM (#44363159)
> Inverters are the cheap part

The whole point with actual inertia is that you get a large multiple of your maximum capacity without any redundant parts or added system complexity.

Keeping around 10x+ more semiconductors than you need to cover a tiny fraction of operational scenarios is difficult economics.

A semiconductor device cannot be overloaded like a spinning generator or transmission infrastructure can. You cannot trade temperature and maintenance schedule for capacity in the same way. Semiconductors have far more brittle operating parameters.

Re:2025 Iberia Blackout Report by ajross on Tuesday June 24, 2025 @08:15AM (#44365323)
> Keeping around 10x+ more semiconductors than you need to cover a tiny fraction of operational scenarios is difficult economics.

Not according to the prices I see. Digikey tells me I can switch a MW of power for about the price of a MBP. I ask again, is there a citation for this nonsense?

Re:2025 Iberia Blackout Report by giantg2 on Monday June 23, 2025 @05:36PM (#44360408)
Seems like pumped hydro offers a nice compromise.
Re:2025 Iberia Blackout Report by AnotherGoodName on Monday June 23, 2025 @05:44PM (#44360472)
Fwiw the hornsdale battery linked above cost AUD$172 million and can provide 2000MW of equivalent inertia. Link: https://www.energymagazine.com.au/sa-approves-world-first-ba...

That equivalent inertia can only be done for short periods but that's exactly what grids need in stability - there's generally no lack of total generation, just a need to jump in and smooth out spikes.

You can't build a dam for that price, nor could you do it in under 100 days from contract signing as that battery was built. Batteries are definitely the answer here. The 'more spinning mass' answers don't make sense since Australia literally solved the above problem in a much cheaper way already.

Re:2025 Iberia Blackout Report by giantg2 on Monday June 23, 2025 @06:02PM (#44360644)
You don't need to build a dam, you just need the pipes and pumps for an existing dam (or elevated natural basin).
Re:2025 Iberia Blackout Report by _carbyau_ on Monday June 23, 2025 @07:47PM (#44361392)
I thought you needed two dams. One higher than the other. You pump water back and forth between the two to generate or capture energy.

Is it that common that dams are already existing in nearby-ish pairs with the sufficient height difference? And that we haven't done this already?

Doing this is good where we can. But it has geographical limitations. Batteries don't so much.

Re:2025 Iberia Blackout Report by Rodeoclash on Monday June 23, 2025 @08:16PM (#44361565)
My layman's understanding is that most locations that are suitable for pumped storage already have pumped storage built on them.
Re:2025 Iberia Blackout Report by MobiusHorizons on Monday June 23, 2025 @08:57PM (#44361834)
Yep, this is the issue. That and land cost. Also pumped hydro is most useful when you need very large capacity storage, whereas for preventing blackouts you need very high capacity fast generating to fix oscillations or to allow more generating capacity to come on line. They are basically acting as decoupling capacitors (except for AC) in this application.
Re:2025 Iberia Blackout Report by Polizeiposaune on Monday June 23, 2025 @08:27PM (#44361630)
You need two sufficiently large bodies of water close to each other at different elevations. You don't necessarily need two dams - for instance, the Ludington pumped storage plant adjacent to Lake Michigan uses the lake as the lower body.
Re:2025 Iberia Blackout Report by floatrock on Monday June 23, 2025 @07:16PM (#44361197)
Most economically-suitable locations for pumped hydro have been built out already.

You can always use a ton more concrete and force new locations, but the best locations have already been utilized and scaling law of batteries has brought them to the point where they're more competitive than new hydro for this kind of use.

Re:2025 Iberia Blackout Report by bryanlarsen on Monday June 23, 2025 @09:20PM (#44361972)
Most economical locations for hydro generation have been built out already. Pumped hydro doesn't require flow like generation does, so there are thousands of times more suitable locations. Those haven't been built out.
Re:2025 Iberia Blackout Report by Maxion on Tuesday June 24, 2025 @12:51AM (#44362940)
At least in my country they have. They keep trying to build a facility but anything they come up with, the ROI just isn't there.
Re:2025 Iberia Blackout Report by bryanlarsen on Tuesday June 24, 2025 @11:17AM (#44367165)
In other words, there are lots of places they could build, but it's just too expensive to build and/or the value of long term electricity storage is too low.
Re:2025 Iberia Blackout Report by plorg on Monday June 23, 2025 @07:17PM (#44361203)
Sure, if you can site it.
Re:2025 Iberia Blackout Report by outside1234 on Monday June 23, 2025 @10:24PM (#44362342)
What batteries CAN do however is go from 0W to their capacity watts in milliseconds. It is their instant-on ability that is disruptive.
Re:2025 Iberia Blackout Report by IndrekR on Tuesday June 24, 2025 @04:29AM (#44364002)
Not only from 0W, but from negative capacity (max charging power) to positive capacity (max discharging power).
Re:2025 Iberia Blackout Report by pjc50 on Tuesday June 24, 2025 @06:36AM (#44364686)
> Spinning generators can easily briefly go to 10x the rated current for a second or so to smooth out big anomalies.

I'm very suspicious of this, because it would also imply 10x overcurrent on the associated transmission gear. There's limits on how much you can overcurrent a transformer before the core magnetically saturates, for example. Also I would expect protection systems to trip out at such a huge divergence from rated current. Do we have a citation?

Re:2025 Iberia Blackout Report by xwolfi on Monday June 23, 2025 @08:19PM (#44361587)
But Australia is tiny: 27M people. Just Spain is twice as big, and the European grid serves 500M people, we don't have the same problems, and probably can't solve them with the Australian solutions.
Re:2025 Iberia Blackout Report by laurencerowe on Monday June 23, 2025 @09:34PM (#44362040)
I wouldn't dismiss lessons from Australia. It has slightly higher electricity consumption than Spain (273 vs 265TWh/annually [1].) And there are limited interconnections to France [2]:

> That problem may not have been entirely Spain’s fault, El País said. “Interconnections with the rest of the continent continue to be much fewer than the European Commission recommends, not because Spain isn’t interested, but because France has for years resisted expanding them.”

[1] https://en.wikipedia.org/wiki/List_of_countries_by_electrici...

[2] https://www.theenergymix.com/massive-blackout-in-spain-shows...

Re:2025 Iberia Blackout Report by cyberax on Tuesday June 24, 2025 @02:35AM (#44363406)
> Completely solved with lithium based grid storage at key locations btw.

That's because Australia has a moderate amount of renewables and prefers to burn fossil fuels. Right now, around 25% of the electricity in Australia is generated by solar or wind.

Spain is past 50% of renewable generation, and their problems are much bigger.

Re:2025 Iberia Blackout Report by AnotherGoodName on Tuesday June 24, 2025 @12:08PM (#44367707)
The state where this was occurring before the battery build out is over 70% renewables.

https://en.wikipedia.org/wiki/Energy_in_South_Australia