To respond to your exact point, big parts of the nuclear-qualified workforce in most places really do move from large job to large job (assuming relatively static demand), so you do get that transfer of knowledge on sequential jobs.
Also, don’t forget the design and manufacturing that happens off-site, which can be significant and often is a huge driver of risk and cost. (10 MW vertical motors! Big safety-related pumps! Mega-sized forged components! Specialized custom fabrications!) The back office engineers and subcontractors and factory floor people who make them remain pretty static as long as there is work to be done. By the Nth unit, there is know-how and known problems are worked out; some of this is translatable into drawing updates and schedule resequencing but really a lot of it is expertise that stays in peoples’ heads. Once everybody is demobed and scatters, that is all lost.
https://news.usni.org/2019/01/31/navy-awards-2-carrier-contr...
The link says the savings from Newport would be $1.6B.
It also quotes the Navy acquisitions chief pointing out "about a third of the cost of a carrier comes from government-furnished equipment that the Navy would contract for separately" and that he previously said the overall savings of ordering two at once would be around $2.5B after considering similar efficiencies of "scale" from those vendors.
Considering the cost[1] of these Ford-class carriers is around $13B this represents a savings of about 10% overall, at least according to my crude, back-of-the-napkin math [ 2.5B/(2x13B) or 1.6B/(2/3x2x13B) ].
So it might be closer to "buy 10, get one free".
[1] https://en.m.wikipedia.org/wiki/Gerald_R._Ford-class_aircraf...
To be fair, the building of the actual carrier is just part of the price of a carrier. What's the cost to also fit that carrier out with all of the various aircraft required to make the carrier worth having? Didn't we see an example of this when the NSA donated Hubble equivalent satellites to NASA, but NASA had to politely say no since they had no budget to operate them?
It was the NRO not the NSA and NASA did accept the donation. They announced the mission schedule for one of the satellites in 2016 [1]
[1] https://spaceflightnow.com/2016/02/18/nasa-moves-forward-wit...
Right idea! The answer is "hardly anything, relative to crewing it for its useful lifetime", but you're barking up the correct tree.
Not to mention the hundreds of small decisions related to "X part supplier went out of business. Y part is similar with a slightly different alloy and mechanical properties, is it a suitable replacement? how can we verify this?"
The original design teams would have auxiliary artifacts that were vetted, and tribal knowledge to help quickly answer these questions. Subsequent design teams will not. The timescales between plant construction exceeds most engineer's memory at 5-10 years.
We have newer reactor designs, materials, and engineering knowledge today that could significantly reduce cost just in material savings or construction time.using something like FAST reactor, is significantly different that the older tech and could save 90% on fuel and waste.
Unfortunately most of the new reactors built in the US and Europe have run massively over time and over budget, despite new technology. Vogtle 3&4 in Georgia drove Westinghouse bankrupt. These were modern AP-1000 models. Flamanville 3 in France (an EPR) is running nearly triple its cost estimate and the delivery time ballooned to 15 years. Olkiluoto in Finland (the first EPR) went massively over time and budget as well. These reactors were specifically designed to be more cost-effective and promised much lower prices, but failed to deliver.
The problem in the nuclear industry isn't the technology itself, but the fact that they consistently fail to deliver projects within their allotted time and budget. Unfortunately this shows no signs of changing, and renewable energy industry looks poised to completely out-compete them in the energy market.
I say this all as someone that used to have high hopes for nuclear tech, after working in nuclear physics research all throughout university.
Thus, breeders generally end up being more expensive than a conventional BWR or PWR.
Here I should mention that I spent some time in nuclear physics research. There's a lot of misinformation floating around about nuclear energy. Most of the "miracle solutions" don't live up to their promises (especially thorium tech and breeders). If they did, we'd already be using them -- nuclear engineers are not fools, and most of these reactor concepts have been kicked around for literally decades.
One other point: the physics behind breeders and conventional slow-neutron reactors isn't fundamentally different. Both neutron capture ("breeding") and fission ("burning") reactions happen in both, the ratios in a breeder are just optimized to favor the first process more. In fact in conventional light water reactors, around a third of the energy released comes from fissile isotope bred from fertile isotopes such as U-238.
I'm not saying that the engineers are idiots. But there are some engineers (supported by government or corporate funds) still building new prototypes and testing new designs, such as FAST. Especially in the US, a driving reason that new designs aren't used is that there have been few built I'm recent decades - partially due to lower cost alternatives and also due to public opinion.
> eliminating the need for ever increasing safety tech and complexity of it for conventional reactors would be a cost savings
Passive safety features are useful, but they don't end up replacing active features (you still need to control the reactor during normal use). At best they might allow for reducing the redundancy level on a critical system -- which might save a bit bit of money, although not much.
Better safety is always a great feature in general, but it's not close to making breeders cost competitive on its own.
> Not to mention the clean up costs when you compare to a conventional reactor that could melt down, even if it's rare.
Actual meltdowns are exceedingly rare (and catastrophically expensive + devastating), so you don't really factor them into the cost equation for a normal reactor.
> Especially in the US, a driving reason that new designs aren't used is that there have been few built I'm recent decades - partially due to lower cost alternatives and also due to public opinion
Mostly cost tbh -- nuclear energy has been historically somewhat unpopular (especially after major accidents) but there's a lot of industrial projects that continue anyway despite being unpopular (oil pipelines etc). The financials for nuclear reactors are not great (it's a big, financially high-risk investment that takes decades to really pay off), so there's less incentive.
https://www.sciencemag.org/news/2020/11/several-us-utilities...
> announced that completion of the project would be delayed by 3 years to 2030. It also estimates the cost would climb from $4.2 billion to $6.1 billion.
Unfortunately it has become a pattern now for the nuclear industry to promise that the next tech will suddenly make nuclear energy cheap and fast to build. They consistently have failed to deliver on their promises -- the fiasco of the AP1000 reactor build at Vogtle in Georgia is a recent example.
It seems like the problem of the nuclear industry is the industry, not the technology itself. They're too used to relying on fat taxpayer subsidies, and are not well equipped to compete against other energy sources on the free market.
Also...
* Often the starting point is a poorly organized mess that needs to be unpicked and understood.
* People conduct "reviews" of existing work that consumes budget and leads to new issues being found.
* You are continuing an existing chain of communication, but with a loss of continuity. The people you need to ask can't remember, or are not available to ask.
* Overly optimistic budgets lead to corner cutting and mistakes.
I assume we'd lose power during the transformer steps, but would it preclude building the plants away from people and groundwater reservoirs?
It's not as attractive for managing nuclear accident risk as you might think, as nuclear is already struggling with cost competitivenss even without HVDC lines, and risk reduction per buck of other safety design features are better.
But it's brilliant for eg hydro (for obvious reasons), wind power (because 2000 km away it'll be windy when you have local lulls and vice versa) and solar (2 time zones worth of distance balance out production/consumption peaks nicely).
> France aims to rapidly develop renewable wind, solar and biomass capacity to curb its dependence on atomic power, reducing its share in its power mix to 50 percent by 2035, from 75 percent today.
We have to look at France and how much carbon it produces. Right now it is one of the lowest producers in Europe. Let's look at the electricity map[0]. Sweden, Norway, and France are leagues ahead of others in terms of carbon emissions. France's plan is first to replace existing natural gas, biomass, and coal with renewable resources. The second part of the equation is that their reactors are reaching EOL, so do you build more or replace them? If you pay attention to energy trends solar and wind (something France has an abundance of) is getting much cheaper and battery storage is getting cheaper (France doesn't have to bet as much on battery storage since they can over produce and sell excess energy, which they currently do a fair amount of). So if you're going to take bets this is still a good bet. A big part of a good and stable power grid is by having a diversification of energy resources. 75% of your energy being dependent upon one resource is not a good idea. No matter the resource. Even 50% is high, but acceptable. They aren't planning from going away from reactors, there's even one under development. But you also want to hedge your bets. If any of these factors (solar, wind, battery storage, smart grids, ITER, etc) don't pay off, then they need to maintain their nuclear grid. It would take a large revolution in energy development for France to be able to still produce so little carbon and provide its citizens with a modernized (electrified) country.
Also consider that France doesn't have good access to hydro like Norway and Sweden do so its options for clean energy are nuclear, solar, and wind (lots!). They should, and are planning on, using a diversification of these. Nuclear provides a strong baseload and the others supplement. You may notice that this is a key argument made by many proponents of nuclear. Anyone that says the grid should be entirely nuclear is an armchair scientist who understands very little about nuclear or the climate. But the same is true for those that think we can solve the issue with just solar and wind.
So if you're saying France is turning away from nuclear, then this is adding desires into a plan that does not express or concern itself with those desires. A big part of this decision is about diversification and increasing energy independence (just like recycling fuel is a big part of their energy independence, which they power a whopping 17% of their grid with recycled nuclear alone).
The UK is doing fine with a renewables-heavy powergrid, as are Spain and Portugal. 40% of their electricity comes from this, and the share is rising steadily.
> However, the bill also calls for "realistic goals to transform our energy model by increasing the timeframe for reducing nuclear power to 50% by 2035 instead of 2025, which would have required the construction of new gas-fired plants, and would have involved an increase in our greenhouse gas emissions."
I'm sure World Nuclear News is more favorable to nuclear power, but I don't see how that is relevant. Do you believe that this article fabricated the contents of the French bill?
This comes off more as a cheap jab than a substantive claim of bias.
Legislation gets written and rewritten as timelines get tweaked. That's a reality. The core goal is unchanged.
They literally are, and have formally said so. They're not shutting down all their reactors right away or anything. But for a country that took pride in betting big on nuclear, officially planning to go from 70% nuclear to 50% is a pretty huge drop. They've already shut down the first two reactors at Fessenheim as part of this.
Yes, they're kicking the can down the road slightly at last news. That's not surprising since many of the reactors may be possible to life-extend to 50 years, and renewable energy costs are dropping quickly. Delaying a few years saves some money. But that does not change the fact that many of the reactors will not be replaced when they hit end-of-life.
> They literally are, and have formally said so
Citation needed.
As I stated in another reply to you, reducing dependence on nuclear has a lot of advantages unrelated to "nuclear is bad" or "nuclear is not clean" or etc. Like I said before, no matter what your energy source is, 75% of your power being produced from a singular source is not a good idea. You may be familiar with the old saying "don't put all your eggs in one basket." This is the same reason we don't invest in a single stock. Dropping to 50% is far from getting rid of nuclear and it is an absurd claim.
> But that does not change the fact that many of the reactors will not be replaced when they hit end-of-life.
Many, but many are planed to be replaced. You're focusing too much on the reduction aspect. Reduction is not elimination. France has no plans on eliminating nuclear in the foreseeable future. The only way this would happen is if ITER was a major success and small versions could reliably be developed and deployed. I'm not counting on that.
I already provided a citation for this - https://www.reuters.com/article/france-electricity-solarpowe...)
Quote
>> France aims to rapidly develop renewable wind, solar and biomass capacity to curb its dependence on atomic power, reducing its share in its power mix to 50 percent by 2035, from 75 percent today.
A quick google will turn up dozens of other sources discussing that if you like.
> reducing dependence on nuclear has a lot of advantages unrelated to "nuclear is bad" or "nuclear is not clean" or etc
When did I even say that? Please have the decency NOT to convert my educated and reasoned points into a straw-man argument. I spent years working in nuclear physics. I'm not making some idiotic "nuclear reactors will turn us into glowing mutants" argument here.
The real issues with nuclear are -- and always have been -- simple, practical problems of cost, time to construct, and the usual problems of cost overruns and delays that you see with constructing a very complicated system. The Flamanville EPR has been a fiasco, with costs triple its original estimate and a timeline that ballooned to 15 years.
In comparison, the competition from renewable energy has heated up rapidly. Economies of scale are rapidly driving down the costs renewables and batteries (and the underlying technology is improving rapidly). Between 2010 to 2019 wind energy become 70% cheaper and solar became 89% cheaper: https://www.lazard.com/media/451082/lcoe-8.png
Battery costs have dropped 75% over the last 6 years: https://www.greentechmedia.com/articles/read/report-levelize...
Nuclear energy in 2020 is often quite expensive compared to renewable energy, and the comparison is only getting worse over time.
> France has no plans on eliminating nuclear in the foreseeable future.
In 2020, Energy Minister Élisabeth Borne announced the government would not decide on the construction of any new reactors until Flamanville 3 starts operation after 2022. Citation: https://www.neimagazine.com/news/newsfrance-to-decide-on-new...
"France has undertaken to cut the nuclear share in its electricity mix from around 75% to 50% by 2035 while increasing the share of renewable solar, wind and biomass."
“Whether we are looking at 100% renewables or a percentage of new nuclear, we want to consider all the elements, including technical, economic,” she noted. “On such important subjects, we must make rational, reasoned decisions, and that is the objective of the various studies that have been launched.”
To put that all together: France is cutting their use of nuclear, and waiting to decide whether or not to replace reactors that are fast approaching end-of-life. They're going to look and see how the energy market shakes out.
>>> They literally are, and have formally said so
>> Citation needed.
>> reducing dependence on nuclear has a lot of advantages unrelated to "nuclear is bad" or "nuclear is not clean" or etc
> When did I even say that?
Wow this conversation is a mess.
Unless building a nuke plant is a common thing where the crew that built a plant in Georgia can then go build one just like it in Alabama then one in Tennessee, then in Ohio, etc, then I don't see how building two plants with identical layouts can leverage economies of scale. For example: Wolf Creek NGS in Kansas and Calloway NGS in Missouri were apparently the first two plants in the US to be built using the same blueprints. If two more plants were built today with those same blueprints but by different construction crews who don't have any of the tribal knowledge from the construction of Wolf Creek and Calloway then what you have are four essentially bespoke plants that just happen to use the same blueprints.