Then came a showdown late last year between the utility and Microsoft, whose hardball tactics shocked some local officials.
In an attempt to erase a $210,000 penalty the utility said the company owed for overestimating its power use, Microsoft proceeded to simply waste millions of watts of electricity, records show.
If a customer moves in and says "oh yeah, I'm gonna need an average of 100 MW 24/7 for the next 20 years" and then turns out to only use half that, the utility is now short a bunch of a money that it spent upgrading its distribution infrastructure for that customer's supposed needs.
And, the utility put Microsoft in the position of wasting $70,000 of power or paying a $210,000 fine.
Exactly what did they EXPECT was going to happen?
As much as I like to slag Microsoft, any rational human being is going to react that way when presented with those incentives.
That's a really interesting point. I wonder if we'll see utility companies get into bitcoin mining as a way of profiting from their excess capacity during non-peak times.