I doubt that is true https://en.wikipedia.org/wiki/Diablo_Canyon_Power_Plant#2021... talks about a report that states "that keeping Diablo operating until 2045 would save the state a cumulative $21 billion," and I doubt they'd make a projection like that if the plant would be worn out in 2025.
It's probably not end of life, it probably just needs maintenance and recertification. This nuclear plant (https://en.wikipedia.org/wiki/Turkey_Point_Nuclear_Generatin...) has some reactors that were built earlier, and are apparently now licensed to operate for a total of 80 years.
> Building a new nuclear power station is logistically impossible. Without getting into it, in essence the U.S. has lost the ability to construct nuclear power stations. People cite the regulatory nightmare, but that's not the real issue - that's an excuse. The real issue is much more complicated.
You make this claim, but you don't really support it. Why is this a "lack of ability" rather than a lack of political will?
Even in countries that are massively pushing for nuclear energy and where the utilities are sometimes outright government-owned, like in France, Finland or the UK, nuclear reactor projects have continuously hit massive cost and deadline overruns: Finland's Olkiluoto 3 had 12 years delay and ended up costing over three times as expected, French Flamanville will end up at over six times the estimated budget and at least eight years delay, and UK's Hinkley Point can't even be reliably estimated.
The only ones being able to build out plants is China, and for what it's worth I think they will manage to blow up at least one of them due to shoddy construction.
Accounting for all these risks takes up serious amounts of money, enough to make the construction of a new plant so expensive it literally cannot ever turn a profit against incredibly cheap solar energy and ever-cheaper battery or molten-salt storage.
One might even say that nuclear energy was never profitable because the only way it appeared to be cheap was that the general public took up an extremely risky bet that the reactors would not go boom and because the costs for teardown and storage were never really accounted for.
Coal plants cause orders of magnitude more premature deaths, but since they happen in hospitals and cancer treatment centers rather than homes, nobody cares. You can't make a 'Chernobyl' miniseries about cancer and emphysema patients scattered over an entire country (or planet.)
We haven't, really. We were quite lucky.
What if the Chernobyl disaster had reached the Pripyat river, and in turn contaminated the Dnieper? We are all familiar with them geography of Ukraine now.
What if a radioactive cloud from Fukushima had reached Tokyo?
What would have been the cost of a temporary evacuation of Tokyo?
Nuclear radiation isn’t a boogeyman, and isn’t the most dangerous type of contamination by a long shot. I would be way more worried about a chemical spill or a industrial accident that released toxic gas.
>China’s Climate Goals Hinge on a $440 Billion Nuclear Buildout
https://www.bloomberg.com/news/features/2021-11-02/china-cli...
But that's not necessarily accurate, either. My dad worked in the nuclear industry all his career and specifically within the licensing group for maybe five or ten years. His job was, for a time, to relicense the plant that he worked at so they could continue after their 40 year initial licensure period.
Maybe Diablo happens to be end of life due to other issues, but saying that the license is up is not the same as it being end of life.
If nuclear can't guarantee baseload, then how is it a better investment than much cheaper renewables?
> at least a factor in that decision anyway.
What were the other factors? Were the plummeting LCOE of renewables and storage part of it? Also what about the (previously low) price of natural gas?
Now that natural gas is expensive, it seems like keeping Diablo Canyon operational for another 20 years is back in the table if federal funds can be used to subsidize it:
https://www.utilitydive.com/news/analysts-differ-on-feasibil...
* Cost to extend the operating license of the plant. The NRC will likely mandate modifications be made in order to keep the plant running safely for another 20-40 yers.
* Public Relations. There's strong public opposition to nuclear power. PG&E already has a poor image in California. Closing the plant would be expected to generate some goodwill toward PG&E.
* Soaring insurance costs/increased liabilities. California has made it abundantly clear to PG&E that if Diablo were to have any problems affecting the public in any manner whatsoever then they are totally on the hook for the financial impacts. Look at what happened with the wildfires caused by arcing transmission equipment. Now imagine the costs associated with a nuclear "incident." That's simply too much risk.
Between the high financial risk and decreased dispatch that's a one-two punch that makes continued operations untenable.
* VC Summer in South Carolina: failed due to corruption and construction/design incompetence
* Vogtle in Georgia: might finish, but every few months gets delayed more for a grab bag list of reasons. See, for example:
https://thecurrentga.org/2021/12/03/construction-quality-iss...
* Flamanville in France: who knows what went wrong here
* Hinkley Point C in the UK: not looking great
* Olkiluoto in Finland: it finally finished and works! Yay!
https://thecurrentga.org/2021/12/03/construction-quality-iss...
Even in France's first generation of building, of the same design, costs rose as they built more. Nuclear just can not seem to find its groove of being reliably constructed or planned.
Here in Europe eyes seem to have been wrenched open and the resistance against nuclear power is being seen for what it is by many, a form of Luddism which is partly pushed by fossil fuel industries. Several countries - the Netherlands and the UK among them - are now planning to build new nuclear power stations. France seems to have been saved from the brink of switching their mostly nuclear power fleet to non-nuclear and is now planning to continue its reliance on nuclear power. Then there is Germany, the black sheep (probably due to it grazing next to a coal-fired power station) of Europe where 'die Grüne' (the Green party) and their ideological allies have managed to increase Germany's emissions substantially by forcing the closure of all nuclear power stations. Germany is one of the better examples on how not to manage power production and distribution.
Consulting the current list of nuclear power plants under construction around the world by a pro-nuclear power agency here: https://world-nuclear.org/information-library/current-and-fu...
I see the following as the only ones still under construction in all of Europe (not counting Belarus and Russia): 1) Mochovce 3 in Slovakia. Construction started November 2008, originally scheduled to complete in 2012, now hopefully complete later this year, so 15 years total, 10 years late. 2) Flamenville 3 in France. Construction started in 2007, originally scheduled to complete in 2012. Hopefully complete in 2023, so 16 years later, 11 years late. 3) Mochovce 4 in Slovakia. Construction started November 2008, original scheduled to complete in 2013, now hopefully complete in 2023, so 16 years total, 10 years late. 4,5) Hinkley Point C1 and C2 in the UK. Construction started in roughly 2008[1], originally expected to be online 2022 or so ("early 2020s" is the best I can find with Google now, and that's for both C1 and C2 to be online). Now C1 is expected to be complete in 2027, and C2 in 2028. So 19-20 years total, 6 years late.
(The US has two reactors on the list, Vogtle 3 and 4, started in 2009, originally expected to finish in 2016 and 2017, now expected to finish in 2023.)
South Korea has 4 reactors under construction right now (plus two they are building in the UAE). India has 8, China has 19, and Russia has 3 (plus 4 they are building in Turkey, 1 in Belarus, 2 in Bangladesh). Argentina has their first indigenous design under construction- and that appears to be it, as far as nuclear power plant construction goes around the world.
One or more of those countries might have things figured out, but whatever problems the US has seem to be happening across the developed world (minus potentially South Korea), which suggests that it really is not a case where firing a few rogue regulators will fix things.
[1]: The Hinkley Point story is a complete flustercluck of nonsense.
Come on now, don't leave us hanging like that!
It doesn’t have to be this way.
Anybody who says it does should not be allowed near anything in even the lowest levels of government/bureaucracy
Gas being burned to heat something is way more efficient than gas being burned to turn turbines to make electricity to be transported hundreds of miles to a restaurant only to be used to heat coils at 1500 watts to boil water. I am guessing at least 15 times more gas would be used.
That's a bit disingenuous. Those units were brought online in 1985 and 1986 and are licensed to operate through 2025. That's forty years - which is the life span of a power plant, especially a nuclear power plant. So, they're not being "switched off", they've hit end-of-life. Building a new nuclear power station is logistically impossible. Without getting into it, in essence the U.S. has lost the ability to construct nuclear power stations. People cite the regulatory nightmare, but that's not the real issue - that's an excuse. The real issue is much more complicated.
Note: I work for a U.S. utility that tried to build a nuclear power station due to go online in 2009. We had to abandon the effort and turned the plant into a Integrated Coal Gasification Combined Cycle (IGCC) power plant. It was brought online shortly after President Obama made the statement there will be no more coal plants opened in this country. I still get a chuckle out of that (we've since shuttered several of our coal units and have reduced our CO2 output by 50%). I know of at least two other U.S. utilities that ended up building IGCC plants for the same reasons. All of us already had nuclear generators in our fleet, so we all know how to work with the NRC. Given all the problems we've experienced trying to build new nuclear generation stations I seriously doubt we'll see any new nuclear generation stations built for some time. The last nuclear generation station brought online was in 2016 and took 43 years to build! It also cost billions of dollars. Nobody has the appetite for that kind of endeavor.