Re:The Olkiluoto 3 EPR plant unit started up by thinkingemote on Tuesday December 21, 2021 @03:55AM (#29635419)
Given that it has cost around $11 Billion and has taken 13 years, but has around a 60 year life span (much longer than older ones) and then the costs with decommissioning, how long will it take to be economically worth it? (let alone make an operating profit or be environmentally beneficial)
Re:The Olkiluoto 3 EPR plant unit started up by fuoqi on Tuesday December 21, 2021 @04:16AM (#29635530)
Assuming electricity cost $110 MWh and OPEX of the reactor on the level of $25 MWh with 90% capacity factor without accounting for interest (since it's near zero nowadays), it will take slightly more than 10 years for the reactor to pay for itself. Realistically, with decommissioning I would say it will be 15-20 years. So in addition to positive impact on economy due to lower electricity prices and improved reliability, for at least 40 years it will produce a pure profit. Also in reality it probably will operate for 80-100 years.
Re:The Olkiluoto 3 EPR plant unit started up by Gwypaas on Tuesday December 21, 2021 @04:47AM (#29635721)
That seems like extremely low numbers. From what I've found the range seems to be $123-$204 / MWh, or $0.123 - $0.204 per KWh

https://www.lazard.com/perspective/levelized-cost-of-energy-...

For Hinkley Point C, another EPR we have the following, a guaranteed strike price of $140/MWh.

EDF has negotiated a guaranteed fixed price – a "strike price" – for electricity from Hinkley Point C of £92.50/MWh (in 2012 prices),[25][83] which will be adjusted (linked to inflation – £106/MWh by 2021[77]) during the construction period and over the subsequent 35 years tariff period. The base strike price could fall to £89.50/MWh if a new plant at Sizewell is also approved.[25][83] High consumer prices for energy will hit the poorest consumers hardest according to the Public Accounts Committee.[86]

In July 2016, the National Audit Office estimated that due to falling energy costs, the additional cost to consumers of 'future top-up payments under the proposed HPC CfD had increased from £6.1 billion in October 2013, when the strike price was agreed, to £29.7 billion'.[87][88] In July 2017, this estimate rose to £50 billion, or 'more than eight times the 2013 estimate'.[9]

https://en.wikipedia.org/wiki/Hinkley_Point_C_nuclear_power_...

Re:The Olkiluoto 3 EPR plant unit started up by fuoqi on Tuesday December 21, 2021 @04:50AM (#29635737)
Note that in my comment $25 MWh was only about OPEX (fuel cost, personnel, etc.), while your cost includes CAPEX, interest, and probably payments to a decommission fund. The number is based on 2013 estimate of the US Department of Energy (IIRC at the time it was $23 MWh), so it may be indeed different for ERP. Though if it's sufficiently higher than OPEX of the old US reactors, then I would say there is a problem with the ERP design.
Re:The Olkiluoto 3 EPR plant unit started up by Gwypaas on Tuesday December 21, 2021 @05:08AM (#29635823)
Well, no one is going to make an investment calculation on only OPEX. Lazard puts the average marginal cost for fully depreciated reactors at $29/MWh.

There in lies the issue, the total cost for newly built solar and wind is lower than the OPEX of existing plants.

Re:The Olkiluoto 3 EPR plant unit started up by fuoqi on Tuesday December 21, 2021 @05:26AM (#29635919)
I was answering the GP question with a rough estimate based on simplistic calculations, not building a full blown business model for the reactor in question.
Re:The Olkiluoto 3 EPR plant unit started up by Gwypaas on Tuesday December 21, 2021 @05:40AM (#29636022)
Well, saying it's an easy profit for 40 years seems like a too certain conclusion then?

On a yearly basis these are the average wholesale prices in Finland:

2020 - €28,02 /MWh

2019 - €44,04 /MWh

2018 - €46,80 /MWh

2017 - €33,19 /MWh

2016 - €32,45 /MWh

2015 - €29,66 /MWh

From that we can see is that the average price during the years was about equal to the OPEX we've seen from several sources. Other years you might make some back compared to OPEX.

https://www.nordpoolgroup.com/services/power-market-data-ser...

Re:The Olkiluoto 3 EPR plant unit started up by belorn on Tuesday December 21, 2021 @05:04AM (#29635805)
$0.11 kWh seems pretty conservative given current trend in energy prices. Just looking at the cost here in south of Sweden, it is set today at $0.47 kWh. It won't likely stay there for long (temperature/wind conditions, oil/gas prices, water reserves), but if we use the estimated cost for the next few years it is unlikely (according to prices for long term agreements) that the price will be on average below $0.2.
Re:The Olkiluoto 3 EPR plant unit started up by Gwypaas on Tuesday December 21, 2021 @05:25AM (#29635918)
Always two sides of the coin. These are the average spot prices the last couple of years in SE3.

2020: $0,024 per kWh.

2019: $0,045 per kWh.

2018: $0,050 per kWh.

Nuclear are $0.13 - $0.204 per kWh to build. Therefore, even with these fluctuating prices you would need to make back the average loss of the year during a few short spurts, not looking likely that.

Re:The Olkiluoto 3 EPR plant unit started up by doikor on Tuesday December 21, 2021 @07:26AM (#29636709)
The monthly average spot price in Finland has not been that low during the winter in Finland in any of those years.

Also there is no way OL3 actually costs that much to build. Lets say it runs at 90% of max output on average it gets you ~14 000 000 MWh of electricity per year and with 60 year planned lifetime that comes to 840 000 000MWh of electricity produced.

With your numbers (the low end $0.13 per kWh) it would come to ~100 billion euros building costs which is roughly an order of magnitude more then reality (somewhere between 5.4 to 12 billion to be paid by TVO once all the lawsuits are settled)

At the end of the day with operational and decommissioning costs the overall lifetime costs will go up obviously but I doubt in the tune of over 1 billion per year to reach your estimate costs.

Also getting the profitability number of OL3 is really difficult due to TVO not actually selling any electricity directly to the public/pool but instead at cost to the investors of each reactor. Some of it going directly to Fortum or Helen who just sell it to whoever but some of it goes to the big paper companies who use it to run their factories.

TVO is a "mankala-periaate" company which I can't really find a good english explanation of but basically it is a company that sells all of its product to its owners at cost allowing multiple players in the field to share a single supplier while stills staying in control of the supply chain.

Re:The Olkiluoto 3 EPR plant unit started up by Kliment on Tuesday December 21, 2021 @07:53AM (#29636881)
Here's a good English-language explanation of the Mankala model https://www.lexology.com/commentary/energy-natural-resources...
Re:The Olkiluoto 3 EPR plant unit started up by Gwypaas on Tuesday December 21, 2021 @08:12AM (#29637023)
Hinkley Point C another EPR is right in that range with the fixed strike price being paid by the consumers at £106 per MWh, or $0.140 per kWh. The nice thing about nuclear and average prices is that unless nuclear is ran at about 100% all the time your initial investment takes even longer to pay back, so comparing directly to a yearly average price fits their use case.

EDF has negotiated a guaranteed fixed price – a "strike price" – for electricity from Hinkley Point C of £92.50/MWh (in 2012 prices),[25][83] which will be adjusted (linked to inflation – £106/MWh by 2021[77]) during the construction period and over the subsequent 35 years tariff period. The base strike price could fall to £89.50/MWh if a new plant at Sizewell is also approved.[25][83] High consumer prices for energy will hit the poorest consumers hardest according to the Public Accounts Committee.[86]

In July 2016, the National Audit Office estimated that due to falling energy costs, the additional cost to consumers of 'future top-up payments under the proposed HPC CfD had increased from £6.1 billion in October 2013, when the strike price was agreed, to £29.7 billion'.[87][88] In July 2017, this estimate rose to £50 billion, or 'more than eight times the 2013 estimate'.[9]

https://en.wikipedia.org/wiki/Hinkley_Point_C_nuclear_power_...

Re:The Olkiluoto 3 EPR plant unit started up by doikor on Tuesday December 21, 2021 @08:38AM (#29637223)
Again none of the electricity from OL3 is sold directly to consumers so there is no strike price to think about. Instead the investors pay whatever the "at cost" price happens to be to run the plant. Also TVO does not have that much debt as most of the money for the reactor came from the investors (debt they took not TVO)

Also the current price for the plant is 5.7 billion euros (in the last "official" statement from TVO). It might go up to 7 to 8 billion after the lawsuits etc. Basically the plant was built at fixed cost contract with the builders (Areva and Siemens) taking a huge hit but that is not TVOs problem.

The biggest investors in OL3 are paper companies more interested in some guaranteed max price than paying the least by getting as much of their electricity from their own production (the nuclear plants by TVO, their own hydro, etc). Basically they want to be able to say 1 year in advance that paper/paperboard will cost X without taking a huge hit when fulfilling their contracts due to electricity price jumping up. If they happen to find cheaper electricity from somewhere else then it is just a happy accident and more profit for them.

Basically OL3 got built as the investors were so happy with the previous 2 reactors at the site so I would think they know how to do it in a profitable way.

Re:The Olkiluoto 3 EPR plant unit started up by belorn on Tuesday December 21, 2021 @07:54AM (#29636888)
SE3... Funny choice. The electrical zone in Sweden with the highest amount of nuclear. At this hour about 70% of the power comes from nuclear, 15% from hydro, and about 3% from wind. SE4 in south of Sweden has 0% nuclear, and is the zone with the highest energy cost and with the highest production from wind.

We are however also talking about two very different kind of prices. My numbers are what the customer is paying, which can be seen either on the website by the electric company or sites dedicated to it (https://www.eon.se/el/elpriser/aktuella and https://elen.nu/dagens-spotpris/se4-malmo/#). What you are describing is the price on the energy market Nord Pool, like those that can be read at (https://www.energimarknadsbyran.se/el/dina-avtal-och-kostnad...).

Re:The Olkiluoto 3 EPR plant unit started up by crote on Tuesday December 21, 2021 @04:51AM (#29635740)
That's comparing apples to oranges.

In reality, a significant fraction of the cost comes from interest. Sure, the 1-month LIBOR rates may be 0.1% nowadays, but construction started in 2005. The 10-year treasury rate in 2005 was closer to 5%. Nobody would be willing to lend money for the construction of a plant like this for anything less.

Re:The Olkiluoto 3 EPR plant unit started up by doikor on Tuesday December 21, 2021 @07:58AM (#29636913)
The few numbers for the loans that have been public have been somewhere between 2 and 3%
Re:The Olkiluoto 3 EPR plant unit started up by fuoqi on Tuesday December 21, 2021 @04:55AM (#29635754)
This is why I wrote that realistically it will be closer to 15-20 years. There are other factors which are not considered in my simplistic calculation.
Re:The Olkiluoto 3 EPR plant unit started up by pasiaj on Tuesday December 21, 2021 @04:16AM (#29635528)
At current energy prices in Finland, it would take less than 1/10 of the time expected.

(Of course the current price is a bit of an anomaly.)

Re:The Olkiluoto 3 EPR plant unit started up by eb0la on Tuesday December 21, 2021 @07:35AM (#29636767)
I am not sure if it is just a bit. Gas supply in Europe is having issues: - Gas supply from Algeria via Morocco is closed. - Russia is sending less gas as usual (and profiting from it).

Demand from gas in Europe remains the almost the same, but supply isn't.

Re:The Olkiluoto 3 EPR plant unit started up by fuoqi on Tuesday December 21, 2021 @08:12AM (#29637018)
- Force long-term contracts to be tied to spot prices instead of oil.

- Do not fill storage assuming lower prices in autumn.

- Intentionally delay certification of a pipeline from one of your main suppliers.

- Act very surprised when the aforementioned supplier does nothing to stop spot prices explosion due to the external circumstances and even fans the flames a bit.

- Make questionable remarks which accelerate the rise of gas prices even further.

- Demand (sic!) from the supplier additional gas not covered by existing contracts, even though it's clearly not in his interest.

I wonder why does the EU has gas supply issues?

Re:The Olkiluoto 3 EPR plant unit started up by zajio1am on Tuesday December 21, 2021 @11:10AM (#29638740)
> Intentionally delay certification of a pipeline from one of your main suppliers.

The pipeline is not certified because it breaks existing legislation. It is up to pipeline developers/owners to fix this issue.

Re:The Olkiluoto 3 EPR plant unit started up by fuoqi on Tuesday December 21, 2021 @11:50AM (#29639209)
Do you really think that Nord Stream 2 AG lawyers are that stupid? Note that the application was filled in June 2021, BNetzA begun certification procedures in September 2021, and only almost two months later (suddenly!) they have found that you need a German company. Ok, let's say that BNetzA indeed was simply not familiar enough with the new legislation passed by EP in May 2019 and by Bundestag in November 2019 (sure, you need almost two whole years to read it reaaally carefully). Also let's forget that those changes to the Third Energy Package were effectively aimed only at Nord Stream 2. And while we at it, also let's forget about the really questionable Baerbock's declarations (Minister for Foreign Affairs). But now we have an official statement from BNetzA what in the best case scenario certification will not end until summer of 2022. In other words, it will take the maximum possible time allowed by the procedures, meaning that the properly working pipeline will not be used for almost a whole year.

So if this does not look to like an intentional delay, then I don't know what to say.

Re:The Olkiluoto 3 EPR plant unit started up by zajio1am on Wednesday December 22, 2021 @11:47AM (#29651748)
> Do you really think that Nord Stream 2 AG lawyers are that stupid?

Nord Stream 2 AG is a subsidiary of state-owned Gazprom. They probably think that if they put enough political pressure, they could negotiate an exception.

Re:The Olkiluoto 3 EPR plant unit started up by doikor on Tuesday December 21, 2021 @08:49AM (#29637321)
Finland also has the unique problem of most of the imported electricity having to come through Sweden and the national grid of Sweden is not up to the task (one of the reasons for really high electricity prices in Finland at the moment)
Re:The Olkiluoto 3 EPR plant unit started up by bjourne on Tuesday December 21, 2021 @08:02AM (#29636938)
It depends on future interest rates and electricity prices.

Assuming a fixed interest rate of 5%, construction costs including interest is about $16 billion = €14 billion. Assuming an availability of 95% (maybe unrealistic for a brand new reactor) it will generate 13TWh/year. Assuming an electricity cost of €100/MWh (higher than usual but lower than current extreme prices) and a marginal cost of €26/MWh, the income/year is €0.99 billion. From this you have to deduct the interest of the loan of about €0.70 billion. So for the first year you have €0.29 billion in profit that you can use to amortize the loan.

So when the plant becomes profitable is highly dependent on what future interest rates are and how high future electricity prices will be. While current interest rates have been very low for the past few years, it may be very hard to get an investor to lend you money for a nuclear plant for only 5%. A discount rate of 7% or even 9% is often used for many commercial projects. Using those rates Olkiluoto 3 will never generate any return (barring insane electricity prices).

Re:The Olkiluoto 3 EPR plant unit started up by tov247 on Tuesday December 21, 2021 @09:01AM (#29637430)
My question is how much non-nuclear could have been generated for the same price
Re:The Olkiluoto 3 EPR plant unit started up by ftth_finland on Tuesday December 21, 2021 @04:25PM (#29642293)
Between none and very little, unless you are seriously suggesting building new gas power plants.

Neither solar nor wind works during these cold winter days when power usage is at its highest. There’s nowhere to build new hydro. Coal is being banned.

Re:The Olkiluoto 3 EPR plant unit started up by AnssiH on Tuesday December 21, 2021 @06:40AM (#29636400)
> Given that it has cost around $11 Billion [...]

Note that due to the fixed-price nature of the original supply contract, the total cost of the plant was "only" €5.7B ($6.4B) to the owner/operator (TVO).

The $10B-$11B is the estimated cost to the plant supplier (Areva NP/Framatome), i.e. they made a huge loss.

Finnish source of numbers: https://www.kauppalehti.fi/uutiset/olkiluoto-3-alkaa-tuottaa... (paywall)

Re:The Olkiluoto 3 EPR plant unit started up by chinathrow on Tuesday December 21, 2021 @05:16AM (#29635864)
I am sure that decomissioning costs are not available and if so, not exact - as learned from other plants.