I.e. you would also want to be sure that your wiring was rated for 100% utilization, and that other circuit-breaker-like functions exist.
Fire is an actual thing, and figuring out the best way to recharge a halon system isn't exactly what you want to be doing.
When you hardwire the circuit the electrical code allows you to use a 100% breaker.
This is less common in DCs historically but more and more as folks do 208v 3phase 100A circuits.
For a deployment of this scale it should be metered power (For example 1 (or more) 3phase a+b drops to each cabinet) where you only pay a Non-Recurring setup Charge (NRC) and then the MRC is based on actual power draw.
3phase also means fewer physical PDU's (uses less space), but more physical breakers. Over-building delivery capability will eliminate any over-draw concerns for startup cycles.
Since my cabinet number is usually evenly divisible by N*PDUs, this impacts overall capital.
Having a little headroom on your power circuits is also incredibility important, and not every facility will sell 100% rated breakers. It may make more sense to be in a facility with 80% rated breakers than 100%, even with the added capex of an extra PDU or two.
Goes back to my previous comment. What is important to you, at the pod / multiple pod level, isn't as important to the 1-2 cab deployment.
Similarly, ensure spare room in the cabinet for adjustments, that thing you forgot, and small growth. Much better to have 70% full and not need the space then to have no free RU and need the space.