http://www.energycentral.com/generationstorage/energystorage...
The other factor is that when you're operating at grid scale, it's overall changes to the grid flow that you're concerned with. A large city might have a peak load of 2000 MW, and the plant here could handle a fluctuation of 10% -- given the law of large numbers, that's a lot. Sure, you might be turning on a slew of light banks in any given period, but someone somewhere else could be cycling down a cooling plant, or resistance heater, or the like.
I suspect large rapidly cycling loads might also be at issue -- with electrified transit, light rail and trolley buses make high instant demands on the grid, and then return energy through regenerative braking. I don't know how such loads are managed, but they're substantial and I do know that utilities tend to segregate these from other residential and commercial circuits.
Your average, underfunded community or educational theater has 150-200 lighting dimmers, each at 2.4 kW. I can consume half a megawatt (200 circuits x 20A x 120V = 480kW) in 6 keystrokes.