Re:Troubled welds on the Bay Bridge by jacques_chester on Sunday June 08, 2014 @11:57PM (#7866943)
I feel that the title is misleading.

Caltrans faulted by practicing terrible project management.

If someone underbids the next contractor by $250 million on a job they've never done before, you're supposed to politely laugh them out of the room.

Edit: for the benefit of those now arriving, the title and link have been changed.

Re:Troubled welds on the Bay Bridge by techsupporter on Monday June 09, 2014 @02:24AM (#7867287)
> If someone underbids the next contractor by $250 million on a job they've never done before, you're supposed to politely laugh them out of the room.

Most of the time, you can't, at least not for government projects. Because of procurement laws and rules (designed, among other things, to allegedly be transparent and to provide accountability), a government body is required to accept the lowest bid from the contractor that met all of the requirements. Seeking an "experienced contractor" is usually seen as code for "we want to use our friends" by a skeptical legislative body, so things like tenure and past projects can't be considered.

Re:Troubled welds on the Bay Bridge by div on Monday June 09, 2014 @03:37AM (#7867392)
Odd. I've been involved in a few government bidding processes in Europe, and detailing past projects was always a major part of what we'd get graded on.
Re:Troubled welds on the Bay Bridge by Someone on Monday June 09, 2014 @04:31AM (#7867483)
Indeed. Typically, being able to build the thing is a requirement, and that is typically made objectively measurable by stating that you must have successfully built similar projects.

That has its downsides, too. A common complaint in the EU is that there is no way for small building companies to become large companies. Reason is that, to become a large company, you have to do large projects, and to get large projects, you have to have done large projects.

In the EU, when comparing offers, one doesn't have to pick the absolutely cheapest that meets the requirements, either. A slightly more expensive offer that more than meets the requirements (for example by having much less environmental impact, by requiring less closure time of a road, or by producing something that has lower maintenance costs) can windhover one that just meets the requirements.

Re:Troubled welds on the Bay Bridge by dagw on Monday June 09, 2014 @07:19AM (#7867862)
It's part of your grade, but it is rarely an overriding factor in my experience. Lots of experience plus slightly higher price will beat little experience and slightly lower price, but it won't beat little experience and very low price.

I was recently involved in a bid for a government contract where we got perfect scores on all factors, but still lost the bid to a small company with little to no relevant experience, but who claimed they could to the job for a third of the price.

Re:Troubled welds on the Bay Bridge by bane on Monday June 09, 2014 @07:53AM (#7867968)
To alleviate this somewhat, at least in Federal contracting, "best performer" can be chosen over "lowest bid" and often is if the project will be put at risk by an inexperienced contractor, or somebody trying to slip in on the cheap and provide substandard contract completion and/or try to squeeze the money out of the government later.
Re:Troubled welds on the Bay Bridge by bmelton on Monday June 09, 2014 @10:37AM (#7868653)
The obvious counter to this, and it's built-in to the process, is the "past qualifications" requirement. If your company has never built a bridge, they should have been disqualified from the bidding process via F.A.R.

The usual workaround for this is in IT is to sub-contract the necessary portions to those with said experience, so that the packaged team has the experience as a whole, but while that might seem like a loophole, it generally isn't bad because it means that the ones with the experience are the ones doing the work that requires the experience.

Admittedly, this isn't federal, and I don't know how what the bidding requirements are for state work, but if there's no disqualifier for "never done this before", heaven help the state of California.

Re:Troubled welds on the Bay Bridge by elnate on Monday June 09, 2014 @12:14AM (#7866989)
I've worked for a company (electronics design/installation) that desperately underbid competitors to get as many jobs as possible, then the boss piles pressure on the workers to get the job done at an inhuman speed. Inevitably, up fucks occur and the boss has a shit fit, you get in trouble and have a black mark against your name. Not fun all around.

The lessons, not every job is worth doing and always allow margins for mistakes.

Re:Troubled welds on the Bay Bridge by opendais on Monday June 09, 2014 @12:03AM (#7866954)
Not just the next contractor but the lowest bid by a contractor who has ever built a bridge before.

Just in case someone doesn't read the article. ;)

Re:Troubled welds on the Bay Bridge by carlisle_ on Monday June 09, 2014 @02:27AM (#7867296)
And the real kick in the balls:

>As the project wound down, ZPMC reaped tangible rewards, sharing with ABF more than $250 million in cost overruns and incentive payments.

Re:Troubled welds on the Bay Bridge by pijsong on Monday June 09, 2014 @01:11AM (#7867145)
caltrans and california gov ... just way too corrupted
Re:Troubled welds on the Bay Bridge by cmelbye on Monday June 09, 2014 @01:38AM (#7867208)
Never attribute to malice that which is adequately explained by stupidity.
Re:Troubled welds on the Bay Bridge by dnautics on Monday June 09, 2014 @03:46AM (#7867401)
in this case the administrators are probably not malicious, they are thinking, "I'm doing society a solid... I should be entitled to a due". It's only malicious if they actually have a modicum of introspection.
Re:Troubled welds on the Bay Bridge by saraid216 on Monday June 09, 2014 @03:07AM (#7867350)
Accepting a lower bid isn't an example of corruption.

This is the equivalent of buying a startup's product on the chance they figured out how to provide value more cheaply. That's not corruption; that's basic market forces.

Re:Troubled welds on the Bay Bridge by rwallace on Monday June 09, 2014 @03:39AM (#7867393)
If you look carefully at the full text, it's clear the fiasco made no economic sense, and there was bribery and corruption involved.
Re:Troubled welds on the Bay Bridge by acomjean on Monday June 09, 2014 @01:39PM (#7869454)
usually the wording is "lowest bid from a qualified contractor"

If the the contractor is not qualified they should be removed from the bid. In NY there was a list of contractors no longer able to bid state jobs that had to be checked as well.