Re:Huawei Patents 3,000km Solid-State Battery with 5-Minute ...
by 7e on Monday June 30, 2025 @06:25PM
(#44428582)
Superchargers with 98 stalls, today, absolutely cannot handle peak charging of all those stalls at the same time. That’s the equivalent of 34,000 homes turning on at the same time, which is basically a medium size city.
Re:Huawei Patents 3,000km Solid-State Battery with 5-Minute ...
by bryanlarsen on Monday June 30, 2025 @08:18PM
(#44429325)
Cannot handle it, and doesn't have to handle it. A Tesla will only pull the full 350kW for 2 minutes in a charging session, and sessions average ~20 minutes. And even when the station is full, there are always stations pulling 0W because they're switching between vehicles et cetera.
But if it did need to handle that level of instantaneous load, it would be straight forward to supply. 98 Tesla's worth of batteries on site could do it. The grid tie is substantially smaller, because the grid tie only has to handle average load, not instantaneous load.
There are two main ways of handling that randomness.
1. Spread it over a large number of vehicles, and let statistics average out the demand spikes. We're doing this at a significant rate, adding > 1 million EV's to American roads every year. Also, we already have superchargers with 98 stalls. There's going to be little demand difference between 98 350kW chargers vs 32 1MW chargers. 9 350kW vs 3 1MW chargers loads a grid harder, but 98 vs 32 not so much.
2. Batteries. Charging stations are already large enough that many are utilizing batteries to smooth electricity demands.