Re:Going Colo
by mindslight on Tuesday June 26, 2012 @11:05PM
(#4165306)
Yes, this is a requirement of the NEC. Branch circuits need to be rated at 125% of the continuous load. In general, wires are sized not only on their overcurrent protection, but also (overbuilt) for the planned load. Unplanned "noncontinuous" loads get a free pass as the only thing that really keeps them in check is the overcurrent protection.
But kika's downthread comment is most on the mark - of course data centers would rather advertise the less relevant "circuit rating" as the number is higher. The load calculations are the same either way.
(btw speaking of the NEC, http://bulk.resource.org/codes.gov/ is a fantastic resource)
I think this is an NFPA/NEC[1] standard.
You could look at it another way: circuits are breakered such that you can temporarily peak 25% above their normal capacity without tripping the breaker. I don't know why the standard isn't more conservative, except to guess that it's because typical household/office uses are likely to have low continuous and high intermittent loads (e.g. vacuum cleaner), making it a good trade-off.
[1] USA (and Canada?) only. Anyone know how it is in other countries?