Re:Going Colo by mindslight on Tuesday June 26, 2012 @11:05PM (#4165306)
Yes, this is a requirement of the NEC. Branch circuits need to be rated at 125% of the continuous load. In general, wires are sized not only on their overcurrent protection, but also (overbuilt) for the planned load. Unplanned "noncontinuous" loads get a free pass as the only thing that really keeps them in check is the overcurrent protection.

But kika's downthread comment is most on the mark - of course data centers would rather advertise the less relevant "circuit rating" as the number is higher. The load calculations are the same either way.

(btw speaking of the NEC, http://bulk.resource.org/codes.gov/ is a fantastic resource)