Note that the point of the article was that the design is being proven, lessons are being learnt, and the skills of individuals and organisations developed, which reduces the risk of overruns etc.
The most recent estimates put costs as high as £34bn at 2015 prices, £46bn in today’s money.
I believe the range is £31–35 billion in 2015 prices, so between 75% and 100% overrun.> that's the whole reason France is crying for relief here from the UK.
The overrun combined with COVID combined with the spike in inflation and also CNG being frozen out of the UK nuclear market/cooling of relationship with China.
> claims that nuclear will show good experience effects this time, for sure, are to be treated with skepticism.
Agreed, which is why the second unit at HPC will be interesting.
Interestingly the nuclear data implies that those (45% of) projects not in the tail (defined as >= 50% cost overrun) have a mean overrun of 17.33%.
120% = 0.45 * X% + 0.55 * 204% therefore X% = (120% - 0.55 * 204%)/0.45 = 17.33%
Fixed price contracts in the nuclear industry have rarely if ever worked out well for the suppliers. Contrast this with renewables which typically come in within 10% of the contracted price.