Re:Hinkley Point C: Building Britain's first nuclear reactor... by davedx on Monday September 23, 2024 @07:05AM (#41624722)
Weren’t those agreements made way back before the giant cost overuns?
Re:Hinkley Point C: Building Britain's first nuclear reactor... by pfdietz on Monday September 23, 2024 @07:17AM (#41624815)
Yes. Huge mistake for France, that.

Fixed price contracts in the nuclear industry have rarely if ever worked out well for the suppliers. Contrast this with renewables which typically come in within 10% of the contracted price.

Re:Hinkley Point C: Building Britain's first nuclear reactor... by tonyedgecombe on Monday September 23, 2024 @08:42AM (#41625440)
Yes, it seems the only projects that have larger cost overruns than nuclear power stations is dealing with nuclear waste.
Re:Hinkley Point C: Building Britain's first nuclear reactor... by chickenbig on Monday September 23, 2024 @09:07AM (#41625651)
Don't forget the Olympics, with a format designed to minimise the learnings.

Note that the point of the article was that the design is being proven, lessons are being learnt, and the skills of individuals and organisations developed, which reduces the risk of overruns etc.

Re:Hinkley Point C: Building Britain's first nuclear reactor... by pfdietz on Monday September 23, 2024 @09:09AM (#41625665)
Hasn't it already greatly overrun the initial promises? I mean, that's the whole reason France is crying for relief here from the UK. Anyway, claims that nuclear will show good experience effects this time, for sure, are to be treated with skepticism.
Re:Hinkley Point C: Building Britain's first nuclear reactor... by chickenbig on Monday September 23, 2024 @12:00PM (#41627499)
> Hasn't it already greatly overrun the initial promises? Hinkley Point C got the green light in 2016 with an estimated £18bn build cost

  The most recent estimates put costs as high as £34bn at 2015 prices, £46bn in today’s money.
I believe the range is £31–35 billion in 2015 prices, so between 75% and 100% overrun.

> that's the whole reason France is crying for relief here from the UK.

The overrun combined with COVID combined with the spike in inflation and also CNG being frozen out of the UK nuclear market/cooling of relationship with China.

> claims that nuclear will show good experience effects this time, for sure, are to be treated with skepticism.

Agreed, which is why the second unit at HPC will be interesting.

Re:Hinkley Point C: Building Britain's first nuclear reactor... by chickenbig on Wednesday September 25, 2024 @01:29AM (#41643967)
I take it you are referring to https://x.com/BentFlyvbjerg/status/1662016016493191169

Interestingly the nuclear data implies that those (45% of) projects not in the tail (defined as >= 50% cost overrun) have a mean overrun of 17.33%.

120% = 0.45 * X% + 0.55 * 204% therefore X% = (120% - 0.55 * 204%)/0.45 = 17.33%