My disappointment comes from the fact that there are stations where the Piccadilly just blazes through and doesn't stop. The platforms are there, maintained and in use, but the train just goes past. Those areas have been repeatedly told for the past decade "no new stops until signalling upgrades which you'll get when the new trains come – otherwise it would make the journeys longer and we can't have that on a line that services Heathrow!".
Now the time has come and the signalling upgrades were axed, meaning according to the original logic, no chance of getting the trains to stop at your station. Of course new stations could be serviced, at a cost of making the journeys slower – surely the argument of "if the train stops at your station, it'll slow down the journey for everyone" applies to all stations, not just a select few? But even if we go with the nonsensical "we can't slow down the average journey time", other options could be taken, such as making the trains stop at the least used stations alternately – you don't even need to go full "Express Train" route NYC does if your issue is just a couple of stations.
Still, TfL hasn't really shown any interest in touching any that and always said "you'll get your stop with the new trains". Well, the new trains are almost here and it doesn't look like it'll come with a solution, just more of the status quo.
Air conditioning is of course great and I'm not advocating for maintaining old stock forever. But a shiny new train does nothing if the train won't stop at your station. And you're not going to get much gains if your shiny new trains are effectively throttled to last century speeds with last century reliability.
I think you are really overegging the impact of the skipped station (turnham green?) You can just get a district line train and change. Ok, it's not ideal but it's probably only adding 5-10mins to journey times. It's one station on a network of hundreds and does not justify billion+ spent for it.
And I don't think there is a business case for further capacity, as not only would it require resignalling it requires another batch of trains to be built to get it up to 36tph. There isn't the demand for that post covid. This may change but there are much more pressing captial projects for tfl (bakerloo line extension for example) imo.
The problem with relying on post COVID passenger reductions is that whilst tube numbers are down 20% since COVID that just means they're at the level they were in 2009/10. Even if they don't bounce back fully this year, post COVID working hasn't cut out the peaky nature of tube travel. Even if people work from home Monday and Friday, they'll often all come into the office on Tues-Thurs making peaks on those days.
I agree the demand for capacity on other lines that is even more pressing. Last time I rode the tube regularly was 10 years ago and even then I recall the Victoria line during rush hour was literally cattle class, your face in someone else's armpit. The 2019 numbers put the Northern Central, Jubilee and Victoria lines are well over the 100% mark at peak time. Despite having the highest comparative fares compared to other cities the Tube is still woefully underfunded. There is so much technical debt because much of the system was built in the 1800's and early 20th century. First mover disadvantage, because we got to make all the mistakes.
No it doesn’t. Some stations serve more passengers and transfers than others. And even if stations were identical, the opportunity cost of stopping goes up as the train gets more full.
> such as making the trains stop at the least used stations alternately
Yes, this can make sense. But it doesn’t necessarily have to. You have to actually check the numbers.
Similar to how the last westbound central line train to Ealing Broadway holds at White City to allow the final westbound train of the night (towards West Ruislip) to transfer the last stragglers from the city
Having the Piccadilly stopping here during the day would allow for better passenger distribution -- I've often found that one or the other line is brimming with passengers even when the other is half-empty.
So basically any given train was only stopping at maybe 60% of the stations.
Pardon my ignorance, but how can a signaling system cost that much money? Is it made out of gold and platinum or what?
1) very complicated and drawn out design/approval processes with many expensive consultants involved. on network rail you would not believe the amount of studies they have to do, including testing the light levels everywhere in a carpark to make sure there are no dark spots, amongst a billion other small things. there has been endless regulation forced on the railways/tfl, which on one hand is good for safety but on the other has meant even a tiny project needs a trillion risk assessments done, which typically get outsourced to specialist consultants, who have a massive incentive to find problems so they can retest.
2) lack of competition at the top level contractor layer. the procurement rules require really only huge companies can bid, which means they can act in a semi-cartel way. this is probably difficult to solve given signalling stuff but in more basic construction projects it feels like not much competition is going on (not suggesting there is a cartel here, fwiw, just feels a bit like it!)
3) on the tube the access is extremely restrictive. you tend not to close the line for extended periods of time (though this is changing recently as i think people are realising the cost of keeping the line isn't worth it vs doing a week closure), which means that you have to get all your equipment down to the tunnel (which might taken an hour), do 2-3 hours of work, then remove all the equipment, in 4-5 hour blocks each night between midnight and 5amish, which means you are paying people often "night working" wages for working really 2 hour shifts, instead of paying them normal wages for working through the day for 8 hour shifts. This probably increases the cost of labour by 5-10x.
Proving that it fails safely requires a mountain of effort and documentation, but it's required because failure doesn't just lead to some speculative CPU bugs leaking a password or to a browser crash, it leads to many people dying.
Aren't we talking about physical signalling kit - no copying and pasting? 272 stations and ~400km of track - a lot of which is pretty difficult to access?
Having a common design does help but it doesn't help that much as most of the problems are with the physical realities of each location - and what I did was much simpler and less critical than signalling.
It is not ever 'just'. This isn't copying code. This isn't building identical silicon for multiple end users. This is more like trying to add additional threads to something that is not embarrassingly parallel. What you're saying is like saying 'why can't you just make all of my computer programs run on all 32 of my CPU cores?'.
And even if you minimise the increasing complexity added by expanding the system, waterfall-style design (which is absolutely the most appropriate approach when dealing with these sorts of projects) front-end loads a frankly Herculean amount of risk management into the process because you want to make sure that's all absolutely square and true before you progress to implementation.
Lastly, it's worth noting that with systems this complex, a lot of the detail is bespoke because the number of complicating input variables the system is exposed to necessarily requires a relatively bespoke solution. Yes, the idea of e.g. ETCS being ETCS is going to hold, but how that works in reality, how it ties in to all of the other legacy systems, etc. will mean that you can't for example just take ETCS-equipped train A and and drop it into ETCS-equipped network B.
This is a line that has 53 stations. For comparison that’s 20 more stations than the longest and highest volume L line in Chicago.
I wonder how this cost benefit compares to the $9 billion project to widen Houston highways?
I used to commute 5 times a week (often more) on Piccadilly. So that’s £5,200 for my ridership for the year? From that perspective seems rather expensive…
It’s disappointing they ditched the signal upgrades. It will bite everyone soon enough. Some of these systems date back over a hundred years, and are all incredibly bespoke.
Re the missed stations, I feel like they missed an opportunity with the Elizabeth Line line to shift more Heathrow traffic that way, giving some breather to Piccadilly during signal upgrades.
£5200 for your annual ridership but then divide that by the lifespan of the signaling. Let’s say it lasts 30 years, so that’s €173, (but of course, at the end of the 30 years £173 is worth a lot less).
The only reason I compare it to America is because I don't actually know the figures for the UK, but I expect that car owners would spend more there due to higher cost of petrol, higher vehicle taxes, etc.
That's why I don't think they compare well: many people who use public transport, even the Tube or similar, still need a car, at least sometimes. So it's not an alternative, and it's not equivalent value.
I think the answer is that solving this problem takes a teak of some size and skill, and paying them while making a hefty profit is expensive.
(You can read the article to see the reason for the windows.)
https://en.wikipedia.org/wiki/MVG_Class_C
https://commons.wikimedia.org/wiki/Category:M7_(Metro_Amster...
A better comparison is with the Circle/District/etc lines. Those trains are of similar size to the Dutch and German ones, although I think they are designed to carry a lot more people so there are fewer seats:
https://en.wikipedia.org/wiki/London_Underground_S7_and_S8_S...
Moreover, there's something to be said about consistency of design when it comes to maintenance familiarity and parts interoperability. Consistent design language also tends to happen when you are catering to disability accessibility requirements and providing clear user interfaces for passengers (including those with disabilities, or those who do not speak English).
Lastly, expecting a complete redesign is committing to an astronomical amount of expense relative to even using just some of the old design DNA. However, I'm not even convinced they've just reused an old design. For starters, a different company did these (Siemens vs Bombardier) and secondly I'd bet that there's a whole lot of difference under the skin that is masked by the natural convergence of design appearance driven by the multitude of requirements set forth by TfL - everything from the design language mentioned above, to their access/egress requirements, fire safety, lighting, etc. etc. There's only so much money governments are willing to throw at figuring out how to skin that cat before it's just not worth it.
Is accelerating faster a practical solution though, considering how many people are standing?
SSL = sub-surface line
I also believe the new trains can accelerate faster so new stops are potentially possible. And in theory at least they should be a lot more reliable, even if the signals aren't.
FWIW there was a signals redesign contract for the pic singed in 2022 so I don't think it's never going to happen. Also even before covid it was phased that the new trains and signalling where fairly independent projects.