The matter of fact is that only very few countries in Europe can "afford" to get by without Russian gas or other resources. After all it is the home to the continents largest concentration of natural resources.
There is only so much global production capacity, so much bandwith in terms of logistics, that can compensate for that. It's not like we can suddenly tap a new continent full of resources to replace Russia, reality ain't working like that.
https://www.statista.com/statistics/1201743/russian-gas-depe...
FSRU Independence has sufficient capacity to deliver enough gas to serve 70~100% of the yearly needs of the three Baltic countries, depending on how you count. Of course it remains a question of who supplies the LNG, but it gives the countries a backup, an ability to pick the suppliers and an ability to make politically important decisions, even if it means paying a little more.
They are connected to German pipelines.
This map is excellent: https://www.gie.eu/publications/maps/gie-lng-map/
Spain is also a wind power giant.
As comparison, Germany is not a great location for either wind or solar power.
It isn't that spanish companies can get much help from the government's diplomacy (long topic), so someone else interested in that connection would have to partner with such companies, or a foreign diplomatic body go and do the legwork for the spanish companies, which wouldn't be the first time.
Thus Germany could be like we have it back home in the Iberian Penisula, but no, many people are keeping the courts busy instead.
It's a straightforward piece of technology that can be built quickly by any country, unlike, say, a liquefaction plant or a LNG tanker.
But building any kind of infrastructure takes time. There are some factors which make it more complicated engineering wise: cryogenic fluids, handling large quantities of flamable and explosive liquids and gasses, being built on the waterfront etc etc. None of these are insurmountable mind you! They just complicate it a bit.
One way we can look at is by comparing how long such plants took to get constructed elsewhere. I looked up a few European examples. From the first announcement to the first ship docking:
UK/South Hook ~6 years
UK/Dragon ~4 years
UK/Grain ~6.2 years
Belgium/Zeebrugge ~10 years
Netherlands/Gate ~4 years
Poland/Świnoujście ~9 years
(I have collected my sources on a spreadsheet here: https://docs.google.com/spreadsheets/d/1md_XfmrpIYhWj72Mu3BJ... )Probably I made some mistakes in the above, and there are some inconsistencies (do we count until the first commercial ship, or the first ship trialing the facilities?) Also I assume that all of these things can be done a bit faster in case of a dire emergency. But it seems even in that best case it might take multiple winters until a regassification plant is up and running. Which is a bit cold and scary.
I’m not putting Poland as some kind of benchmark for speedy construction, but I think 1-2 years is a minimum even in a hurry.
> there is not nearly enough of that in Germany right now
To elaborate on that: Germany has no LNG terminals. Zero. They signed the first contracts to build one this year March [1]. If I were a German citizen I would feel very cross with my own government. It's a good idea to have such an infra just in case. Just to hedge the bets.
There is a very real reason why the Floating Storage Regasification Unit serving as the LNG import terminal for Latvia is called "FSRU Independence". [2] These facilities literally provide independence.
1: https://www.maritime-executive.com/article/germany-speeds-pl... 2: https://en.wikipedia.org/wiki/FSRU_Independence