Fabs do not work on jit/lean order principle - if you up your order volume, you can't simply scale it up on demand the next month - even if your design is done and taped out. Fabs aren't sitting around idly waiting for orders nor are they overprovisioned "just in case".
An example of this would be AMD and TSMC. AMD books capacity 3 years in advance for which TSMC designs the entire fabrication facility around, orders the lithography machines (which have a 12 month lead time and can't scale up on a dime) and assembles and staffs those same facilities to produce the wafers. It's not a general-purpose fab as most think. There are rumors that Apple booked m1 fab capacity (on TSMC 5nm) in 2018. For the chip inside a car for example, it is built on much older process, and when 5 of your biggest customers "JIT" reduce their order volume for the next 3 months you simply put those staff elsewhere (probably on the 6x higher margin cutting edge fab you just got booked and prepaid for) since anyone else who might want that process and capacity has already has their orders being produced.
Due to the sheer capital requirements (and consequent commitments required) and multi-year forecasting involved in simply getting what you think you'll need, let alone having extra, it's not hard to see why a small increase in global demand would cause a dramatic shortage. JIT works in Automotive supply chain where you can request that your bearings get made 10 days before they're delivered to the factory, but not when there is an 18 month latency on "scale up" request/response.
It's applying JIT principles to inherently non-JIT supply chains.
Now, the whole world is trying to get TSMC to invest in other locales in advance of Chinese invasion of Taiwan at the same time that NATO is funneling arms and personnel to Ukraine ahead of Russian invasion. Work isn't getting done on expected timelines because of unprecedented disruption caused by responses to covid.
Meanwhile, down at the bottom of the pile, when airlines cancel my flights for unprecedented problems, I wait 3 hours on hold because they don't have enough people working support.
All this to say that, yes, the bullwhip is going to be horrible, but so is not being able to perform your function in the economy because your required inputs are unobtainable. There's no graceful path for a system with so much volatility. Hopefully we can all stomach the creative destruction.
If that were true, they would have ensured the chip manufacturers had constant demand, rather than a famine period followed by a huge feast.
The truth is that just in time is being used as a cost minimization procedure, by offloading the demand risks into the suppliers and increasing any feast or famine event. That maximizes profits as long as there isn't an emergency, what seems to be the favorite administration goal of the current age.
These chips are not fungible commodities. In the automotive space chips are selected based on a number of things including feature set - how many CAN interfaces does it have, how many GPIO, how many PWM, what kind of brown-out handling, what voltage range, thermal rating, etc... Software is then written where a portion of the code is specific to that chip. There are cases where an OEM get really good pricing on a bigger (overkill) chip and helps a supplier get those at good prices too, but usually they just beat you over the head for the lowest cost. Even if everyone adopted a few larger parts and used just those, they're still usually made by a single chip company.
This doesn't exist now for the same reasons it probably wouldn't work in the future: You can save significant amounts of money if you cut the pieces out of the "standard" that you don't actually need. Chips are cheap to make, in bulk. It's almost entirely a fixed cost/area. That's the magic. So, it's almost always cheaper to make a custom chip than to pay for some bloated standard containing large sections that will never see power, especially when chips are something like 40% of the BOM, for modern cars.
No knowledge of the automotive industry, but that sounds impossibly high.
I think there isn't a bullwhip effect on batteries, which is the main cost associated with TVs.
The 72 month loan for a $50,000, 2019 F-250 will be completely underwater, and the car owners may decide to literally send the cars “underwater” to get out of the loans.
Based on what happened in places like California with mortgages, they will default one way or another.
Used EVs used to be pretty dang affordable already (I got a Leaf and a Volt for under $10k each) before all used cars became more expensive and the price of gasoline increased, increasing the demand for EVs.
It’s just about scaling up production.
Another thing I see China doing, is pegging their currency to the dollar, now when the UK did this to the stronger German Deutsche Mark, the UK under Lord Norman Lamont crashed out of the Exchange Rate Mechanism and the UK saw interest rates hit 12/13% so I wonder if this chip shortage has more to it other than investment reasons only?
The lockdowns happened and some lever got pulled. They dusted off the “We love you America, come back and buy a car someday” commercial’s, cancelled everything, and opened the bottle of Scotch.
https://searcherp.techtarget.com/definition/bullwhip-effect
While a lot of people are saying the main issue is the "lean manufacturing" or "just-in-time manufacturing" supply chains, they do not understand manufacturing supply chains. These types of solutions (JIT or Lean) are designed to prevent the bullwhip effect and ensure that suppliers have predictable and constant demand, rather than feast or famine.
Without just-in-time manufacturing, there is significant waste and it is even harder for suppliers to predict what they should be making.
This current bullwhip is going to be horrible on suppliers after the supply catches up with demand and then the demand collapses as so many have bought years in advance.