Re:CERN approves plans for a $23B, 62-mile long super-collider
by simonh on Tuesday June 23, 2020 @04:16PM
(#23619651)
What a strange comparison. Why would you compare it to a space telescope when you could compare it to another supercollider, operated by the same organisation?
The Large Hadron Collider went over budget by about double, which is bad but frankly for these sorts of cutting edge systems hardly unprecedented. Some of that was ironically due to budget cuts causing delays which in the long term increased costs.
Re:CERN approves plans for a $23B, 62-mile long super-collider
by Gibbon1 on Tuesday June 23, 2020 @04:27PM
(#23619779)
> Some of that was ironically due to budget cuts causing delays which in the long term increased costs.
If you want a prime reason things go over budget this is the prime one, not fully funding a project in order to save money. If you look at well executed projects they spend years setting up and then execute as fast as possible.
The JWST is also hugely behind schedule, to the point that XKCD mocks it [2]. Originally scheduled for 2007, the launch date repeatedly slipped. The latest date, 2021, is now in doubt.
I think there's a big risk that this CERN supercollider would have the same cost and schedule risks.
[1] https://www.nature.com/news/2010/101027/full/4671028a.html [2] https://xkcd.com/2014/