Re:‘This Did Not Go Well’: Inside PG&E’s Blackout Control Room by dredmorbius on Saturday October 12, 2019 @07:32PM (#21237096)
Thanks, that was a really quick check. And yeah, that would increase the costs markedly.

(My initial thought on posting was that $30 billion would not be enough, though the first read of actual per-mile costs, neglecting per MW-mile, seemed to suggest otherwise.)

Re:‘This Did Not Go Well’: Inside PG&E’s Blackout Control Room by Pinckney on Sunday October 13, 2019 @01:14AM (#21238509)
This PDF from Wisconsin puts the cost at $280k-390k/mi depending on the voltage of the line. They put the cost of underground transmission lines at $1.5M-2M/mi for the same voltages.

https://psc.wi.gov/Documents/Brochures/Under%20Ground%20Tran...