This was discussed a couple days ago in a different thread [1], when 4TB was the EC2 limit.
$400k for the current-gen (224 cores) or, as a sibling comment [2] notes, $250k for the previous CPU generation (which can use twice as many DIMMs of half the density and only 192 cores of that).
> obviously, there's operational costs to consider as well
We can estimate an upper bound on this, given that the current-gen system has N+2 5x1600W 96% efficient PSUs, so 5kW max. If you're paying a colo $.50/kWh, that's another $66k over 3 years worst case.
Realistically, though, CPUs with a max TDP of 1640W, DIMMs (generously) 700W, leaves plenty of room for fans, SSDs and other overhead before getting to 3kW or $40k, and that's still assuming running full-bore the whole time.
There are obviously also ancillary costs to AWS, such as data transfer and EBS.
If you're already running your own hardware, it sure does look more attractive to pay $400k now and $40k over 3 years than to pay AWS $800k All Up Front (now). If not, perhaps it's more attractive to hand-wave away that $360k as saving the "hassle" of hiring someone who knows how to run equipment in a datacenter.
That's a pretty non-trivial amount of expense to setup a network with enough capacity to support a machine like this fi you want to do it yourself.
It may imply that but only outright requires 40Gb/s total, which is provided by the "4-port 10GBase-T Ethernet SIOM (Intel® X550 controller)" of a SuperServer 7089P-TR4T.
The EBS bandwidth can be elided entirely by using local storage instead. Local storage bandwidth can be much cheaper than ethernet, especially considering how many NVMe ports are already included.
As 10GE is maybe $200/port (including SFPs), at scale, network cost doesn't "move the needle" on a $400k server.
[1] https://www.thinkmate.com/system/superserver-7088b-tr4ft
the first time.. 12TB can cache a lot of logs.
>> SAP HANA in Minutes
> The EC2 High Memory instances are certified by SAP for ⟨…⟩
[SAP HANA keeps everything in RAM.]
Requires a 3-year reservation, and "the effective hourly rate for the All Upfront 3-Year Reservation for a u-12tb1.metal Dedicated Host in the US East (N. Virginia) Region is $30.539 per hour."
Works out to $267,512.88 per year, or $802,538.64 for the 3-year term. I wonder how that compares to building your own on-premise host with that much RAM (obviously, there's operational costs to consider as well).
Also, don't miss the last line: "We’re not stopping at 12 TiB, and are planning to launch instances with 18 TiB and 24 TiB of memory in 2019."