Re:How not to build a ship: the USS Ford by gozur88 on Wednesday June 07, 2017 @06:36PM (#14510391)
The military is always in a bind with contractor selection. If the don't choose the lowest bidder they get hauled up in front of a Senate committee full of people grandstanding for the next election accusing them of taking care of cronies.

Particularly at the rate we build ships these days, if you only chose companies that have done it before you're not going to have many bids to choose from.

Re:How not to build a ship: the USS Ford by scottLobster on Wednesday June 07, 2017 @06:54PM (#14510499)
No relation to the Ford, but speaking as someone who works for one of the big defense contractors the underbidding thing is a real issue. One of our competitors (also not related to the Ford) that stole some business from us a while back is currently eating some serious crow on some promises they couldn't fulfill... but they did get the contract. That's serious money in their pocket.

Likewise I'm pretty sure the average Dog Dating App startup has better equipment than we're given, although to be fair what we have does the job, just not nearly as well as it could. Not to mention the mountain of legacy equipment and code that no one ever wants to spend money to replace or upgrade properly (once again, underbidding). For every F-35 or USS Ford there are hundreds of smaller programs wither much tighter (also underbid) budgets that you never hear about (either because they're classified or just too boring for media coverage). But it has to be that way, otherwise we don't get the business at all.

Don't get me wrong I like my work and my coworkers, I'd certainly rather be where I am than Silicon Valley, but the red tape and budgetary constraints are a repeating source of frustration at all levels, and it sucks that there's not really all that much we (at least anyone remotely close to my pay grade) can do about it. At the end of the day it's up to our customers to set the bidding process and pick the winners. A realistic bid is likely a lost contract.

Re:How not to build a ship: the USS Ford by gozur88 on Wednesday June 07, 2017 @07:08PM (#14510586)
I've been there. This is not an easy problem to solve - they do have vetting procedures and sometimes reject bids because they think the contractor can't do the job. But companies are pretty good at making sure the boxes are all checked during the bidding process.

I had a relative in the Air Force, and his group was in charge of salvaging programs that failed because the contractor couldn't deliver. They would get half-finished satellites and boxes of parts arriving at the loading dock and then try to figure out what to do. Is someone criminally culpable? Can we do a contract to finish this, or do we need to start over?

According to him you could just never tell - sometimes the contractors you were sure would fail actually delivered, and sometimes the old reliables went belly up or just kept asking for more money.

Re:How not to build a ship: the USS Ford by scottLobster on Friday June 09, 2017 @04:26PM (#14524248)
Yeah I'd say the issue there is that traditional defense contractors are highly silo-ed, quality can vary drastically from program to program. I've worked on programs that I'd pit against Google and programs where the culture was a bunch of math majors who learned to code in the 70s and haven't updated since the 90s. Just last year I had to review a 500 line FUNCTION in NEW CODE.

Thankfully I'm no longer attached to that program, had to continuously bite my tongue and pick my battles in code reviews to avoid getting a reputation. Even nicely telling people 15-20 years my senior "go spend two days refactoring this crap" was a non-starter. To be fair the code did work, I doubt a user would ever notice. But I felt bad signing off on the review all the same.

I sdhould point out that not all the old-timers are a problem. I'm currently working with some 20-year guys who are VERY up to date and open to new ideas; and the company is trying to modernize from the top-down, but some programs have taken to it better than others and some have outright resisted. Given that these programs are only staffed after a bid is won, I'm not sure what kind of vetting process could catch these kinds of inefficiencies.

Re:How not to build a ship: the USS Ford by ericd on Thursday June 08, 2017 @12:00AM (#14511834)
Is there some reason we can't make the penalty of cost overruns that the contractor eats it, with the provision that the government is not allowed to change the specs once committed, after a preliminary speccing phase where they work with a few bidders to see their proposals? I imagine that we'd start seeing much more realistic bids in a hurry, with potential overruns built into the bid.
Re:How not to build a ship: the USS Ford by gozur88 on Thursday June 08, 2017 @05:49PM (#14517435)
Periodically we try fixed price contracts and it never really works out. It's fine if you're ordering hammers or assault rifles - something that gets built all the time in quantity.

But when you're building an aircraft carrier there are just too many unknowns, so you run into trouble in the very beginning when nobody wants to bid on it. Then if it looks like the overrun will be too large the contractor goes bankrupt and you end up with a half-finished ship and a gaping hole in the capability it was supposed to provide.

Re:How not to build a ship: the USS Ford by dragonwriter on Wednesday June 07, 2017 @06:46PM (#14510452)
> The military is always in a bind with contractor selection. If the don't choose the lowest bidder they get hauled up in front of a Senate committee full of people grandstanding for the next election accusing them of taking care of cronies.

No, they (or, rather, contractors) solved that problem by assuring that all contracts are divied up between as many states and Congressional districts as possible, so that anyone in Congress attacking any procurement is attacking jobs in their own district, and cost controls are less important because the overruns are also producing work, often also widely distributed.

Of course, this also produces the problem (for the military, not contractors) that any attempt to impose accountability on contractors has political problems that are similarly widespread.

Re:How not to build a ship: the USS Ford by stcredzero on Wednesday June 07, 2017 @06:42PM (#14510423)
The military is always in a bind with contractor selection. If the don't choose the lowest bidder they get hauled up in front of a Senate committee full of people grandstanding for the next election accusing them of taking care of cronies.

Isn't there some famous economics paper somewhere that shows strategies like median bid produce much better outcomes?

Re:How not to build a ship: the USS Ford by teddyh on Wednesday June 07, 2017 @07:00PM (#14510531)
Do you have a reference to this? I’m particularly curious if they address the secondary effects this will have on bids, and if the strategy then remains viable.
Re:How not to build a ship: the USS Ford by ams6110 on Wednesday June 07, 2017 @08:00PM (#14510857)
Could you do something like adjust the bids by the average percentage overrun the contractor has on prior projects?