Re:Microsoft Planner by yardie on Monday June 06, 2016 @05:07PM (#11850389)
Is anyone using gantt[1] charts? I've been using them for product planning for years. I know the kanban style planners are all the rage but I like the proceduralness of having the entire project laid out in front of me.

[1]https://en.wikipedia.org/wiki/Gantt_chart

Re:Microsoft Planner by UK-AL on Monday June 06, 2016 @05:11PM (#11850431)
Gnantt charts force you to plan the entire thing up front.

That's at odds with the more agile way people develop software today.

Plus they almost never match up to reality. Good for planning the sequence of things, but don't expect them to be accurate over the long term.

Re:Microsoft Planner by exclusiv on Tuesday June 07, 2016 @03:14AM (#11852924)
Agreed although we typically ensure we have plenty of tasks in parallel so one missed item doesn't throw off the whole schedule. Our Gantt charts are therefore ugly. :)
Re:Microsoft Planner by monk_e_boy on Monday June 06, 2016 @05:59PM (#11850769)
Gantt charts are great for showing task dependencies, but I agree that they rarely predict task length correctly.
Re:Microsoft Planner by patrickg_zill on Monday June 06, 2016 @05:54PM (#11850733)
Yes, they are useful. I like the ability to use TaskJuggler, a Ruby program, where you can edit the project info via your favorite text editor, then run TJ against it to produce various reports.

The nice thing about Gantt is that it can show up your expectations as being too optimistic, very quickly.

Re:Microsoft Planner by 1123581321 on Monday June 06, 2016 @05:24PM (#11850527)
Some of my coworkers use them. They aren't helpful tools for actual planning, but they look organized and that appearance helps sell projects to internal and external customers.
Re:Microsoft Planner by tacos on Monday June 06, 2016 @07:51PM (#11851431)
Gantt charts are tools for planning and scheduling. It got Hoover Dam done two years ahead of schedule. It'll probably be useful for your Rails app, too.
Re:Microsoft Planner by 1123581321 on Tuesday June 07, 2016 @02:04AM (#11852689)
Yes, they work well in operations that have many parallel steps which must be performed once, correctly, and in the correct time and order, and where the effort is quantifiable. While Hoover Dam was constructed on an unprecedented scale, the project planners could still do reliable man-hour calculations for many parts of the project.

Most software development projects lack those properties. Many software projects live or die by how well the "last 90%" of development goes (as opposed to a public works project which has much more critical initial work), but a Gantt chart usually represents that entire effort with one bar.

Re:Microsoft Planner by tacos on Tuesday June 07, 2016 @08:32AM (#11853981)
It's a bar chart; you're free to plot whatever subset of data you wish. If you're working with a team and you can't represent at least the next few weeks on a Gantt chart you're not engineering--you're playing software bumper cars.

Having team members sign up for brief work items (2-3 days max), charting it out, then watching where it strains is useful and often humbling.