It's a bar chart; you're free to plot whatever subset of data you wish. If you're working with a team and you can't represent at least the next few weeks on a Gantt chart you're not engineering--you're playing software bumper cars.
Having team members sign up for brief work items (2-3 days max), charting it out, then watching where it strains is useful and often humbling.
Most software development projects lack those properties. Many software projects live or die by how well the "last 90%" of development goes (as opposed to a public works project which has much more critical initial work), but a Gantt chart usually represents that entire effort with one bar.