Re:First new U.S. nuclear reactor since 2016 is now in opera... by mpweiher on Wednesday December 27, 2023 @06:28PM (#38788156)
Oh good grief, not that Lazard "study" again.

They took the cost to build Vogtle, which is one of the most or even the most expensive outlier in terms of time/cost overruns of all time, and decided to make that the baseline for "the cost of nuclear power".

When the average time to build a nuclear reactor in the world has consistently been around 7.5 years. For the last 50 years, and also for the ones that came online in 2022, lest you think these were just the bygone good old days.

https://www.sustainabilitybynumbers.com/p/nuclear-constructi...

Re:First new U.S. nuclear reactor since 2016 is now in opera... by adrianN on Thursday December 28, 2023 @07:07AM (#38792635)
Which new nuclear would you suggest instead? Hinkley C will cost about $160/MWh, right in the range given by Lazard.
Re:First new U.S. nuclear reactor since 2016 is now in opera... by mpweiher on Thursday December 28, 2023 @07:24AM (#38792760)
I would suggest we look at overall stats instead of isolated examples.

Time to construct a nuclear plant takes on average 7.5 years, a number that hasn't really budged in the last 50 years.

https://www.sustainabilitybynumbers.com/p/nuclear-constructi...

And since financing (i.e. interest) is the primary cost of nuclear (~50%), time is money.

Hinkley and Flamanville are examples of the EPR, a brand new reactor type that is both at the start of its learning curve, always problematic, and also apparently a design that is particularly difficult to build. And both Europe and the US haven't really built any nuclear plants for quite a long time, so the know-how to build them is just not there. Oh, and the regulators sometimes change regulations after parts of the plants have been built so they have to tear down what they have built and start again.

These are obviously all solvable problems, and mostly solvable by just building more. The problem is that we didn't build enough. Just build more.

Re:First new U.S. nuclear reactor since 2016 is now in opera... by adrianN on Thursday December 28, 2023 @07:56AM (#38793024)
Construction time is misleading. It takes a few days to a couple of weeks to build a wind turbine, but at least in Germany a wind turbine construction project takes more than five years.

So what better estimate would you suggest? What nuclear power plants where built in the last decade or so, for how much do they sell their power? How big will their decomissioning costs be per MWh?

Re:First new U.S. nuclear reactor since 2016 is now in opera... by mpweiher on Thursday December 28, 2023 @10:21AM (#38794243)
> Construction time is misleading.

Please support your claim.

We were talking about cost, and cost is directly proportional to construction time because financing (interest) is the primary cost of nuclear power plant construction.

Re:First new U.S. nuclear reactor since 2016 is now in opera... by adrianN on Thursday December 28, 2023 @10:37AM (#38794439)
It’sa lot harder to find investors for a project that takes 20+ years from planning to first income than for a project that takes seven and a half years.

I’m still waiting for better cost estimates than what Lazard gives.

Re:First new U.S. nuclear reactor since 2016 is now in opera... by mpweiher on Thursday December 28, 2023 @11:36AM (#38795217)
Simple:

Take the Vogtle-3 time, divide by average time to construct a nuclear reactor.

Apply factor to Lazard "estimate".

Re:First new U.S. nuclear reactor since 2016 is now in opera... by hef19898 on Thursday December 28, 2023 @12:17PM (#38795708)
If it is so simple, can you do that math for us?
Re:First new U.S. nuclear reactor since 2016 is now in opera... by adrianN on Thursday December 28, 2023 @01:25PM (#38796665)
Even going by that ridiculously oversimplified calculation, and taking best-case numbers 0.75*$141 (10 years from first concrete poured to grid connection vs your 7.5 years average) is still barely competitive with worst-case Wind+Storage and more expensive than solar as Lazard estimates. And those are proven numbers from real projects not some pie in the sky guesstimates.
Re:First new U.S. nuclear reactor since 2016 is now in opera... by mpweiher on Thursday December 28, 2023 @02:20PM (#38797373)
Your numbers don't add up.

Vogtle was only delayed by 25%, 2.5 years? I thought it was such a disaster and this proved nuclear doesn't work?

Now it's all good?

This says the delay was 7 years:

https://apnews.com/article/georgia-nuclear-power-plant-vogtl...

Oh, and the plant will still be cost effective, apparently, even with those delays.

Oh, and the solar numbers include sufficient batter storage? I saw something about 4h for half the capacity on some of the graphs. Most didn't explain at all.

Re:First new U.S. nuclear reactor since 2016 is now in opera... by adrianN on Thursday December 28, 2023 @11:17PM (#38801709)
As I said above, where you didn't believe me, construction times are misleading. First concrete poured was 2013. If you don't like the numbers, please suggest a better cost estimate. As it is, nuclear seems to be expensive.
Re:First new U.S. nuclear reactor since 2016 is now in opera... by mpweiher on Friday December 29, 2023 @10:02AM (#38805656)
"LCOE of less than $30/MWhre for 40-60 years"

https://web.mit.edu/kshirvan/www/research/ANP193%20TR%20CANE...

Re:First new U.S. nuclear reactor since 2016 is now in opera... by natmaka on Thursday December 28, 2023 @10:12AM (#38794129)
Mean project cost over-runs: Nuclear power 120% Oil and gas 34% Mining 27% Fossil thermal power 16% Wind 13% Energy transmission 8% Solar 1%

https://www.enr.com/articles/55774-oxford-professors-latest-...