Re:$60/MWh for advanced nuclear electricity is achievable: G...
by jeffbee on Monday April 03, 2023 @06:37PM
(#35432307)
There are panels in NREL's PV Lifetime Project that are on pace to have 80% rated output after 200 years. https://www.nrel.gov/docs/fy22osti/81172.pdf
PV "lifetime" is overblown fossil industry propaganda. It does not factor into any economic decision.
Re:$60/MWh for advanced nuclear electricity is achievable: G...
by crote on Monday April 03, 2023 @06:25PM
(#35432166)
PV is now being sold with a 25-year warranty - it'll still have at least 80% capacity after that time.
As the article rightly points out, it often just makes more economic sense to replace them earlier due to improvements in panel technology. There isn't really a technical reason to replace them.
1: https://energy.mit.edu/news/study-even-short-lived-solar-pan...