Time to go to the local charity shop and buy some wool sweaters.
try this one from 20 years ago:
http://news.bbc.co.uk/1/hi/uk/3034088.stm
(it's on this topic of energy)
Gas 38%
Coal 32%
Nuclear 23%
Oil 4%
Others 3%
Compare that to the use of renewables and the reduced dependency on fossil fuels today and at least we’ve taken some big steps in the right direction since then.There isn’t much to like about the current situation, but it does mean the danger of relying on supplies of non-renewable fuels has been shown beyond any doubt. If we do experience one of the bad scenarios with rolling power cuts this winter, it must be near-certain that whoever forms the government for the rest of the 2020s will get elected on a very green platform. If important steps towards making us both more resilient and more environmentally friendly then get taken sooner, that’s one small victory at least.
Overall the UK grid is probably too dependent on wind energy, with all the variability that involves.
Right now gridwatch.org.uk is showing about 13.5GW from wind (40% of demand), but I've seen some days when there has been well under 1GW.
We need a lot more storage, even battery storage plus wind is way cheaper than current gas shortage induced prices, and both wind turbines and batteries are getting cheaper
> Sites with a continuous manufacturing process, not sustainable through BEIS standby generation, where regular shutdown for 3-hour periods is not possible and would cause significant financial damage
I wonder if this includes Agile offices, it seems like a broad definition!
Very broad indeed, though I think it's just qualification for asking, not grounds for acceptance, (thankfully)
One thing I'm curious to know is what it's like on the distribution side though, getting these requests and then approving them (or not)
I wonder if they only get serious requests (say steel mills and hospitals) or if they also get requests from non-essential businesses who shouldn't be on the list?
Most data centers should have back up power, so the question of whether Facebook, Twitter and Amazon get cut off probably doesn't need to be asked.
If you've never been in a secure datacenter when they throw, it's fun.
> If you've never been in a secure datacenter when they throw, it's fun.
I find your ideas intriguing and would like to subscribe to your newsletter.Seriously, though, do tell us more.
They announced it over the PA because it was a planned transfer - and then all the "normal" lighting went off (think overhead fluorescents) at the same time the emergency lighting came on - the power to the servers and anything plugged into the racks didn't even flicker, of course.
There was a huge thunking sound from somewhere (I assume something disconnecting from grid power) and the muted roar of the generators starting. A few moments later, the main lights came back on.
It was an entirely different experience than a normal power failure, where everything goes quiet - you knew something happened, but other than that it all worked smoothly.
(Regularly) shutting down such operations could quite realistically bankrupt them.
The report showed, under a base case scenario, that margins between peak demand and power supply were expected to be sufficient and similar to recent years thanks to secure North Sea gas supplies, imports via Norway and by ship.
Any operator that didn't have such contingency plans would be negligent.
Is it going to happen in reality: hopefully not
Edit: I have a feeling that the article may be referring to the 3 hour Loss of Load Expectation (LOLE) service level target for the year.
This isn't quite the same as a three hour blackout.
I'm not sure though because the sky article doesn't reference its sources.
Which may be this:
https://www.nationalgrideso.com/document/264521/download
or it might not?
edit2:
actually I think it's this:
https://www.nationalgrideso.com/document/268346/download
edit3:
Found it, its not the LOLE target, but the response to scenario 2 on page 10 of the second link:
scenario 1: "In this scenario we assume that we have no electricity interconnector imports from France, Belgium and the Netherlands (these are assumed to provide a de-rated capacity of 3.9GW in the Base Case). It is assumed that we import 1.2GW from Norway and export 0.4GW to Northern Ireland and Ireland."
scenario 2: "In this scenario we assume the same assumptions as Scenario 1, but with an additional 10GW CCGTs unavailable for a two-week period in January1. These assumptions have been chosen to illustrate the potential impact on the electricity system if there was insufficient gas supply in Great Britain."
"Should this scenario happen, it may be necessary to initiate the planned, controlled and temporary rota load shedding scheme under the Electricity Supply Emergency Code (ESEC). In the unlikely event we were in this situation, it would mean that some customers could be without power for pre-defined periods during a day – generally this is assumed to be for 3 hour blocks. This would be necessary to ensure the overall security and integrity of the electricity system across Great Britain. All possible mitigating strategies would be deployed to minimise the disruption."
Which I think would then follow this set of rules:
https://assets.publishing.service.gov.uk/government/uploads/...
final: I think my information here is mostly right. But you should not base your electricity operational decisions on it!