Re:California grid set record of 97% renewable power on April 3 by doikor on Thursday April 21, 2022 @04:27AM (#31107133)
> It's not like you can ramp a coal-fired or nuclear power station up and down on a whim either though.

At least nuclear you can relatively fast. In terms of KW/min change rate faster then most gas peaker plants. It is not done much outside of France though as the operating costs of a nuclear power plant are pretty much identical when operating at 5% or 100% output.

edit:

German nuclear power plants also used to do load matching.

https://www.oecd-nea.org/upload/docs/application/pdf/2021-12...

Source for the KW/min change rate of nuclear vs CCGT/coal

https://snetp.eu/wp-content/uploads/2020/05/SNETP-Factsheet-...