Re:Tasking developers with creating detailed estimates is a ... by HPsquared on Friday November 19, 2021 @07:36AM (#29276526)
Lognormal distribution is always a good one.

It's applicable where the randomness has a multiplicative rather than additive effect. For example, the work may double or be halved. Lots of natural processes work this way.

https://en.m.wikipedia.org/wiki/Log-normal_distribution

Re:Tasking developers with creating detailed estimates is a ... by marcosdumay on Friday November 19, 2021 @04:40PM (#29282917)
An useful property is that the Law of Large Numbers doesn't apply to it, so all of your estimate history is basically useless. Also, when you add enough estimates, the total time to completion is mostly determined by the error in one or two of them.
Re:Tasking developers with creating detailed estimates is a ... by jbay808 on Friday November 19, 2021 @11:57AM (#29279313)
I've written about this before more extensively, but my previous company tracked time vs predictions very rigorously and extensively, and they always fit a lognormal distribution shockingly well.