Ergo, in the worst case, any given single component's ballooning time can dominate the overall project schedule.
Which turns estimation into a game of "How certain am I that no component's time will explode?" To which the answer in any sufficiently complex system is "Not very."
I'm pushing my work to move to something more like a converging uncertainty plot, as milestones are achieved and we can definitely say "This specific component did not explode."
Our PMs aren't used to hearing an idealized minimum schedule time + an ever decreasing uncertainty percentage based on project progress, but it feels like less of a lie than lines in the sand based on guesses.
(Note: This is for legacy integration development, which probably has more uncertainties than other dev)
The funny thing is the risks that were removed all occurred during the project. We should have stood our ground.