Re:Activists who embrace nuclear power
by PoignardAzur on Tuesday February 23, 2021 @08:33AM
(#26237011)
Part of the problem with Flamanville is notoriously that France hasn't built a new nuclear reactor for 20 years, and a lot of the expertise has been lost; also, the ASN's safety regulations have become a lot stricter in that time.
So I think overall GP's points apply.
Interesting you mentioned France, the only project they are building is Flammanville 3 which started in 2007 with an estimated cost of ~3 billion euros, it is now estimated to go online in 2022 with an estimated cost of 19 billion euros. That's just construction cost.
Regarding the cost for decommissioning, the European commission has actually called out France for currently significantly underfunding the cost by a factor of 3 or 4.