Re:CDC website built by Deloitte at a cost of $44M is abando... by ethbr0 on Sunday January 31, 2021 @12:38AM (#25976351)
> most missteps happen early, dooming projects before anyone sits down to code

This one is more insightful (in the big non-tech enterprise / government spaces). Because the takeaway for most HN developers who flip between projects should be: (1) learn how to recognize one of these projects & (2) stay away / find a new job when you do.

You'll save years of your work.

Re:CDC website built by Deloitte at a cost of $44M is abando... by rabidrat on Sunday January 31, 2021 @02:10AM (#25976807)
How might you recognize a project like this?
Re:CDC website built by Deloitte at a cost of $44M is abando... by mpfundstein on Sunday January 31, 2021 @03:22AM (#25977112)
Ask yourself some critical questions.

- is the scope well defined?

- do I understand the value add and agree with it?

- do I feel as if all stakeholders are aligned and adequately involved?

- do I think the team can pull it off ?

- do I think the mood and style fits myself?

- do I think the timelines and budgets are realisitc?

- do I agree with the level of transparency from management?

Etc etc

Ask yourself these questions - and more - and you will discover the answer for yourself.

In the end listen to your guts.

One important nuance: A project can be a major fail overal but a big success for you. Big check, new knowledge, rich connections...

Re:CDC website built by Deloitte at a cost of $44M is abando... by ethbr0 on Sunday January 31, 2021 @09:56AM (#25979265)
In addition to what others have said, from my previous experience:

- Does the customer have an IT org capable of fulfilling basic tasks you won't be authorized to do (app / db access, AD / rights modification, firewall adjustment, AV adjustment) in a timely manner?

- Can the customer provision necessary machines in a timely manner? If using VMs, is the virtualization team competent with their chosen platform?

- Does this project directly threaten the job of anyone whose blessing / help is required to successfully deliver the project?

- Is your leadership / your customer champion intelligent and willing enough to say "No" to scope creep when the customer gets excited?

- Do the PMs attached to the project have a basic understanding of how software is built and the systems involved?

- Does their management understand the actual processes being interacted with? (Major red flag! If their management / leaders say things in meetings that demonstrate a basic lack of understanding in what their own people do, run)

Re:CDC website built by Deloitte at a cost of $44M is abando... by mongol on Sunday January 31, 2021 @02:34AM (#25976929)
I think a tell-tale sign is if they apply the waterfall approach.
Re:CDC website built by Deloitte at a cost of $44M is abando... by GVIrish on Sunday January 31, 2021 @08:27AM (#25978646)
That won't save you at all. A lot of federal IT contracts are now written to mandate using Agile or Scrum. Many other forms of dysfunction that doom projects remain.
Re:CDC website built by Deloitte at a cost of $44M is abando... by razakel on Sunday January 31, 2021 @02:50AM (#25976987)
Didn't the guy who coined the term give it as an example of a development model that never worked?
Re:CDC website built by Deloitte at a cost of $44M is abando... by bdavis__ on Sunday January 31, 2021 @08:42AM (#25978744)
they will say "agile", but will mean , "all requirements up front with an increment delivered every sprint".

which works very well if the developers and the customer really know what they want when the project starts.