Re:New nuclear plant at Sizewell set for green light by pasabagi on Friday October 30, 2020 @09:10PM (#24948282)
Construction projects are inherently unpredictable, because it's building something large, bespoke, and in constantly varying conditions. Nuclear plants are very complex, so that obviously raises the level of unpredictability.

Every manufactured object has an insanely long and convoluted dependency chain, where each link is subject to disappearance due to factors completely out of your control. Especially objects that require special or unusual parts.

Then there's actually building the thing, which can go wrong for a million reasons before you've even reached the grand and rolling lands of human error.

Re:New nuclear plant at Sizewell set for green light by roenxi on Friday October 30, 2020 @10:04PM (#24948585)
Article says:

"However, the BBC understands that the fact Sizewell C is a carbon copy of Hinkley - which has seen work on a second reactor there completed 30% more quickly than the first - is thought to have substantially mitigated that risk."

It sounds like it should be pretty easy to budget for this plant. Plans are allowed to include a 20% "we don't know what this is going to be spent on but something will come up" for surprises.

Re:New nuclear plant at Sizewell set for green light by pfdietz on Friday October 30, 2020 @11:57PM (#24949023)
> Construction projects are inherently unpredictable

And yet, renewable projects typically come in within 10% of the contracted price.

Re:New nuclear plant at Sizewell set for green light by imtringued on Saturday October 31, 2020 @06:39AM (#24950335)
If each solar farm consisted of one giant solar panel I'm sure we would see exactly the same problem. In reality building a solar farm involves redoing one simple step over and over again. It's much easier to scale up.
Re:New nuclear plant at Sizewell set for green light by onion2k on Saturday October 31, 2020 @02:50AM (#24949606)
Offshore windfarms cost billions. A 10% overspend is quite significant.
Re:New nuclear plant at Sizewell set for green light by pfdietz on Saturday October 31, 2020 @08:19AM (#24950806)
Much better than a 300% overspend. Any renewable project that is going in that direction would be cancelled. Not only are renewables easier to build in small modules, but the staged build-out allows any problems (like, bad cost estimates) to be identified and fixed (or aborted).

The modular nature of renewables also allows them to be much more resilient in the face of component failure, or in face of construction errors (with the exception of common mode design failures). This means they can be installed with less skilled labor that makes more mistakes.

Renewable fields are akin to server farms w. large numbers of replaceable blades. Nuclear plants are like mainframes.