Reviving the nuclear industry will be painful and costly, but the same is true for reviving and rehabilitating other heavy industries that have withered away, if and when these countries ever choose to do so. The justifications for resolving ourselves to their death are hypocritical. Both solar and wind power manufacturing industries, not to mention the automobile industry, would be non-existent in the U.S. without heavy subsidies. For example, special trade zones that incentive partial manufacturing of certain wind generator components in the U.S., or in the case of automobiles flat-out quotas. But even then the future of these industries in the U.S. remain tenuous. Fortunately for consumers (but less so for semi-skilled and skilled factory labor), solar panels, wind generators, and cars are easily imported; nuclear plants not so much, not unless the modular reactor designs take off.[1]
[1] Interestingly, the skillsets, including project management techniques, for these industries can't be imported, either. Toshiba bought Westinghouse because they thought they could use their superior heavy industry skills to rehabilitate Westinghouse and the American nuclear industry. But heavy industry skillsets are especially tuned to local industrial supply chains and labor pools, as well as domestic regulatory frameworks. Toshiba couldn't do squat with Westinghouse; it was deadweight from day 1.
[1] Fukushima being an obvious example. I'm neither an engineer nor nuclear cynic, but I was always skeptical of the claims nuclear engineers were making on the news in their self-defensive and, ultimately, self-defeating attempts to mitigate panic. They were far too credulous of engineering tolerances and quality control despite the evidence piling up in front of them regarding the probability of the supposedly improbable. Anyone remotely familiar with any kind of construction project knows things always fall short in the field.
I am hopeful about the new crop of companies currently designing SMRs. This was probably the way it should have been done from the onset, rather than pushing single unit power to hundreds of gigawatts.
I only began recording in 2018 particularly noteworthy reporting and research pieces (regarding any topic) I stumble upon. I just added the above to my personal bibliography for good measure.
For Hinkley, EDF have assumed the construction risk in return for an exceptionally high, guaranteed "strike price" for the electricity it produces.
But for Sizewell, it sounds like a different finance arrangement will be in place, likely where the UK government/public assumes more of the risk in return for a cheaper per-MWh price.
https://www.edf.fr/en/the-edf-group/dedicated-sections/inves...
Construction started in 2007, with estimated completion in 2012 at a cost of €3.3 billion.
As of 2020, the plant is still not complete and the cost has spiralled to €19.1 billion. It is now tentatively planned to go online at the end of 2022.
https://www.nytimes.com/2017/03/29/business/westinghouse-tos...
Areva, responsible for the construction of Olkiluoto-3 in Finland on a fixed price contract. Restructured and sold all of it's reactor business except Olkiluoto-3, which it still is liable for, to EDF.
https://en.wikipedia.org/wiki/Areva