Re:New nuclear plant at Sizewell set for green light by Reason077 on Friday October 30, 2020 @09:47PM (#24948478)
Well, EDF have not been so successful with their most recent project in France, Flamanville 3.

Construction started in 2007, with estimated completion in 2012 at a cost of €3.3 billion.

As of 2020, the plant is still not complete and the cost has spiralled to €19.1 billion. It is now tentatively planned to go online at the end of 2022.

Re:New nuclear plant at Sizewell set for green light by petre on Saturday October 31, 2020 @04:38AM (#24949904)
We saw what happened to Areva building reactors on a fixed cost contract. Today's economic realities do not quite let one plan a 10 year project on a fixed cost. 3.3bn do not equate to 2007 3.3bn in 2020. The Chinese are able to do it because they not a free market economy, they can force people to work at gunpoint.
Re:New nuclear plant at Sizewell set for green light by jnxx on Saturday October 31, 2020 @01:34PM (#24953437)
So, these things are not viable in a market economy? Why should they be pursued then?
Re:New nuclear plant at Sizewell set for green light by petre on Saturday October 31, 2020 @03:16PM (#24954356)
They are viable but I'm quite skeptical about accurately estimating the costs for a 10 year project. Concrete, steel, fuel, workforce costs fluctuate from a year to another, let alone 10 years. We'll just have to accept that there are going to be cost overruns.
Re:New nuclear plant at Sizewell set for green light by sudosysgen on Saturday October 31, 2020 @12:28AM (#24949139)
Comparatively to other nuclear companies and in aggregate, EDF has the best safety record, the cheapest energy when subsidies are taken out, and is solidly profitable. That one or two constructions went overbudget does not matter if the result is still head and shoulders ahead of the fray.