Houses typically go according to plan because so many of the processes and parts are standard. Even large mansions can go according to plan if you have good management (note that cheap management is rewarded for change orders and thus will ensure things don't go according to plan while better management will see that if they don't make a minor change now things won't go according to plan latter.
[0] Best example of this sort of logic that I have seen implemented is painting the golden gate bridge, just one properly sized and experienced crew painting from one end to the other and back again without the boondoggle.
The Project Production Institute take a similar view: that instead of modeling a project as a fixed thing, you focus on it as a production process.
Otherwise every 20 years they would need to hire, train, then fire 200 painters for a 6 month-long paint job project. 200 painters, managers, and etc. who will invariably be less experienced with the finer points of painting said bridge since they don't do it every day.
We do have ships, rockets, and a few other things that don't need wheels (tough they tend to have wheels of some form inside), but the wheel itself is still just incremental improvements on that first one way back...