Re:All late projects are the same (2011) [pdf] by rossdavidh on Sunday February 03, 2019 @07:56PM (#19073202)
While much of this is true, I think it also leaves out a very common cause of software being late, perhaps the most common. The time it will take is unknown, in some cases unknowable, and no one is willing to say so. "How long will it take?" (equivalently, "Can you do this feature set by this date?") The only honest answer is: "I don't know." Nonetheless, a date gets put on it.
Re:All late projects are the same (2011) [pdf] by mden on Sunday February 03, 2019 @08:37PM (#19073347)

  and no one is willing to say so.  
Except most engineers are perfectly willing to say so in my experience but management decides to ignore them or force them to say a made up number promising falsely not to hold them to it. Even worse what happens very often is an engineer would give an estimate and then a manager would "bully" it down to a lower number.

On the reverse of course it makes sense to have estimates otherwise how should managers or product people decide what should be done next?

A big part of the issue is we don't have good knowledge how to estimate work. It's not a skill that is heavily invested in and is wrongly assumed as an inherent ability.

Re:All late projects are the same (2011) [pdf] by jadedmgr on Monday February 04, 2019 @12:05AM (#19074114)
As a manager over a new project with a ridiculous release date, I'm subject to the same political bullshit as everyone else. At this point, I'm of the opinion that anything with a realistic ship date simply won't get funded. So all I do these days is commit to things that I am certain aren't achievable in the time frame on the table, just so that we can get the project off the ground in the first place. From that point, I immediately start to play the game of politics and showmanship to put together a narrative with the usual culprits for why a project is late. Shifting requirements, other teams that didn't deliver what we depended on, etc.

Then I make more promises and estimates, playing the emotional card of "sunk cost" to convince upper management to continue funding the team rather than torpedo the project. Then we ship, and I quickly get everyone on my team promoted "because we shipped" before it becomes clear to upper management that we shipped something essentially worthless to the company. Because we're in a huge profitable company, everyone can jump ship to the next shiny thing, and whoever is left holding the potato on its way to deprecation just gets re-org'd when it gets canned.

I know it's a bullshit game. But I play it well, and all the software developers on my team get paid and promoted because I am so good at it.

Re:All late projects are the same (2011) [pdf] by Techonomicon on Monday February 04, 2019 @02:14AM (#19074521)
You're subject to the "same political bullshit" because you choose to be. You don't have to partake in it, but you do. You can choose not to, you can choose to try to bring the company around you to greener pastures - but you don't.

You sound wise and such in general, but perhaps your time would be better spent making a difference in how people believe work should be done at a place that actually allows brewing better practices instead of lauding bad ones.

Re:All late projects are the same (2011) [pdf] by thecatspaw on Monday February 04, 2019 @03:05AM (#19074681)
This would just result in them not managing any projects anymore, and "Yes we can do it in 2 weeks" Joe will get them instead
Re:All late projects are the same (2011) [pdf] by lifeisstillgood on Monday February 04, 2019 @01:01AM (#19074282)
One day you might play it so well, you find yourself on the Board.

Will you then argue that all new projects should avoid deadline dates, that no project should have anything other than an MVP and a iteration plan after that?

How do we change the expectations?

Re:All late projects are the same (2011) [pdf] by jt2190 on Monday February 04, 2019 @03:18AM (#19074741)
> So all I do these days is commit to things that I am certain aren't achievable in the time frame on the table, just so that we can get the project off the ground in the first place.

This is exactly the point of the article: Organizations routinely fail to prevent untenable projects from moving forward.

Re:All late projects are the same (2011) [pdf] by jeffasinger on Monday February 04, 2019 @06:51AM (#19075559)
What I don't get about your strategy:

Why not work on something so valuable that even if it takes twice as long as the best estimate, with twice the headcount working on it, it would still be worth it?

As a a manager, I feel that helping to find projects that have that amount of value is an important part of my job, so that if I am fighting for a project my team's working on, I'm actually in the right from a business case point of view, not simply playing some BS political game.

If there are no projects that fit that value filter, then that's a completely different organizational problem.

Re:All late projects are the same (2011) [pdf] by natalyarostova on Monday February 04, 2019 @01:54AM (#19074467)
Lol holy shit, this explains so much of my experience that I never even knew.
Re:All late projects are the same (2011) [pdf] by bartread on Monday February 04, 2019 @10:56AM (#19077308)
> I know it's a bullshit game. But I play it well, and all the software developers on my team get paid and promoted because I am so good at it.

On one level I have to take my hat off to you because you sound like exactly the kind of manager - one who has your team's back - that a lot of people would want to work for.

On another level you're part of the problem: you're wasting organisational resources that could be better and more profitably used elsewhere.

Still, needs must I suppose, because the real fault here - as the article itself hints - is in the determination of what the most valuable use of everyone's time is. I.e., if projects are going to be late (and they are) then you ought only to deploy teams to work on the ones with a putative 10x ROI.

Re:All late projects are the same (2011) [pdf] by a_imho on Monday February 04, 2019 @03:15AM (#19074726)
Though this be madness, yet there is method in ‘t
Re:All late projects are the same (2011) [pdf] by marvin on Monday February 04, 2019 @08:38AM (#19076249)
I had this experience recently. We don't use a lot of detailed estimates in my team, because the work needs to be done regardless, and the estimates are then largely a waste of time.

But there was one occasion, where a product launch had been announced by a C*O before the product was finished, and the engineers were very clear that this launch date was impossible. So there was a lot of drama and bad feelings, and the engineering team eventually said, "okay, let's make a detailed estimate so we can be certain". The estimate came in at three weeks development time, one week after the announced launch date.

One week of the estimate was meant for testing and fixing problems that are found in testing. The business experts immediately jumped on this: "Testing and fixing unplanned errors won't be a big deal and certainly not a whole week. We'll skip that so we can get it done in two weeks".

Thankfully, this is retail banking, so releasing an obviously broken product flies even less than missing the deadline. The product was eventually launched uneventfully, one week after the detailed estimate and two weeks after the announced launch date. All in all a success.

Re:All late projects are the same (2011) [pdf] by rossdavidh on Sunday February 03, 2019 @09:47PM (#19073594)
I have, on more than one occasion, said so, and the response was always bafflement or annoyance, and in either case and unwillingness to accept that answer. When I was younger, I would eventually give a guess, along with a "...but that's just a guess". Nowadays, I don't even give that, because the caveats get forgotten/ignored.
Re:All late projects are the same (2011) [pdf] by codycraven on Sunday February 03, 2019 @10:28PM (#19073770)
I have this sort of discussion, at minimum, three times a week (we're in-house developers). Very often the project scope isn't even defined and upstream dependencies are known to be critically lacking and will need to be augmented to even perform the work. Yet we're always pressured for dates and the caveats given are immediately forgotten and almost never communicated.

The biggest pet peeve is when I give an estimate such as "I don't currently see a reason why we can't deliver X by the end of next week, assuming no other priorities come up." Of course something more important comes up in the mean time and I get scolded in a large meeting with a statement such as "You promised me I'd have X by Friday!" — this is especially infuriating when it is the PM's other project that is the higher priority interruption.

Re:All late projects are the same (2011) [pdf] by lifeisstillgood on Monday February 04, 2019 @01:06AM (#19074296)
It might not be viable, but I used to "publish" internally my own project one pagers, and update the timelines - any discrepancies simply became a shield for this future arguments.

In short it sounds like you don't have the power to say no - but actually you do.

Re:All late projects are the same (2011) [pdf] by chimprich on Monday February 04, 2019 @09:50AM (#19076737)
It doesn't get a lot of love on HN, but these problems are addressed by Scrum. Sprints have a pre-allocated amount of work in them, which makes estimating easier. You can't predict exactly how much time you'll lose through meetings and emergencies, but estimating in story points will add a rough statistical estimate.

Of course, if you already have a toxic development culture like the one you describe, then they'd probably abuse more agile processes too.

Re:All late projects are the same (2011) [pdf] by watwut on Monday February 04, 2019 @04:51AM (#19075072)
Instead of caveats, add to the estimate. Every caveat is some additional time.

Another thing that helped us is to answer with ranges instead of dates e.g., "this will take 1-3 weeks".

Re:All late projects are the same (2011) [pdf] by wwweston on Monday February 04, 2019 @03:05AM (#19074682)
You could argue that these are some of the many forms of "starting late":

* If you just don't know how long something is going to take, and you need a date, then you're late to doing the work to know how long it will take.

* If you do know how long something is going to take, and it's longer than a externally imposed date, then you know exactly how late you are.

This is partly just playing with semantics, but it's also a way of talking around different views of the problem, in this case emphasizing that if dates are a feature, reasonable estimates are themselves a project. If the estimate work hasn't been properly completed and understood before dates are given, obviously, the larger project is by definition already late because there's work that needed to be done before beginning and wasn't.

And I think if you take this view, it's easier to see that it's a project or team management problem rather than an engineering productivity problem.

Re:All late projects are the same (2011) [pdf] by lodi on Monday February 04, 2019 @03:41AM (#19074820)
I completely agree; you discover timelines in the process of doing the work.

The problems start when you need to give an estimate before even being allowed to start working on something.

Re:All late projects are the same (2011) [pdf] by rossdavidh on Monday February 04, 2019 @10:18AM (#19076956)
In at least some cases, you have to be halfway into doing the work (or more) before it becomes apparent that there is a big, previously-unknown subtask or requirement that invalidates the plan for doing it. In other words, if you really know enough to give a good estimate, you are probably mostly done.
Re:All late projects are the same (2011) [pdf] by tcmb on Sunday February 03, 2019 @08:22PM (#19073290)
If you can't be flexible on the delivery date, you have to be flexible in feature scope.

That means building a simple verison first that still fulfills the purpose while not being perfect or polished. Then iteratively improve it to what you and the customer ideally want.

That way, if the deadline comes before you're done, you at least have a working version that fulfills the basic need and allows the kind of workflow that's necessary, even if it still has some rough edges or even gaps in rarely used areas.

Of course this approach requires you to write your contracts in a way that doesn't tie you down too strictly on how exactly things will be solved.

Re:All late projects are the same (2011) [pdf] by zdragnar on Monday February 04, 2019 @03:05AM (#19074680)
Sadly, when it comes to contracts, that gets boiled down in most customers' minds to: "Vendor only commit to delivering buggy and incomplete software". It's a hard sell for most types of projects, even if it's the actual reality of most projects.
Re:All late projects are the same (2011) [pdf] by chii on Monday February 04, 2019 @03:17AM (#19074738)
You sell a small portion, for the same smaller price tag. Then when the deadline comes, the customer checks to see if you delivered, and decides to continue the contract or find somebody else.

So the customer can have assurances that they aint gonna be bogged down with sunk costs. The developer can have more frequent deliveries.

Re:All late projects are the same (2011) [pdf] by wwarner on Sunday February 03, 2019 @08:28PM (#19073311)
Disagree. Upper and lower bounds can be realistically estimated. Whether the estimates meet the demands of the market is another question. I'm an engineer, not a CEO or sales person, but I'm a firm believer in selling first and building it later. Building it after it's been promised is one of the best ways to limit scope.
Re:All late projects are the same (2011) [pdf] by chii on Monday February 04, 2019 @03:20AM (#19074750)
> Building it after it's been promised is one of the best ways to limit scope.

only if those doing the promising knows what's within bounds and what's wildly off bounds!

If the sales person makes wild promises because his commission depends on making the sale, but not the delivery, then the whole organization's interests are not aligned properly, thus fail.

If the salesman's commission comes from successful delivery, then he can bring in an engineer who can at least balance the promises. Who knows, may be different departments can cross-contaminate, leading to a better, more well rounded organization.

Re:All late projects are the same (2011) [pdf] by ryan-allen on Monday February 04, 2019 @12:31AM (#19074195)
> but I'm a firm believer in selling first and building it later

Please elaborate! :)

Re:All late projects are the same (2011) [pdf] by wwarner on Monday February 04, 2019 @11:14AM (#19077490)
In a word, it's "agile".

Let me first acknowledge that there my thoughts are a mixture of the types of projects that I've been working on, my own personality and my own path dependent experience. In particular, my way is intentionally short sighted and won't work for a project plan that takes five years. Also, for sure, if the sales team/ceo is wrong and the project isn't worth doing, then doing it "lazily" won't fix that. But with that out of the way, here's what I mean.

The engineering team has it's own values and priorities and they just don't have anything to do with what really matters to customers. In the end, everyone brings in emotional baggage from the last project they worked on, and that's what's important until new information comes in from customers and the sales team.

So what I shoot for is taking the requirements that we have and producing a long range design that will meet those and little more, and then producing features as quickly as possible and presenting it to the customer (or the customer's advocate).

Why does it limit scope? Because the deadline doesn't move! To meet the most important requirements in a way that actually sells the product, lower priorities are are cut or reframed.

Re:All late projects are the same (2011) [pdf] by rossdavidh on Sunday February 03, 2019 @09:48PM (#19073602)
I have seen "realistic estimates" be off by multiples. Also, "build it after it's been promised" is not making any sense to me, perhaps you can restate that somehow?
Re:All late projects are the same (2011) [pdf] by kgilpin on Monday February 04, 2019 @07:43AM (#19075836)
I think you’re missing the point of the article. His original theses was that we aren’t good enough at estimation. And in fact much hand wringing over estimation has been done in this industry over the last 6+ decades.

Now he’s amending his opinion to state that estimation is not really the core issue. The core issue is that projects are doomed from the start by mismanagement. Issues such as: racing to catch up with a competitor (giving the s/w group an impossible deadline), or starting a project whose business value is so low that minor time and cost overruns reduce the actual value to below zero (at which point people start blame shifting to try and hold on to their jobs).

Re:All late projects are the same (2011) [pdf] by watwut on Monday February 04, 2019 @04:51AM (#19075073)
It is not about it being unknowable. If it would, the estimates would be all around the place. Sometimes short sometimes long.

Instead, we systematically underestimate.

Re:All late projects are the same (2011) [pdf] by agumonkey on Sunday February 03, 2019 @10:26PM (#19073763)
Isn't there some pseudo quantitative form of estimation based on a first draft system network diagram ?