If you used modern cutting-edge designs things might look differently, but anything that is actually being built are updated versions of designs from the 70s. Nobody wants to spend lots of money on research and take the risks with building more radical new designs.
They used to be required to pay into a fund for long-term waste storage, and that fund has about $40 billion now. But after the Yucca Mountain project was shut down, the nuclear operators had to store the waste in concrete enclosures on their own properties, so they went to court saying they shouldn't also have to pay the government to do nothing. In 2013 the courts agreed.
There are actually a lot of companies that want to spend money on R&D and build radical new nuclear designs, including Terrapower, Moltex, Terrestrial Energy, Flibe, Thorcon, Elysium, and many others. In the U.S. the NRC makes this extremely difficult.
A couple years ago I got to sit in a meeting between representatives from about a dozen of these companies and a former head of the NRC. The reactor people said their biggest problem was that the NRC requires a near-complete design before they'll even look at it, and then they give a straight yes or no. If yes you still just have a paper reactor, and if no then you're done. The design process costs several hundred million dollars and you have no idea whether the NRC will let you do anything with it. It's a very difficult environment for investors.
The reactor people said just a more phased process would help a lot. The NRC person dismissed their concerns, said it wasn't the NRC's job to help develop new technology or promote nuclear power, and wasn't interested in climate change.
But from people that I've talked to in the UK, they seem to be more afraid of nuclear than Americans. This seems to be a common trend in Europe. Many people citing radioactive mushrooms from Chernobyl.
Another bright spot is Canada, whose regulators are much friendlier to reactor R&D. Terrestrial Energy has gotten through the hardest part of their licensing process, and expects to have a demo MSR operating by 2025 or so. Seeing their success, Moltex has moved into Canada as well, after making little progress with UK regulators.
Probably not well.
https://www.technologyreview.com/s/612564/chinas-losing-its-... (China’s losing its taste for nuclear power. That’s bad news.)
https://www.theguardian.com/business/2019/jan/17/hitachi-set... (Hitachi scraps £16bn nuclear power station in Wales)
https://www.nytimes.com/2017/07/31/climate/nuclear-power-pro... (U.S. Nuclear Comeback Stalls as Two Reactors Are Abandoned)
https://www.independent.co.uk/voices/hinkley-point-managemen... (Hinkley Point management is the perfect illustration of how not to conduct a modern energy policy)
https://www.tampabay.com/news/business/energy/trigaux-abando... (Trigaux: Abandoning another nuclear project, Duke Energy mimics its failed Levy plant)
https://www.wfae.org/post/duke-cancels-florida-nuclear-proje... (Duke Cancels Florida Nuclear Project, Plans Solar Expansion)
Shutting existing nuclear without ramping renewables would be catastrophic. Best case scenario is extending their operating licenses 10-15 years in the future until generation capacity has been replaced. It only takes about a year to replace the generating capacity (including capacity factor) of a nuclear generator (which takes ~10 years to build) with renewables.
In the US, there are 65 pressurized water reactors (PWRs) with a combined capacity of about 65 GWe and 33 boiling water reactors (BWRs) with a combined capacity of about 34 GWe – for a total capacity of 99,221 MWe. ~50% more than this amount of generating capacity is coming online as utility scale solar over the next five years in the US. Five years! Replace the entire nuclear fleet with replacement nuclear in five years? Never.
https://pv-magazine-usa.com/2019/01/01/solar-tsunami/ (Developers have applied to build 139 GWac of large-scale solar projects in the territory of six grid operators – around five times what is currently online across the country – and that figure doesn’t even cover the entire United States. By any metric, we are looking at an unprecedented boom in solar development over the next five years.)
To really get a good idea why this is the case, check out the maps on the right side of https://www.eia.gov/electricity/monthly/#tabs_unit-4, and compare the maps between generating units coming online in the next 12 months to the map of generating unit retirements in the next 12 months. All new generation is solar, wind, and natural gas. All retired generation is primarily coal or nuclear.
To be blunt, no further commercial nuclear generation will be built. Maybe we subsidize renewables more? That'd be swank.
The links all just point to trends. The inventory just says the way things are. And then a map of actual plans? Who asked about actual plans?
That wasn’t the question at hand. The fundamental question at hand was the difference between old versus new nuclear technology, whether or not whatever the actual plans are.
But yeah, just drop links and say no. Really great. Top notch discussion.
From the Union of Concerned Scientists:
https://www.ucsusa.org/nuclear-power/cost-nuclear-power
> The first generation of nuclear power plants proved so costly to build that half of them were abandoned during construction. Those that were completed saw huge cost overruns, which were passed on to utility customers in the form of rate increases. By 1985, Forbes had labeled U.S. nuclear power "the largest managerial disaster in business history.”
> The industry has failed to prove that things will be different this time around: soaring, uncertain costs continue to plague nuclear power in the 21st century. Between 2002 and 2008, for example, cost estimates for new nuclear plant construction rose from between $2 billion and $4 billion per unit to $9 billion per unit, according to a 2009 UCS report, while experience with new construction in Europe has seen costs continue to soar.
Feel free to read the entire blog post to understand exactly why nuclear is so expensive it can't be built. There is also a link to a report the UCS published in 2009 and a financial analysis published in 2011 that goes into great detail.
It's no use saying it would be great in theory if it turns out not to work or be cost effective in practice. This problem dogs a lot of technologies but nuclear has a particularly bad case of making promises that it doesn't meet in practice.
And what Floridians are going yo do at night? Fornicate?
Knowing that most code deployments for server side software cannot claim the benefits of total rewrite from scratch, many of us would love to get a chance at trying exactly that.
What would this assessment look like for a nuke-to-nuke replacement, instead of nuke-to-wind/solar?
In other words, if they abruptly terminated use of all the aging nuclear plants today, and immediately started building totally new, highly modern nuclear power facilities, how would that stack up against this research favoring renewables?