Re:A $225 GPS spoofer can send sat-nav-guided vehicles into ...
by athenot on Thursday July 19, 2018 @09:00AM
(#17565784)
Really? $10 won't buy you much in terms of steel. You'd probably need a lot more than just a crowbar. I'm not saying trains are invulnerable to debris on the tracks, just that they are designed to handle small stuff on the tracks.
[ Parent
| on HN ]
Re:A $225 GPS spoofer can send sat-nav-guided vehicles into ...
by dsfyu404ed on Thursday July 19, 2018 @09:58AM
(#17566302)
Stop shopping at the hardware store and go to an actual steel supplier. If you don't need a lot of material then don't be picky and just by a drop to avoid a cut fee (and revise your design for whatever material you get).
Re:A $225 GPS spoofer can send sat-nav-guided vehicles into ...
by Robotbeat on Thursday July 19, 2018 @09:02AM
(#17565805)
A crowbar well-placed/used is sufficient.
Re:A $225 GPS spoofer can send sat-nav-guided vehicles into ...
by Faaak on Thursday July 19, 2018 @09:56AM
(#17566276)
10$ is around 10kg of steel. With that, you can make a crude derailer and easily (and I mean it) derail a train.
Re:A $225 GPS spoofer can send sat-nav-guided vehicles into ...
by IshKebab on Thursday July 19, 2018 @09:47AM
(#17566191)
A crowbar is not "small stuff on the tracks". Have you ever seen a train?
Re:A $225 GPS spoofer can send sat-nav-guided vehicles into ...
by athenot on Thursday July 19, 2018 @10:00AM
(#17566322)
Yes. They are designed for that stuff. Here's the biggest accident (in France) from having a large object on the tracks: 80 ton oversized load. Only the engine car derailled.
Trainset involved: 70 (Sud-Est)
Service: train 736, Grenoble to Paris
Location: PN 74, Voiron
Injuries: 2 dead, 60 injured
[Edit: date: 23 September 1988]
A special road transport with a weight of 80 tons became stranded on level
crossing 74. Train 736, rounding a curve toward the crossing, ploughed into it
at 110 km/h (68 mph). The large mass of the road vehicle made this crash much
worse than it might otherwise have been; the engineer and one passenger died,
and many more were injured when the first trailer was ripped open by debris.
Only the leading power unit derailed. This wreck, the most violent to date,
became a reference for the design and crash testing of safety features for the
next generation of TGV, as embodied by today's Duplex trainsets. These newer
trains have several deformable sections, at the front and rear of the power unit
and at the front of the first trailer, to manage and absorb crash energy without
damage to passenger compartments. Trainset 70 was never returned to service, and
the trailing unit 23140 became a spare in the Sud-Est fleet.