Re:Why Development Teams Struggle to Deliver on Time, on Bud... by bazooka_penguin on Tuesday June 05, 2018 @10:31AM (#17237929)
How do you estimate how much time a task will take, especially when it's a novel idea, at least for your developers?
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by mirceal on Tuesday June 05, 2018 @10:37AM (#17238002)
You break it down (effectively doing the work) as part of planning and after that you pretend that you have a working system. Make sure not to go into details and/or “take it offline” until the developer is tired/annoyed enough to just agree with you pipe-dream estimates /s
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by bazooka_penguin on Tuesday June 05, 2018 @10:51AM (#17238184)
I see, so you simply hire superhumans who finish the project before UX mockups are even available. Simple stuff. I think I'm ready to start my own consulting business
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by mirceal on Tuesday June 05, 2018 @10:55AM (#17238220)
You got it. Make sure every task can be done in half a day or less. That is key /s
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by commandlinefan on Tuesday June 05, 2018 @11:15AM (#17238434)
> How do you estimate how much time a task will take when it's a novel idea

In my experience, they just pretend it doesn't exist and remove it from the "plan". Where I see this the most is in figuring out how things work. For some reason, non-programmers have it in their head that once you've finished college, you ought to know (even though they don't) how everything that goes on a computer works instantaneously. We're going to use Apache Kafka! Ok, need to spend some time figuring out how that works. Um, ok, that should take like an hour, right? Because there's no time in the budget to learn anything. If you push back, they say, "ok, never use anything new that you have to learn. Only use the things you already know". That doesn't work either, because the things that we have to integrate with don't work with the old things. Or, "you don't need to know how that works, Bob knows how that works, just ask him. But don't let it take any time, because there's no time in the plan for that" And Bob is sick of all your questions that you'd know the answer to if you'd just spent a two or three days reading the online documentation and installing a test system and testing it out.

Re:Why Development Teams Struggle to Deliver on Time, on Bud... by markkanof on Tuesday June 05, 2018 @11:50AM (#17238822)
You hit on one of my favorite gems, "Bob has done something like that before, just ask him how to do it." The manager is envisioning that the team already possesses the knowledge necessary to get the task done, so there should be zero learning time involved. What this is missing though is that Bob isn't going to be solving the problem for the current task AND/OR Bob didn't even solve a similar problem, he just used the same tool or library that is now being used for the current task. If we had a Matrix like ability to instantanously transfer knowledge then this approach might work, but we aren't there yet.
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by LargeWu on Tuesday June 05, 2018 @10:32AM (#17237940)
You don't. That's the thing. Yet decision makers commit to deadlines anyway, and that's the problem.
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by crdoconnor on Tuesday June 05, 2018 @11:06AM (#17238336)
Invest time in determining the right approach and planning it out.

Most of that will be doing spikes: http://agiledictionary.com/209/spike/

It's one the most underappreciated agile concepts. I wish people would shut up about standups once in a while and give more thought to doing spikes.

Re:Why Development Teams Struggle to Deliver on Time, on Bud... by fjsolwmv on Tuesday June 05, 2018 @04:39PM (#17241818)
It wouldn't be easier if we didn't have to keep learning silly new words for everything. I used to do prototypes and proofs of concept, now I have to do spikes.
Re:Why Development Teams Struggle to Deliver on Time, on Bud... by crdoconnor on Wednesday June 06, 2018 @06:21AM (#17245815)
Spikes are not necessarily proofs of concept or prototypes. A spike is simply a task aimed at gathering information.

Spending 30 minutes researching four different libraries to see which one to would be a spike, for instance, but it doesn't necessarily involve building a proof of concept.