Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by mrb on Thursday March 29, 2018 @12:56AM (#16704597)
The average cost of a solar power plant is $1 per watt. So this budget would build a 200 GW plant. It would satisfy 10% of the world's demand of electricity. This is huge!

Edit: taking into account the capacity factor it would really only represent 3%; still impressive though.

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by rgbrenner on Thursday March 29, 2018 @01:32AM (#16704721)
You didn't count in the capacity factor for solar.. which is only 10-30% (depending on the type of solar plant they build).

So best case, 200 GW will only produce 525 TWh annually. This is equivalent to a 66 GW nuclear plant (nuclear has a 90% capacity factor).

Out of 20000 TWh electricity produced globally, that's only 2.5%.

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by Reason077 on Thursday March 29, 2018 @06:51AM (#16705983)
"So best case, 200 GW will only produce 525 TWh annually. This is equivalent to a 66 GW nuclear plant (nuclear has a 90% capacity factor)."

Sure. But these days, you'd be hard pressed to build 66 GW of nuclear for $200 billion. It's costing about US$30 billion for one 3.2GW nuclear plant currently under construction in the UK (Hinkley Point C). And it's probably a lot more than that by the time you account for eventual decommissioning costs and long term waste storage.

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by adventured on Thursday March 29, 2018 @07:31AM (#16706123)
China can still build 66GW for $200 billion in nuclear. They're the only large economy still aggressively pursuing nuclear over the next decade.

They have 19 reactors under construction right now that will add 21GW +/-, and 50-60GW of additional nuclear energy planned for the very near-term. Their goal is to add roughly 100GW+ of new nuclear energy output in the next 12 years.

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by cinquemb on Thursday March 29, 2018 @01:54AM (#16704810)
What kind of solar? If you are talking PV with storage, then id agree, but if its CSP with thermal storage (like molten salt) and if we use Gemasolar (19.9 MW)[0] as an example, their capacity factor is 63%, which is close to parity with geothermal but less than nuclear.

[0] https://en.wikipedia.org/wiki/Gemasolar_Thermosolar_Plant

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by rgbrenner on Thursday March 29, 2018 @02:08AM (#16704875)
That plant burns natural gas at a night to heat up the molten salt. That's why the capacity factor is so high. (Saudi Arabia could do that.. they currently burn fossil fuels for electricity.)

But it was very expensive.. about $360M for 20MW (or $18B per GW). The price they give -- $200B for 200GW -- would rule out this type of plant.

It's almost certainly PV.. which is currently $1/Watt for new utility scale plants. The price matches perfectly.

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by cinquemb on Thursday March 29, 2018 @02:48AM (#16705041)
Where are you getting your $1.2B? Closest thing I can find is 260M GBP[0], or about $364.0M at today's mid market fx rate or ~$728.0M at 2011 fx rates. However this was completed and running in 2011, and uses salts with a starting at about 200 deg C and capping out at 500 deg C (You can have molten salts staring around deg 50C today). I wonder what a project at this scale could achieve a decade later.

But yeah, seems more likely to be PV at this investment price (assuming this will be the total for the project, which I kind of doubt, but I dont know how much costs will inflate to), would be great to get more details about what they are proposing.

[0] http://www.dailymail.co.uk/sciencetech/article-1393879/Gemas...

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by rgbrenner on Thursday March 29, 2018 @02:53AM (#16705057)
I rechecked, and you're right about the price. I must have been looking at a different plant.. not sure, I cant find the page again. I adjusted the numbers in my post. Thanks.
Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by cinquemb on Thursday March 29, 2018 @03:23PM (#16710259)
there's a dead comment from a new account that says this:

"1) regarding price, it's probably PV at those prices, as CSP today comes in at least 2x of PV installed capacity cost and that's taking a very aggressive estimation- although one could probably get CSP costs down to $1/watt with the design and procurement scale economies being talked about. 2) Regarding Venning's point about demand, even with significant amount of energy storage, this would create quite a bit more peak power on sunny days than their current grid demand can handle so announcement may be based on a couple (dodgy to me) assumptions: a) either they assume building it out in phases slowly over time to accompany some aggressive assumed demand growth or b) they are thinking about power exports in a region where Saudi Arabia probably doesn't have too many politically viable customers"

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by bren_dano on Thursday March 29, 2018 @03:50AM (#16705299)
1) regarding price, it's probably PV at those prices, as CSP today comes in at least 2x of PV installed capacity cost and that's taking a very aggressive estimation- although one could probably get CSP costs down to $1/watt with the design and procurement scale economies being talked about. 2) Regarding Venning's point about demand, even with significant amount of energy storage, this would create quite a bit more peak power on sunny days than their current grid demand can handle so announcement may be based on a couple (dodgy to me) assumptions: a) either they assume building it out in phases slowly over time to accompany some aggressive assumed demand growth or b) they are thinking about power exports in a region where Saudi Arabia probably doesn't have too many politically viable customers
Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by venning on Thursday March 29, 2018 @01:20AM (#16704667)
> It would satisfy 10% of the world's demand of electricity.

That doesn't sound right. According to the (better) article from Bloomberg [1], "Saudi Arabia’s electricity generation capacity ... stood at 77 gigawatts in 2016", which that article points out is a third of this new project's.

I don't work in electrical production, but I don't think this capacity will work for 10% of the world. Wikipedia [2] agrees with your assessment of ~2300GW for worldwide average production; but I think the problem is how an average production number is calculated as compared with quoted output numbers for a given installation.

EDIT: Hmm, if Saudi Arabia produces ~3.3% of the world's electricity currently, then maybe this does represent enough for a substantial percentage of the world's population, assuming the production and capacity numbers are comparable. (Deriving 3.3% from 77GW of 2311GW, which I recognize come from different years.) Anyone who knows more about this care to weigh in?

[1] https://www.bloomberg.com/news/articles/2018-03-28/saudi-ara...

[2] https://en.wikipedia.org/wiki/Electricity_generation#Product...

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by jazoom on Thursday March 29, 2018 @04:20AM (#16705416)
But can it power Bitcoin?
Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by joshhart on Thursday March 29, 2018 @01:18AM (#16704659)
According to Wikipedia the worldwide consumption of electricity is about 21k Tera watt hours. That's 21,000,000 gw so it's .001% right? Also I think cost is now about a quarter per watt
Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by philipkglass on Thursday March 29, 2018 @01:45AM (#16704779)
A terawatt hour is a unit of energy. A terawatt, or a gigawatt, is a unit of power. To estimate how many TWh can be generated annually from 200 GW of solar capacity, we need two more numbers:

- The number of hours in a year.

- The percentage of nameplate capacity that the system can be expected to produce on average, e.g. the capacity factor.

There are 8760 hours in a year. A solar PV system in a sunny region may have an annualized capacity factor of 25%. (Installations in really sunny regions may achieve upward of 30%, and Saudi Arabia certainly has a lot of sun, but dust offsets some of the benefits of sunny deserts.)

200 * 8760 * 0.25 = 438000 gigawatt hours of electricity generated per year, e.g. 438 TWh, or about 2% of present annual global electricity generation of 21,000 TWh.

Re:SoftBank Group and Saudi Arabia plan to spend $200B build... by bumblebeard on Thursday March 29, 2018 @01:32AM (#16704722)
Watts measure power, Watt hours measure energy. A 200 GW power plant could output a maximum of ~1,700 TWh in a year which is about 8% of 21,000 TWh.