Learned that one in my first ever project. We mocked up the entire application in Visual Basic (just windows and buttons, no actual functionality implemented, we just wanted to know if it'd work for them) and then the client got really upset when we couldn't come round and install it the next day. Classic case of failing to manage expectations.
I haven't found a way around this other than careful communication, which works with most but not all clients.
Like this: https://media.balsamiq.com/img/examples/wiki-sketch.png
My wife does this kind of interface mockup presentation as part of her job, whenever she does a client presentation she starts with "so this is a screenshot of the inside of my head..."
The first 80% takes 80% of the time. The last 20% takes the remaining 80%.
(Especially for internal tool) Is it possible that what they've seen is, actually, good enough?
Or at least, good enough to solve 90% of the problem while you fill in the missing piece that covers the rest.
Then we have a few people who completely ignore any limitations I put of tools and use them in ways in which they are explicitly not working.
Case-in-point: I created a process that automated a particular task. Said task bears a resemblance to another task, but there are a lot of edge cases in the other task. The manager who runs the second task got upset that I had automated one task but not the other, and complained in a senior staff meeting about this.
I mentioned that the second process was much more complex, and a lot could go wrong if she tried using the new process for it.
Anyways, I took a sick day yesterday, and she had sent an email to me CCing my boss, complaining about how the new process was broken. She had tried changing the settings to work with her process and broken both processes.
She is fully convinced I am just keeping tools from her because I don't like her. The reason she doesn't have any tools is because I have to build the most robust tools possible or she'll break everything, and I can automate 10 other processes with that sort of time.
I'd say that my boss generally makes the right decision when it comes to what is best for the organization, and I'm not in the habit of rewarding people for being abusive.
One of my complaints about working in an environment where I am the only person who can program is that nobody else understands this. I've taken the time to explain this point to people, and they seem to grasp it fairly well, but once they see something that somewhat resembles the final product they get really impatient.
The last 25% of functionality takes far more time than the first 75%, especially once you consider handling edge cases, etc.