-looks at this datacenter-

Well, actually it doesn't.

RAM and Xeons are expensive.

Re:A million-dollar engineering problem by gkop on Thursday March 16, 2017 @07:14PM (#13889998)
So how many does it buy?
Re:A million-dollar engineering problem by tiplus on Friday March 17, 2017 @06:30AM (#13892889)
I would estimate the cost for three years like this:

- 1U single socket Supermicro Xeon E5v4-2630 10core+1GTX1070 GPU = 1500EUR

- operation costs (power+cooling) over 3 years = 1500EUR

- cost of 2 hardware admins 160k/year

- renting local rack space 15EUR/U

This equals about 145 servers for 3 years for us for 1 Million. The setup is highly optimized for _one_ set of data crunching tasks, not DB. We do not need much ram, or network but require a specific CPU/GPU ratio.

Re:A million-dollar engineering problem by geezerjay on Saturday March 18, 2017 @11:57AM (#13901835)
>cost of 2 hardware admins 160k/year

This is by far the most expensive item in your estimate, and I'm sure that you don't suddenly need to hire another pair of admins when you buy a single Xeon blade.

Once you factor this fact in your estimates, you'll realise that the unit cost of each server is, unlike your estimate, negligible.

Re:A million-dollar engineering problem by user5994461 on Friday March 17, 2017 @09:24AM (#13893711)
Let's say 1 Rack of 42 * 1U servers.

That's about the upfront costs of servers ONLY.

Ignoring cooling, all personal costs, electricity, networking gear, network storage and future maintenance.

Re:A million-dollar engineering problem by Aeolun on Friday March 17, 2017 @03:53AM (#13892305)
Approximately 4?