Re:Ask HN: How to Be a Good Technical Lead? by sokoloff on Thursday October 15, 2015 @08:24PM (#10396819)
Be very judicious about how often you put your own delivery on the critical path of the project (or sprint, or other unit of work.)

It shouldn't be very often.

Re:Ask HN: How to Be a Good Technical Lead? by oliyoung on Thursday October 15, 2015 @09:09PM (#10396963)
Yep. You should never ever be on the critical path

1. If you don't deliver and you hold up the schedule, you lose authority as a leader because really … if you can't, then you can't expect others. 2. You WILL be diverted to other tasks that will hold you up

Knowing #2 and still causing #1 is fatal.

Re:Ask HN: How to Be a Good Technical Lead? by hinkley on Thursday October 15, 2015 @11:47PM (#10397363)
My biggest energy expenditure is usually right at the beginning of a release cycle, or even a week or two before it when our process is working correctly (a good process means a boring release week).

We will have figured out some big infrastructure or design issue we need to fix and between requirements meetings we code like hell. Blocking people during week 1 or 2 goes a lot better than week 8 or 17.

Re:Ask HN: How to Be a Good Technical Lead? by kevsim on Monday October 19, 2015 @03:28AM (#10411605)
I've found this to be the single greatest challenge I have as a tech lead. It's incredibly tempting to say "oh, I think I'll have time this week, so I can take that Trello card". If it's on the critical path, leave it for someone else. You won't have time.