While Scrum is a rigidly defined methodology, kanban is less rigidly defined, but the linked article here covers the main difference and provides useful additional links.
The huge overarching difference is this: Scrum is based on timeboxed releases (sprints) into which individual units of work are grouped, while Kanban is flow-based allowing each unit of work that delivers independent business value to proceed independently. This, in theory, eliminates friction that exists in Scrum around managing sprint size/content.
The huge overarching difference is this: Scrum is based on timeboxed releases (sprints) into which individual units of work are grouped, while Kanban is flow-based allowing each unit of work that delivers independent business value to proceed independently. This, in theory, eliminates friction that exists in Scrum around managing sprint size/content.