Re:Poor developer estimates, a.k.a. guesstimation by phillmv on Sunday September 15, 2013 @01:52PM (#6389684)
And even then, large capital projects are routinely wildly off estimates. I think the delta in "how far off we were" just tends to be larger more frequently.
Re:Poor developer estimates, a.k.a. guesstimation by jacques_chester on Sunday September 15, 2013 @08:01PM (#6390855)
In the Industrial Megaprojects book I quoted elsewhere, the single best predictor of every measure of project performance was "Front End Loading" -- how completely the project has been studied and specified before it is funded. There are at least three FEL stages. Companies that muck up FEL-1 are doomed to failure, companies that muck up FEL-2 or FEL-3 are doomed to poor returns.