Re:Poor developer estimates, a.k.a. guesstimation by msluyter on Sunday September 15, 2013 @09:15AM (#6388975)
I've always found this article -- "Evidence Based Scheduling" -- by Joel Spolsky to be rather compelling:

http://www.joelonsoftware.com/items/2007/10/26.html

I'm curious if anyone else has tried it?

Re:Poor developer estimates, a.k.a. guesstimation by jacques_chester on Sunday September 15, 2013 @09:36AM (#6389035)
As part of my research on estimations I've been working through Edward Merrow's book Industrial Megaprojects. It's based in part on a large database of megaprojects that his firm consulted on.

He considers Monte Carlo-based methods to at best pointless, at worst harmful to outcomes (p 324):

    The average megaproject cost estimate when Monte Carlo simulation 
    was used overran by 21 percent, with a standard deviation of 26
    percent and with a sharp right skew. When Monte Carlo simulation 
    was not used, teams were actually more sensitive to basic risks as
    they set contingency.

    ... The use of Monte Carlo simulation has no relationship to success
    of megaprojects or any of our other five figures of merit of projects:
    cost growth, cost competitiveness, schedule slippage, schedule
    competitiveness or production attainment.