We used something a bit like this at IBM years ago. I'm pretty sure we weighted the pessimistic estimate higher than the likely estimate though.
t_{expected} = (t_{optimistic} + 4 \times t_{likely} + t_{pessimistic}) / 6
http://www.codecogs.com/latex/eqneditor.php
This also helps indicate what tasks will take the longest, allowing managers to prioritize based on business needs.