Re:Microsoft blames monster email outage on software defect ... by tacticus on Monday November 16, 2026 @07:40PM (#50525816)
> It’s both, but every grid has a sub-set of power stations with black-start capability

They should have that and they typically pay substantially more for it. Unfortunately it's also the case that the private companies providing said black-start capability may have just not bothered to tell anyone they haven't been able to do it for a few months\years.

Re:Microsoft blames monster email outage on software defect ... by avianlyric on Wednesday November 18, 2026 @07:48AM (#50545682)
Nor should. They absolutely must, otherwise it would be basically impossible to blackstart the grid.

A properly run network will require those facilities to be tested multiple times a year to ensure it actually works, and make payment for the facility contingent on passing those tests.