Like noddingham said, avoiding long distance transmission is one reason. There is a lot of opposition to new electrical transmission projects, which makes them slow and difficult to construct, even in countries that otherwise support renewable energy (like Germany). In the United States, the SunZia transmission line entered operation this year:

https://patternenergy.com/sunzia-comes-online/

It took 3 years to build from start of construction but 20 years from start of planning:

https://en.wikipedia.org/wiki/SunZia_Wind_and_Transmission#H...